Projects · SIGNATURE INFRBUILD PVT. LTD.
Signature Global City 92
Signature Infrbuild · Sector 92, Gurugram
Registered with RERA: Jul 2021
Is it legal?
- RERA registered, valid till Apr 2026 (date has passed)
- HRERA has opened 4 cases of its own against the builder over this project (4 open):
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jul 2024, open)
- Did not submit its quarterly progress report (Jun 2022, open)
- Did not submit its quarterly progress report (open)
- 1 more case: reply 4
- 2 complaints about this project decided by HRERA since Nov 2023 (1 delay interest ordered, 1 compensation ordered)
Will it be delivered on time?
- Original deadline Apr 2023, extended 3 times to Apr 2026
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- Done: Sewerage, Storm water drains, Parks and playgrounds, Treatment and disposal of sewage and sullage water/stp, Site office
- In progress: Internal roads & pavements 95%, Parking 95%, Water supply 95%, Landscaping & tree plantation 95%, Street lighting/electrification 95%, Club 70%, and 7 more
- Money: ₹129.4 crore spent of ₹129.2 crore (CA certificate, Sep 2026)
What's on offer?
- 157 units: 0 sold, 0 unsold (builder's certificate, Sep 2026)
- Registration now covers 157 residential plots and 2 commercial plots
- 191 plots, 84–212 sq yd
Location
- Nearest metro: Millennium City Centre Gurugram, 22.9 km by road (58 min by car)
- Cyber City 64 min · Airport 49 min by car at 9:30 am
- Within 3 km: 0 hospitals, 0 schools, 0 malls
Location shown for Sector 92; the exact site was not found.
The builder: Signature Infrbuild
- 2 projects registered in Gurugram
- 0 with an occupation certificate on record
- 2 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | SIGNATURE GLOBAL CITY 92 |
|---|
| Builder (promoter) | SIGNATURE INFRBUILD PVT. LTD. |
|---|
| Location | VILLAGE MEVKA, WAZIRPUR, SECT OR-92, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-860-2021 |
|---|
| Registration certificate number | GGM/470/202/2021/38 DATED 27.07.2021 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 27/04/2026 |
|---|
| Registered with | HRERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|
| Land area | 10.30 acres |
|---|
| Licence | 12 of 2021 dated 12.03.2021 Endst. No. LC-4248/Asstt.(MS)/2021/6671 Dated 15/03/2021 |
|---|
| Estimated cost of the project | ₹10,754.28 lakh (₹107.54 crore) |
|---|
| Total units (plots, apartments, shops) | 191 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | Not applicable (new project) |
|---|
| Units unsold when registered | Not applicable (new project) |
|---|
| Layout plan approved on | 01-05-2021 |
|---|
| Building plans approved on | Not found in the records checked |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
|---|
| Latest report submitted on | 14-Oct-2026 |
|---|
| Quarterly reports listed on the portal | 20 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹0 |
|---|
| Units in the project (apartments / plots) | 0.00 apartments, 157.00 plots |
|---|
| Sold in the quarter | 0 plots |
|---|
| EDC (development charges): paid / due as on date | ₹1,200.8 lakh (₹12.01 crore) paid; ₹0.05 lakh (₹0 crore) due |
|---|
| Approvals listed | - Layout Plan: Obtained Approval 12-03-2021
- Demarcation Plan: Obtained Approval 12-03-2021
- Zoning Plan: Obtained Approval 20-04-2021
- Service Plans: Obtained Approval 08-04-2021
- Electricity Plans: Obtained Approval 03-05-2021
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026, for 30 Sep 2026 |
|---|
| By part | - Building/Tower (157 plots) - Table A: Excavation in ordinary soil done; RCC of building raft done; water proofing compound being applied; walls, slabs and superstructure yet to be started
- Internal roads & pavements: 95%
- Parking: 95%
- Water supply: 95%
- Sewerage (chamber, lines, septic tanks, STP): 100%
- Storm water drains: 100%
- Landscaping & tree plantation: 95%
- Parks and playgrounds: 100%
- Fixing of children play equipment: 0%
- Benches: 0%
- Shopping area: 0%
- Street lighting/electrification: 95%
- Treatment and disposal of sewage and sullage water/STP: 100%
- Solid waste management & disposal: 0%
- Energy management (solar): 0%
- Fire protection and fire safety requirements: 0%
- Electrical meter room, sub-station, receiving station: 0%
- Site Office: 100%, Temporary
- Club: 70%
|
|---|
| Unclear in the certificate | - Table A percentage and value cells show dashes only, so no percentage is certified for the building/tower work items.
- Community centre (Table B) is marked Yes but has no percentage given.
- Table B water conservation (rain water harvesting) is marked No and has no percentage.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | - Extension 13 of 2023 dated 19 Jun 2023: registration extended from 30 Apr 2023 to 29 Apr 2024. Conditions include: The promoter shall submit copies of the occupation certificate, OC application, deed of declaration and enclosed documents.; The promoter shall offer to execute and register a conveyance deed in favour of allottees for the unit, along with parking if applicable.; If taxes, charges, fees or levies increase after the scheduled completion date, the increase shall not be charged from allottees.; The extension is granted without prejudice to allottees' rights under section 18, as the promoter has not shown reasonable circumstances and fault-free delay in completing the project within the declared timeline.; The promoter shall comply with the Act and the rules and regulations made under it.; The promoter shall not contravene any other law in force that applies to the project.; If the conditions are not fulfilled, the Authority may take action against the promoter, including revoking the registration.
- Extension 13 of 2023 dated 08 Aug 2024: registration extended from 29 Apr 2024 to 28 Apr 2025. Conditions include: The promoter must deposit 100% of amounts realised from allottees in a separate account to cover construction and proportionate land cost, used only for that purpose.; The promoter must pay delay possession charges to allottees under section 18(1) from its own funds. Project cash inflow cannot be used for this.; The promoter paid a penalty of Rs. 25,00,000 for violation of sections 3 and 4 of the Act, by reference dated 29 Jul 2024.; The promoter must not accept more than ten percent of the cost as advance or application fee without a written agreement for sale, as per section 13(1).; No subvention or assured return scheme may be run for the registered project without prior approval of the Authority.; The promoter must submit a monthly comparison of projected and actual work completed, and give an affidavit on compliance, as directed by the Authority.; The promoter must not create further encumbrance on future receivables from sold units or on the separate RERA accounts, except the existing lender's charge.; Registration may be revoked if the conditions are not met, as per the Act and rules.
- Extension 13 of 2024 dated 13 Aug 2025: registration extended from 28 Apr 2025 to 27 Apr 2026. Conditions include: The promoter must deposit 100% of the amounts collected from allottees in a separate account, to be used only for construction and the proportionate land cost.; The promoter paid a penalty of Rs. 25 lakhs for violating sections 3 and 4 of the Act, before this certificate was issued.; The registration remains without prejudice to allottees' rights to delay possession charges under section 18(1) of the Act.; The promoter must pay delay possession charges under section 18(1) from its own funds; project cash inflow shall not be used for this purpose.; No subvention or assured return scheme may be run for the project without the Authority's prior approval.; The promoter must not accept more than ten percent of the plot cost as advance payment before entering a written agreement for sale.; The promoter must form an association of allottees within three months of the majority of allottees taking possession.; Some licenses and approvals may expire before the project completion date, and the promoter must renew them on time.; The Authority may take action, including revoking registration, if the conditions are not met.
|
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 4 |
|---|
| By status | First Hearing: 4 |
|---|
| Proceedings | - RERA-GRG-3361-2024: Suo motu monitoring of Signature Global City 92 by Signature Infrabuild Pvt Ltd over an expired registration certificate, alleged violation of Section 4(2)(l)(C) of the RERA Act 2016 Status: First hearing held on 09 Aug 2024. The promoter's representative said continuation was approved on 24 Jul 2024, valid up to 28 Apr 2025, and asked for the notice to be dropped. The Authority directed the matter to be put up on file. Latest: 09 Aug 2024, First hearing held. The promoter's representatives attended. The promoter's representative stated that continuation of registration was approved on 24 Jul 2024, valid up to 28 Apr 2025, and requested that the notice be dropped. The Authority directed the matter to be put up on file.
- RERA-GRG-3657-2022: Show cause notice to the promoter for not submitting a quarterly progress report, started by the Authority against Signature Infrbuild Pvt. Ltd. Status: The case is at its first hearing stage. The page shows a hearing listed for 27 Jun 2022. No order or outcome is recorded on the page. The complaint has not yet been dispatched. Latest: 27 Jun 2022, First hearing was listed. The Authority issued a show cause notice to the promoter for non-submission of its quarterly progress report. The promoter was asked to appear before the Authority at 11.00 am on 27 Jun 2022 at the HARERA Gurugram office, with a written reply if it had anything to say.
- RERA-GRG-3658-2022: Show cause notice to the promoter, Signature Infrabuild Pvt. Ltd., for not submitting its quarterly progress report. The Authority asked the promoter to explain in writing and appear for a hearing. Status: First hearing listed for 27 Jun 2022. The case page shows the status as First Hearing, with no order text recorded. Latest: 27 Jun 2022, First hearing listed at 11.00 am at the HARERA Gurugram office, where the promoter was asked to appear with a written reply. The listing status is First Hearing, with no proceedings or order recorded.
- RERA-GRG-4463-2022: A project RC compliance hearing involving SIGNATURE INFRBUILD PVT. LTD., listed on HRERA Gurugram's record. The case page shows the matter was received as a new complaint on 11 Jun 2022, and the Authority is named in the party field. Status: First hearing listed for 01 Jul 2022. The page does not show a hearing outcome or order. Latest: 01 Jul 2022, First hearing was listed. The proceedings field shows only 'FIRST HEARING', with no order recorded.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 2 |
|---|
| Cases | |
|---|
| Decided cases against SIGNATURE INFRBUILD PVT. LTD. (all its projects) | 2 (Complaint: 2) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in