Registration

Project nameSIGNATURE GLOBAL INFINITY
Builder (promoter)STERNAL BUILDCON PVT.LTD.
LocationSECTOR-36
RERA project IDRERA-GRG-938-2021
Registration certificate numberGGM/519/251/2021/87 DATED 20.12.2021
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to27/02/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area2.15 acres
Licence09 of 2021 dated 05/03/2021
Estimated cost of the project₹14,258.11 lakh (₹142.58 crore)
Total units (plots, apartments, shops)595
Unit sizes (carpet area, as declared)180 units averaging about 160 sq ft carpet (2 towers); 10 units of 1,397 sq ft carpet (1 tower); 44 units of 4,252 sq ft carpet (1 tower); 85 units of 7,966 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on24-11-2021
Building plans approved on24-11-2021

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-12-2021
Likely completion date31-05-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on17-Oct-2026
Quarterly reports listed on the portal19

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹440.71 lakh (₹4.41 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹221.8 lakh (₹2.22 crore)
Spent on construction of apartments in the quarter₹573.66 lakh (₹5.74 crore)
Spent on infrastructure in the quarter₹383.62 lakh (₹3.84 crore)
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹374.66 lakh (₹3.75 crore)
Project bank account (escrow): withdrawn in the quarter₹374.66 lakh (₹3.75 crore)
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)595.00 apartments, 0.00 plots
Sold in the quarter4 apartments
EDC (development charges): paid / due as on date₹941.9 lakh (₹9.42 crore) paid; ₹0 due
Approvals listedNot found in the records checked

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for 30 Sep 2026
By part
  • Tower 1 - Sub structure: 100%, Excavation and raft done; waterproofing of sub-structure at 0%
  • Tower 1 - Super structure: 100%, RCC works complete on total area; walls, staircase, lift wells and lobbies shown as work in progress in detailed sheet
  • Tower 1 - Mechanical (MEP): 93%, Lifts, ventilation etc.; 2% done in the quarter
  • Tower 1 - Electrical (MEP): 82%, Conduiting, wiring, fixtures; 1% done in the quarter
  • Tower 1 - Plumbing and firefighting (MEP): 93%, Piping, pumps, fixtures; 1% done in the quarter
  • Tower 1 - Internal finishing: 76%, Plaster, tiling, flooring, painting; 1% done in the quarter
  • Tower 1 - External finishing: 76%, Plaster, painting, facade; 1% done in the quarter
  • Internal roads and pavements (temporary): 100%
  • Water supply: 82%
  • Sewerage (chamber, lines, septic tanks, STP): 82%
  • Storm water drains: 67%
  • Landscaping and tree plantation (temporary): 97%
  • Parks and playgrounds: 90%
  • Fixing of children play equipment: 0%
  • Benches: 0%
  • Shopping area: 0%
  • Street lighting and electrification: 0%
  • Treatment and disposal of sewage and sullage water / STP: 55%
  • Solid waste management and disposal: 0%
  • Energy management (solar): 0%
  • Fire protection and fire safety requirements: 0%
  • Electrical meter room, sub-station, receiving station: 0%
  • Site office (temporary): 100%
  • Marketing office (temporary): 100%
  • Community centre (to be transferred to RWA): 0%
Unclear in the certificate
  • Table A shows internal and external finishing at 76%, but the detailed status sheet shows wall plastering, wall tiling and flooring as yet to be started (0%). The two figures do not match.
  • Only one tower (Tower Nos. 1) is shown. Table A is marked for Tower 1 only.
  • Council of Architects registration number and its validity date are blank on the certificate.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed2
By statusFirst Hearing: 1; Disposed: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project1
Cases
Decided cases against STERNAL BUILDCON PVT.LTD. (all its projects)64 (Complaint: 64)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026