Projects · SIGNATUREGLOBAL HOMES PRIVATE LIMITED

Signature Global Park V

Signatureglobal Homes · Sector 36, Gurugram

Registered with RERA: Jul 2020

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Signatureglobal Homes

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSIGNATURE GLOBAL PARK V
Builder (promoter)SIGNATUREGLOBAL HOMES PRIVATE LIMITED
LocationVILLAGE HARIYAHARA, SECTOR-36
RERA project IDRERA-GRG-582-2020
Registration certificate numberGGM/402/134/2020/18 DATED 20.07.2020
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/12/2021
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area10.53125 acres
Licence118 of 2019 dated 12.09.2019 (Transfer of License in the name of Signatureglobal Homes Private Limited vide order no. LC-4087/Asstt(AK)/2019/30737dated 13/12/2019
Estimated cost of the project₹9,458.87 lakh (₹94.59 crore)
Total units (plots, apartments, shops)152
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on09-03-2020
Building plans approved on09-03-2020

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-07-2020
Likely completion date31-12-2021

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2022 (JUL-SEP)
Latest report submitted on18-Nov-2022
Quarterly reports listed on the portal8

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2022 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹96.28 lakh (₹0.96 crore)
Other costs in the quarter (EDC, taxes, etc.)₹1,909.86 lakh (₹19.1 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)272 plots
Sold in the quarter0 plots
EDC (development charges): paid / due as on date₹566.62 lakh (₹5.67 crore) paid; ₹1,180.5 lakh (₹11.81 crore) due
Approvals listedNot found in the records checked

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2022, for 30 Sep 2022
By part
  • 272 Nos. (Plots) - Table A sub-structure and super-structure: Excavation in ordinary soil and RCC building raft done. Waterproofing compound being applied (0%). 0% of RCC works completed on total area. Fixing of door and window frames 40%. Slabs, walls, staircase, lift wells, MEP, plastering, tiling, flooring and finishing yet to be started.
  • Internal roads & pavements: 100%
  • Water supply: 80%
  • Sewerage (chamber, lines, septic tanks, STP): 80%
  • Storm water drains: 70%
  • Landscaping & tree plantation: 95%
  • Parks and playgrounds: 35%
  • Fixing of children play equipment: 20%
  • Benches: 30%
  • Shopping area: 0%
  • Street lighting/electrification: 0%
  • Treatment and disposal of sewage and sullage water/STP: 0%
  • Solid waste management & disposal: 0%
  • Energy management (solar): 0%
  • Fire protection and fire safety requirements: 0%
  • Electrical meter room, sub-station, receiving station: 0%
  • Site office (temporary): 100%
  • Marketing office (temporary): 100%
  • Community centre: 0%
Unclear in the certificate
  • Table A percentage columns for sub-structure, super-structure, MEP and finishing are shown as dashes, so no cumulative figure is given for them.
  • No overall project percentage or quarter-only percentage is stated.
  • Council of Architects registration number and validity date are left blank.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed4
By statusFirst Hearing: 3; Disposed: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against SIGNATUREGLOBAL HOMES PRIVATE LIMITED (all its projects)50 (Complaint: 47; Compensation: 3)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in