Projects · SIGNATUREGLOBAL (INDIA) PRIVATE LIMITED
Signature Global City 63A
Signatureglobal (India) · Sector 63, Gurugram
Registered with RERA: Mar 2022
Is it legal?
- RERA registered, valid till Feb 2027
- HRERA has opened 2 cases of its own against the builder over this project (2 open):
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jul 2024, open)
- Failed to meet registration certificate conditions for SIGNATURE GLOBAL CITY 63A; bank guarantee had expired (Nov 2022, open). At stake: Authority proposed forfeiting bank guarantee and revoking registration; no penalty amount stated
Will it be delivered on time?
- Original deadline Feb 2023, extended 4 times to Feb 2027
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- Done: 7 parts
- In progress: Club 60%, Fixing of children play equipment 0%, Benches 0%, Shopping area 0%, Street lighting / electrification 0%, Treatment and disposal of sewage and sullage water / stp 0%, and 6 more
- Money: ₹118.7 crore spent of ₹118.7 crore (CA certificate, Sep 2026)
What's on offer?
- 72 units: 0 sold, 0 unsold (builder's certificate, Sep 2026)
- Registration now covers 72
- 72 plots, 128–179 sq yd
Location
- Nearest metro: Sector 55–56, 4.7 km by road (15 min by car)
- Cyber City 40 min · Airport 57 min by car at 9:30 am
- Within 3 km: 2 hospitals, 4 schools, 0 malls
The builder: Signatureglobal (India)
- 5 projects registered in Gurugram
- 3 with an occupation certificate on record
- 5 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | SIGNATURE GLOBAL CITY 63A |
|---|
| Builder (promoter) | SIGNATUREGLOBAL (INDIA) PRIVATE LIMITED |
|---|
| Location | VILLAGE KADARPUR SECTOR 63 |
|---|
| RERA project ID | RERA-GRG-1023-2022 |
|---|
| Registration certificate number | GGM/546/278/2022/21 DATED 31.03.2022 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 24/02/2027 |
|---|
| Registered with | HRERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|
| Land area | 5.0125 acres |
|---|
| Licence | 110 OF 2021 DATED 17.12.2021 |
|---|
| Estimated cost of the project | ₹11,866.8 lakh (₹118.67 crore) |
|---|
| Total units (plots, apartments, shops) | 72 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | Not applicable (new project) |
|---|
| Units unsold when registered | Not applicable (new project) |
|---|
| Layout plan approved on | 01-03-2022 |
|---|
| Building plans approved on | Not found in the records checked |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
|---|
| Latest report submitted on | 14-Oct-2026 |
|---|
| Quarterly reports listed on the portal | 17 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹0 |
|---|
| Units in the project (apartments / plots) | 0.00 apartments, 72.00 plots |
|---|
| Sold in the quarter | 0 plots |
|---|
| EDC (development charges): paid / due as on date | ₹598.38 lakh (₹5.98 crore) paid; ₹0 due |
|---|
| Approvals listed | Not found in the records checked |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026, for 30 Sep 2026 |
|---|
| By part | - 72 Nos. (Plots): Sub-structure: excavation in ordinary soil done, RCC of building raft done, water proofing compound being applied. Super-structure: 0% of RCC works completed on total area, working in progress at stilt/ground floor.
- Internal roads & pavements: 100%
- Water supply: 100%
- Sewerage (chamber, lines, septic tanks, STP): 100%
- Storm water drains: 100%
- Landscaping & tree plantation: 100%
- Parks and playgrounds: 100%
- Fixing of children play equipment: 0%
- Benches: 0%
- Shopping area: 0%
- Street lighting / electrification: 0%
- Treatment and disposal of sewage and sullage water / STP: 0%
- Solid waste management & disposal: 0%
- Energy management (solar): 0%
- Fire protection and fire safety requirements: 0%
- Electrical meter room, sub-station, receiving station: 0%
- Site office (temporary): 100%
- Marketing office (temporary): 0%
- Community centre: 0%
- Club: 60%
|
|---|
| Unclear in the certificate | - Table A work-done value and percentage columns are blank (shown as dashes), so no overall percentage is given for the plots.
- The super-structure table states 148 Nos. total floors in the tower/building/plots, while Table A lists 72 Nos. (Plots). The document does not explain the difference.
- Table B, the common areas table, gives percentages for several items, but the stated percentages do not add up to one overall figure.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | - Extension 08 of 2023 dated 17 Apr 2023: registration extended from 28 Feb 2023 to 27 Feb 2024. Conditions include: The promoter shall offer to execute and register a conveyance deed in favour of the allottees for their unit or apartment, along with parking if applicable.; Any increase in taxes, charges, fees or levies after the scheduled completion date, including extension periods granted by the Authority, shall not be charged to the allottees.; This extension is granted without prejudice to allottees' rights under section 18, as the promoter has not shown reasonable circumstances and fault-free reasons for failing to complete the project in the timeline declared under section 7(2)(1)(c).; The promoter must comply with the Act, the rules and regulations, and any other applicable law.; If these conditions are not met, the Authority may take action, including revoking the registration.
- Extension dated 09 Jul 2024: registration extended from 27 Feb 2024 to 26 Feb 2025. Conditions include: Registration is valid from 28 Feb 2024 to 26 Feb 2025 and stays in force subject to the conditions listed.; The promoter paid a penalty of Rs. 25 lakhs for violation of sections 3 and 4 of the Act before the certificate was issued.; The promoter must pay delay possession charges under section 18(1) from its own funds. Project cash inflow must not be used for this.; Allottees' rights to delay possession charges or withdrawal under section 18(1) are not affected by this registration.; The promoter must not accept more than ten percent of the cost as advance or application fee without first signing a written agreement for sale.; The project sale is on carpet area basis, and the total sale consideration includes all charges. No separate EDC/IDC is payable except the total sale consideration.; The promoter must enable formation of an association of allottees within three months of the majority of allottees booking.; The promoter must not start any subvention or assured return scheme without prior approval of the Authority.; Individual possession dates in buyer agreements already signed are not to change if they are earlier than the DPI date.; The promoter must submit a monthly comparison of proposed and actual work on the 7th of each month.; The completion period declared is 26 Feb 2025. Some licences and approvals may expire within that period, and the promoter must renew them on time.; The Authority may cancel the registration if quarterly progress report obligations are not met.
- Extension 2 of 2022 (registration no. 21 of 2022); extended under section 7(3) vide reg. no. 2 of 2022/7(3)/48/2024/07 dated 26 Jun 2025: registration extended from 28 Feb 2023 to 28 Feb 2026. Conditions include: The registration is granted under section 7(3) of the Real Estate (Regulation & Development) Act, 2016 for the project Signature Global City 63A, Sector 63A, Gurugram.; Total saleable units for registration are stated as 72 plots.; The promoter shall enter into agreements for sale in the prescribed form and offer the allottee the unit/plot as per section 17.; The promoter shall not sell on a super area basis; the apartment or building shall be sold only on a carpet area basis.; The promoter shall not accept more than ten percent of the cost of the plot as advance payment without first entering into a written agreement for sale, as per section 13(1).; The Authority has directed the promoter to take approvals and renewals within time; failure will invite stringent action.; The promoter must submit a monthly comparison of proposed work against actual work on the 7th day of every consecutive month.; The promoter has paid a penalty of Rs 25 lakhs for violation of sections 5 and 4 of the Act, as recorded in the document.; The promoter must not create any encumbrance on future receivables from sold units or on the separate RERA accounts.; The promoter must complete the project within the validity of the licence; the project is declared to be completed by 25.02.2026 and the promoter is directed to take steps accordingly.; Common areas and the monitoring commissioner provisions apply as per the Act; any cost of statutory approvals must be met from the promoter's own funds.
- Extension 08 of 2023 (dated 17 Apr 2023) is the only extension listed in the history; this document is Registration No. 21 of 2022/7(3)/48/2024/07 dated 10 Aug 2026: registration extended from 25 Feb 2026 to 24 Feb 2027. Conditions include: The promoter must sign agreements for sale with allottees as prescribed in the HRERA Rules, 2017.; Apartments or buildings are sold on carpet area basis, and the total sale price includes all charges. No separate EDC/IDC is payable beyond the total sale consideration.; The promoter must not accept more than ten percent of the cost as advance payment without first entering a registered written agreement for sale.; The promoter must form an association of allottees within three months of the majority of allottees booking their units.; Individual possession dates in already signed agreements will not change if they fall before the date in the detailed project information.; The registration does not affect allottees' rights to delay possession charges under section 18(1). The promoter undertakes to pay these charges and not use project cash inflow for this purpose.; The promoter must not create further charges on future receivables from sold units or separate RERA accounts, except the existing charge in favour of the lender.; The promoter has declared project completion by 24 Feb 2027, and some licences and approvals will expire before then. Failure to renew approvals on time may invite stringent action.; The Authority reserves the right to start penal proceedings for violations of the Act, rules and regulations.
|
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 2 |
|---|
| By status | First Hearing: 1; Pending: 1 |
|---|
| Proceedings | |
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|
| Decided cases against SIGNATUREGLOBAL (INDIA) PRIVATE LIMITED (all its projects) | 5 (Complaint: 5) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in