Projects · SIGNATUREGLOBAL (INDIA) PRIVATE LIMITED
Signature Global Imperial
Signatureglobal (India) · Sector 88A, Gurugram
Registered with RERA: Mar 2022
Is it legal?
- RERA registered, valid till Feb 2027
- HRERA opened a case of its own against the builder in Nov 2022 (still open):
- Why: missed registration conditions: service estimates, plans, revised LC-IV, escrow agreement; environmental clearance 149 days late
- Latest: second show-cause notice 16 Jan 2026; builder replied 20 Feb 2026
- At stake: proposed forfeiting bank guarantee and revoking registration; no penalty imposed yet
Will it be delivered on time?
- Original deadline Mar 2026, extended to Feb 2027
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- Done: Site office, Marketing office
- In progress: Internal roads and pavements 90%, Landscaping and tree plantation 60%, Treatment and disposal of sewage and sullage water / stp 60%, Sewerage 40%, Storm water drains 40%, Water supply 35%, and 6 more
- Money: ₹247.6 crore spent of ₹338.4 crore; ₹90.8 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 1,378 units: 3 sold, 3 unsold (builder's certificate, Sep 2026)
- Registration now covers 141 Residential + 237 Commercial
- 1,378 units, as declared to HRERA:
- 109 units averaging about 180 sq ft carpet (1 tower)
- 295 units averaging about 420 sq ft carpet (2 towers)
- 846 units averaging about 640 sq ft carpet (6 towers)
- 128 units: the size the builder entered is not possible, so it is not shown
- The builder gave each tower's total carpet area, not each flat's size; averages divide that total by the number of units. HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Millennium City Centre Gurugram, 19.3 km by road (49 min by car)
- Cyber City 56 min · Airport 37 min by car at 9:30 am
- Within 3 km: 0 hospitals, 1 school, 0 malls
The builder: Signatureglobal (India)
- 5 projects registered in Gurugram
- 3 with an occupation certificate on record
- 5 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | SIGNATURE GLOBAL IMPERIAL |
|---|---|
| Builder (promoter) | SIGNATUREGLOBAL (INDIA) PRIVATE LIMITED |
| Location | VILLAGE-HARSARU, SECTOR-88A, GURUGRAM |
| RERA project ID | RERA-GRG-1025-2022 |
| Registration certificate number | GGM/544/276/2022/19 DATED 21.03.2022 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 27/02/2027 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | Extension Certificate Uploaded |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 8.93125 acres |
| Licence | 80 of 2018 ( 02.12.2018) |
| Estimated cost of the project | ₹33,578.61 lakh (₹335.79 crore) |
| Total units (plots, apartments, shops) | 1378 |
| Unit sizes (carpet area, as declared) | 109 units averaging about 180 sq ft carpet (1 tower); 295 units averaging about 420 sq ft carpet (2 towers); 846 units averaging about 640 sq ft carpet (6 towers) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 07-03-2022 |
| Building plans approved on | 07-03-2022 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 28-03-2022 |
|---|---|
| Likely completion date | 28-03-2026 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 14-Oct-2026 |
| Quarterly reports listed on the portal | 18 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹166.24 lakh (₹1.66 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹1,162.15 lakh (₹11.62 crore) |
| Spent on infrastructure in the quarter | ₹27.47 lakh (₹0.27 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
| Project bank account (escrow): deposited in the quarter | ₹113.67 lakh (₹1.14 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹192 lakh (₹1.92 crore) |
| Project bank account (escrow): balance at quarter end | ₹39.18 lakh (₹0.39 crore) |
| Units in the project (apartments / plots) | 1378.00 apartments, 0.00 plots |
| Sold in the quarter | 3 apartments |
| EDC (development charges): paid / due as on date | ₹1,292.54 lakh (₹12.93 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026, for 30 Sep 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | Pending: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against SIGNATUREGLOBAL (INDIA) PRIVATE LIMITED (all its projects) | 5 (Complaint: 5) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in