Signature Global City 92-2

Signature Infrabuild · Sector 92, Gurugram

Registered with RERA: Jan 2023

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for Sector 92; the exact site was not found.

The builder: Signature Infrabuild

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSIGNATURE GLOBAL CITY 92-2
Builder (promoter)SIGNATURE INFRABUILD PVT. LTD.
LocationVILLAGE MEVKA, WAZIRPUR, SECT OR-92, GURUGRAM
RERA project IDRERA-GRG-1221-2022
Registration certificate numberGGM/664/396/2023/08 DATED 13.01.2023
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to28/03/2026
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area8.3125 acres
Licence81 of 2022 dated 24.06.2022
Estimated cost of the project₹11,118.42 lakh (₹111.18 crore)
Total units (plots, apartments, shops)197
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on28-06-2022
Building plans approved on27-10-2022

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-01-2023
Likely completion date30-03-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on14-Oct-2026
Quarterly reports listed on the portal14

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)0.00 apartments, 197.00 plots
Sold in the quarter0 plots
EDC (development charges): paid / due as on date₹968.9 lakh (₹9.69 crore) paid; ₹0.03 lakh (₹0 crore) due
Approvals listed
  • Layout Plan: Obtained Approval 28-06-2022
  • Demarcation Plan: Obtained Approval 28-06-2022
  • Zoning Plan: Obtained Approval 28-06-2022
  • Service Plans: Obtained Approval 28-09-2022

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for 30 Sep 2026
By part
  • Super structure: 0%, 0% of RCC works completed on total area
  • Internal roads & pavements: 15%
  • Water supply: 25%
  • Sewerage (chamber, lines, septic tanks, STP): 85%
  • Storm water drains: 85%
  • Landscaping & tree plantation: 60%
  • Parks and playgrounds: 25%
  • Fixing of children play equipment: 0%
  • Benches: 0%
  • Shopping area: 0%
  • Street lighting/ electrification: 0%
  • Treatment and disposal of sewage and sullage water/ STP: 0%
  • Solid waste management & disposal: 0%
  • Energy management (solar): 0%
  • Fire protection and fire safety requirements: 0%
  • Electrical meter room, sub-station, receiving station: 0%
  • Site Office: 100%
  • Community centre: 0%
Unclear in the certificate
  • Table A percentages for sub-structure, super-structure, MEP and finishing are shown as dashes, so no figures are given there.
  • Water conservation, rain water harvesting item has no percentage entered.
  • Table A refers to 197 plots, with no separate tower or building names or progress figures.
  • No single overall percentage of construction completed is stated in the certificate.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed2
By statusFirst Hearing: 1; Re-Open/Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project2
Cases
Decided cases against SIGNATURE INFRABUILD PVT. LTD. (all its projects)78 (Complaint: 78)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in