Projects · STERNAL BUILDCON PRIVATE LIMITED
Signature Global City 81
Sternal Buildcon · Sector 81, Gurugram
Registered with RERA: Jul 2021
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Jun 2026)
- HRERA has opened 2 cases of its own against the builder over this project (1 open, 1 closed):
- Did not submit the quarterly progress report (May 2022, open)
- Submitted approved service plans and estimates 86 days late (due 25 Oct 2021) (Jun 2022, closed). At stake: Rs 10,000 per day proposed, capped at five percent of project cost; none imposed
- 28 complaints about this project decided by HRERA since Nov 2023 (27 delay interest ordered, 1 refund ordered)
Will it be delivered on time?
- Original deadline Jun 2023, extended 3 times to Jun 2026
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- Done: Site office
- In progress: Treatment and disposal of sewage and sullage water / stp 99%, Internal roads & pavements 95%, Sewerage 95%, Storm water drains 95%, Landscaping & tree plantation 95%, Community centre 90%, and 11 more
- Money: ₹128.7 crore spent of ₹128.4 crore (CA certificate, Sep 2026)
What's on offer?
- 209 units: 0 sold, 0 unsold (builder's certificate, Sep 2026)
- Registration now covers 1209 plots
- 209 plots, 81–176 sq yd
Location
- Nearest metro: IFFCO Chowk, 6.9 km by road (25 min by car)
- Cyber City 37 min · Airport 43 min by car at 9:30 am
- Within 3 km: 53 hospitals, 9 schools, 0 malls
Location shown for Sector 81; the exact site was not found.
The builder: Sternal Buildcon
- 7 projects registered in Gurugram, 2 lapsed
- 1 with an occupation certificate on record
- 64 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | SIGNATURE GLOBAL CITY 81 |
|---|
| Builder (promoter) | STERNAL BUILDCON PRIVATE LIMITED |
|---|
| Location | VILLAGE NAKHDOLA, SECTOR 81 |
|---|
| RERA project ID | RERA-GRG-880-2021 |
|---|
| Registration certificate number | GGM/477/209/2021/45 DATED 27.07.2021 |
|---|
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 27/06/2026 |
|---|
| Registered with | HRERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|
| Land area | 11.9778 acres |
|---|
| Licence | 07 of 2021 dated 05.03.2021 Endst. No. LC-4222/Asstt.(MS)/2021/5797 Dated 08.03.2021 |
|---|
| Estimated cost of the project | ₹12,745.06 lakh (₹127.45 crore) |
|---|
| Total units (plots, apartments, shops) | 209 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | Not applicable (new project) |
|---|
| Units unsold when registered | Not applicable (new project) |
|---|
| Layout plan approved on | 05-03-2021 |
|---|
| Building plans approved on | Not found in the records checked |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
|---|
| Latest report submitted on | 14-Oct-2026 |
|---|
| Quarterly reports listed on the portal | 20 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹11 lakh (₹0.11 crore) |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹11 lakh (₹0.11 crore) |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹0 |
|---|
| Units in the project (apartments / plots) | 0.00 apartments, 209.00 plots |
|---|
| Sold in the quarter | 0 plots |
|---|
| EDC (development charges): paid / due as on date | ₹1,462 lakh (₹14.62 crore) paid; ₹0 due |
|---|
| Approvals listed | - Layout Plan: Obtained Approval 05-03-2021
- Demarcation Plan: Obtained Approval 12-03-2021
- Zoning Plan: Obtained Approval 20-04-2021
- Service Plans: Obtained Approval 20-04-2021
- Electricity Plans: Obtained Approval 24-03-2021
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026, for 30 Sep 2026 |
|---|
| By part | - Plots (209 Nos.) - Table A: Table A values shown as dashes (nil). Excavation in ordinary soil done, RCC of building raft done, water proofing compound being applied. Super-structure: 0% of RCC works on total area, yet to be started.
- Internal roads & pavements (temporary): 95%
- Parking: 78%
- Water supply: 85%
- Sewerage (chamber, lines, septic tanks, STP): 95%
- Storm water drains: 95%
- Landscaping & tree plantation (temporary): 95%
- Parks and playgrounds: 38%
- Fixing of children play equipment: 0%
- Benches: 0%
- Shopping area: 0%
- Street lighting / electrification: 85%
- Treatment and disposal of sewage and sullage water / STP: 99%
- Solid waste management & disposal: not stated
- Energy management (solar): 0%
- Fire protection and fire safety requirements: 0%
- Electrical meter room, sub-station, receiving station: 0%
- Site office: 100%
- Community centre: 90%
- Club: 65%
|
|---|
| Unclear in the certificate | - Table A work values and percentages are shown as dashes, not as figures.
- Percentage for solid waste management & disposal is shown as a dash.
- Total number of floors field is blank (only 'Nos' printed).
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | - Extension 14 of 2023 dated 19 Jun 2023: registration extended from 30 Jun 2023 to 29 Jun 2024. Conditions include: The promoter shall submit a copy of the occupation certificate, copy of application and attached documents, deed of declaration and enclosed documents.; The promoter shall offer to execute and register a conveyance deed in favour of the allottee(s) for the unit/apartment along with parking (if applicable).; If taxes, charges, fees or levies increase after the scheduled completion date as per the registration, the same shall not be charged from the allottees.; This extension is granted without prejudice to the rights of allottees under section 18, as the promoter failed to prove reasonable circumstances and without fault to complete the project in the timeline declared under section 4(2)(l)(c).; The promoter shall comply with the provisions of the Act and the rules and regulations made thereunder.; The promoter shall not contravene the provisions of any other law for the time being in force as applicable to the project.; If the above conditions are not fulfilled, the Authority may take necessary action against the promoter, including revoking the registration.
- Extension 14 of 2023 (earlier extension referenced); current certificate is registration no. 45 of 2021 under section 7(3) dated 09 Jul 2024: registration extended from 29 Jun 2024 to 28 Jun 2025. Conditions include: Registration granted under section 7(3) on the basis of the promoter's information and a detailed project information (DPI) annexed to the certificate.; The promoter must enter into agreements for sale in the prescribed form and offer conveyance deeds to allottees as per section 17.; The promoter must deposit 100% of amounts realised from allottees in a separate account to cover construction and proportionate land cost.; The sale is on a carpet area basis and the total sale consideration must include all charges; no separate EDC/IDC is payable beyond the total sale consideration.; The promoter may not accept more than ten percent of the cost as advance or application fee before a registered agreement for sale is signed (section 13(1)).; The promoter must pay delay possession charges under section 18(1) from its own funds and project cash inflow may not be used for this.; The promoter has deposited a penalty of Rs. 25 lakhs for violation of sections 3 and 4 of the Act before issuance of this certificate.; The promoter must submit quarterly progress reports and monthly comparison of proposed and actual work (PERT chart) on the 7th of every month.; The promoter must not create further encumbrance on future receivables or RERA accounts except the existing charge in favour of existing lenders.; The promoter must renew licences and approvals when due; a few licences/approvals are expected to expire within the project completion period.; The Authority may appoint a Commissioner Monitoring and may withdraw or cancel the registration if conditions are not met.; Sale through real estate agents is allowed only if the agent is registered with HARERA and the brochure and drawings are available.; No subvention or assured return scheme may be run without prior approval of the Authority.
- Extension 14 of 2023 and 08 of 2024 (continuation), with a further extension granted by the Authority vide order dated 07.07.2025 dated 22 Jul 2025: registration extended from 27 Jun 2026 to 27 Jun 2026. Conditions include: Promoter must sell only on carpet area basis, with total sale consideration inclusive of all charges; no separate EDC/IDC payable by allottees beyond the total sale consideration.; Permission to remain in force is without prejudice to allottees' rights under section 18(1) for delay possession charges; promoter must pay delay possession charges from its own funds, not project cash inflow.; Promoter must deposit 100% of amounts collected from allottees in a separate schedule bank account for construction and land cost.; Authority imposed a penalty of Rs. 25 lakhs for violation of section 4(2)(l)(c); promoter deposited it on 08.07.2025 before issue of this certificate.; Promoter must not create further encumbrance on future receivables from sold units or on separate RERA accounts, except the existing lender charge.; Promoter must complete community sites within the declared completion period, and must obtain renewals/approvals on time; failure may invite stringent action.; Promoter must submit quarterly progress reports and monthly comparison of planned versus actual work (PERT chart) on the 7th of each month.; Authority may revoke registration under section 7 if conditions are not met.
|
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 2 |
|---|
| By status | First Hearing: 1; Disposed: 1 |
|---|
| Proceedings | - RERA-GRG-3663-2022: Show cause notice issued by the Authority to the promoter for not submitting the quarterly progress report Status: First hearing scheduled for 27 Jun 2022; the case page shows the status as FIRST HEARING with no order yet uploaded. Latest: 27 Jun 2022, First hearing fixed at 11.00 am at the HARERA Gurugram office, where the promoter was asked to appear with a written reply if it had anything to say. The case page lists the proceedings as First Hearing with no order uploaded.
- RERA-GRG-4476-2022: Suo motu proceeding by the Authority against the promoter M/s Sternal Buildcon Pvt Ltd for not submitting required approvals on time for the registered affordable plotted colony project Signature Global City 81, Sector 81, Gurugram (registration GGM/477/209/2021/45 dated 27.07.2021). The Authority issued a show cause notice for revocation of registration and proposed a penalty. Status: Disposed. The case was filed by order dated 05 Jan 2026 because the promoter had complied with the registration conditions, albeit late, and revocation did not seem justified. Latest: 05 Jan 2026, The Authority decided the matter. Since the promoter had now complied, though with delay, revocation of registration did not seem justified and the case was filed. Penalty: A penalty of Rs. 10,000 per day under Section 63 of the Act, cumulatively up to five percent of the estimated project cost, was proposed in the show cause notice. The final order does not state that any penalty was imposed. Outcome: Case filed. Revocation of the registration certificate was not ordered because the promoter had complied with the conditions, though late.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 28 |
|---|
| Cases | - RERA-GRG-4267-2025 (complaint, decided 29-Sep-2026): Buyer sought possession and compensation for delay; builder ordered to pay 10.80% interest and cancellation notice set aside.
- RERA-GRG-4268-2025 (complaint, decided 29-Sep-2026): Buyer sought possession and compensation for delay; builder ordered to pay 10.80% interest and cancellation set aside.
- RERA-GRG-5349-2025 (complaint, decided 25-Aug-2026): Buyer sought delay possession charges; builder ordered to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-5363-2025 (complaint, decided 25-Aug-2026): Buyer sought delay possession charges; builder ordered to pay 10.80% interest from 28 Feb 2024 due date.
- RERA-GRG-5317-2025 (complaint, decided 25-Aug-2026): Buyer sought delay compensation for late possession; cancellation set aside and builder ordered to pay 10.80% interest on amount paid.
- RERA-GRG-5322-2025 (complaint, decided 25-Aug-2026): Buyers sought delay possession charges; builder ordered to pay 10.80% interest from 28 Feb 2024 till possession.
- RERA-GRG-4321-2025 (complaint, decided 11-Aug-2026): Buyers sought delay interest after possession was late; builder ordered to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-5091-2025 (complaint, decided 11-Aug-2026): Buyer sought delay compensation for possession due 28 Feb 2024; builder ordered to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-5369-2025 (complaint, decided 11-Aug-2026): Buyer sought possession and delay interest; builder ordered to pay 10.80% delay interest and execute conveyance deed.
- RERA-GRG-3280-2025 (complaint, decided 17-Jul-2026): Buyer sought possession after delay past 28 Feb 2024; builder ordered to pay 10.80% interest and hand over possession.
- RERA-GRG-145-2026 (complaint, decided 17-Jul-2026): Buyer sought delay interest for late possession; builder ordered to pay 10.80% interest from Feb 2024 to Nov 2024 and hand over unit.
- RERA-GRG-3770-2025 (complaint, decided 19-May-2026): Buyer bought unit after possession was late; builder ordered to pay 10.80% interest for delay until 28 Nov 2024.
- RERA-GRG-4022-2025 (complaint, decided 19-May-2026): Buyers sought possession and delay compensation; HRERA ordered builder to pay 10.80% delay interest from 28 Feb 2024 until possession.
- RERA-GRG-4326-2025 (complaint, decided 19-May-2026): Buyer sought possession and delay charges; builder ordered to pay 10.80% delay interest and execute conveyance deed.
- RERA-GRG-3674-2025 (complaint, decided 19-May-2026): Buyer sought possession after delay; builder ordered to pay 10.80% delay interest and execute conveyance deed.
- RERA-GRG-3845-2025 (complaint, decided 19-May-2026): Buyer sought possession and delay compensation; builder ordered to pay 10.80% interest on amount paid from 28 Feb 2024.
- RERA-GRG-4371-2025 (complaint, decided 19-May-2026): Buyer sought possession and delay charges; builder ordered to pay 10.80% interest on paid amount from 28 Feb 2024.
- RERA-GRG-4015-2025 (complaint, decided 19-May-2026): Buyer sought possession and delay interest; builder ordered to pay 10.80% interest on amount paid, deliver conveyance deed.
- RERA-GRG-3864-2025 (complaint, decided 19-May-2026): Buyer sought possession and delay charges; builder ordered to pay 10.80% interest from Feb 2024 and register deed.
- RERA-GRG-4002-2025 (complaint, decided 23-Apr-2026): Buyer sought delay possession charges; builder ordered to pay 10.80% interest on amount paid for the delay period.
- RERA-GRG-3812-2025 (complaint, decided 13-Feb-2026): Buyer sought possession and delay interest; builder ordered to pay 10.80% interest and hand over possession after dues.
- RERA-GRG-3809-2025 (complaint, decided 13-Feb-2026): Buyer sought possession and delay interest; builder ordered to pay 10.80% interest on amount paid for delay.
- RERA-GRG-4673-2025 (complaint, decided 13-Feb-2026): Buyer sought possession with interest after delay; builder ordered to pay 10.80% interest on paid amount and give possession.
- RERA-GRG-3041-2025 (complaint, decided 13-Feb-2026): Buyer sought delay interest after possession due 28 Feb 2024; builder ordered to pay 10.80% interest.
- RERA-GRG-4670-2025 (complaint, decided 30-Jan-2026): Buyer's unit cancelled after possession delay; HRERA set cancellation aside and ordered builder to pay 10.80% interest.
- RERA-GRG-4196-2025 (complaint, decided 13-Jan-2026): Buyer sought delay possession charges after possession due 28 Feb 2024; builder ordered to pay 10.80% interest on amount paid.
- RERA-GRG-1007-2025 (complaint, decided 08-Jan-2026): Buyer sought delay interest and possession after 2-year delay; builder ordered to pay 10.80% interest and hand over the unit.
- RERA-GRG-2353-2024 (complaint, decided 28-May-2025): Buyer sought delay possession charges after due date passed; HRERA ordered builder to pay 11.10% interest on amount paid and hand over possession.
|
|---|
| Decided cases against STERNAL BUILDCON PRIVATE LIMITED (all its projects) | 64 (Complaint: 64) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in