Signature Global City 79B

Jmk Holdings · Sector 79B, Gurugram

Registered with RERA: Dec 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Jmk Holdings

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSIGNATURE GLOBAL CITY 79B
Builder (promoter)JMK HOLDINGS PVT. LTD.
LocationVILLAGE, NAUNGRANPUR, SECTOR- 79B GURUGRAM, HARYANA
RERA project IDRERA-GRG-1200-2022
Registration certificate numberGGM/656/388/2022/131 DATED 23.12.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to27/04/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area12.4875 acres
Licence100 OF 2022 Dated 25-7-2022
Estimated cost of the project₹17,933.48 lakh (₹179.33 crore)
Total units (plots, apartments, shops)194
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on14-10-2022
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-11-2022
Likely completion date30-04-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on14-Oct-2026
Quarterly reports listed on the portal15

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹176.64 lakh (₹1.77 crore)
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹176.64 lakh (₹1.77 crore)
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)0.00 apartments, 194.00 plots
Sold in the quarter0 plots
EDC (development charges): paid / due as on date₹1,490.73 lakh (₹14.91 crore) paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 14-10-2022
  • Demarcation Plan: Obtained Approval 14-10-2022
  • Zoning Plan: Obtained Approval 14-10-2022

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for 30 Sep 2026
By part
  • 194 Nos. (Plots), Table A: Excavation done and raft RCC of building done. 0% of RCC works completed on total area. 0% to 10% of slabs laid. Walls, staircase, lift wells, MEP internal works and finishing yet to be started. Percentage column left blank for most items.
  • Internal roads & pavements (temporary): 96%
  • Parking: 80%
  • Water supply: 100%
  • Sewerage (chamber, lines, septic tanks, STP): 100%
  • Storm water drains: 100%
  • Landscaping & tree plantation (temporary): 90%
  • Parks and playgrounds: 0%
  • Fixing of children play equipment: 0%
  • Benches: 0%
  • Shopping area: 0%
  • Street lighting/electrification: 0%
  • Treatment and disposal of sewage and sullage water/STP: 0%
  • Solid waste management & disposal: 0%
  • Energy management (solar): 0%
  • Fire protection and fire safety requirements: 0%
  • Electrical meter room, sub-station, receiving station: 0%
  • Site office (temporary): 100%
  • Marketing office (temporary): 100%
  • Community centre: 0%
Unclear in the certificate
  • Table A gives no overall percentage figure for the building or tower; the percentage column is blank or shows a dash for most items.
  • Table A lists 776 Nos. as total floors but the tower/block label is given only as 194 Nos. (Plots); the link between the two is not clear.
  • Slab progress is stated only as a range (0% to 10%).
  • Table B item numbering repeats item 17; the water conservation item is marked No with no percentage.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusPending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against JMK HOLDINGS PVT. LTD. (all its projects)1 (Complaint: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in