Signature Global PROXIMA-1 Extn.

Signatureglobal (India) · Sector 8, Gurugram

Registered with RERA: Jul 2024

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Signatureglobal (India)

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSIGNATURE GLOBAL PROXIMA-1 EXTN.
Builder (promoter)SIGNATUREGLOBAL (INDIA) LIMITED
LocationVILLAGE - HAYATPUR, SECTOR -8 9, GURUGRAM, HARYANA
RERA project IDRERA-GRG-1628-2024
Registration certificate numberGGM/851/583/2024/78 DATED 30.07.2024
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to27/06/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area0.44375 acres
Licence. 02 of 2022 dated 06.01.2022
Estimated cost of the project₹2,306.47 lakh (₹23.06 crore)
Total units (plots, apartments, shops)91
Unit sizes (carpet area, as declared)6 units of 350 sq ft carpet (1 tower); 4 units of 361 sq ft carpet (1 tower); 20 units of 362 sq ft carpet (1 tower); 8 units of 564 sq ft carpet (1 tower); 8 units of 568 sq ft carpet (1 tower); 16 units of 569 sq ft carpet (1 tower); 8 units of 762 sq ft carpet (1 tower); 14 units of 897 sq ft carpet (1 tower); 7 units of 1,147 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on10-04-2024
Building plans approved on10-04-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction30-04-2024
Likely completion date29-06-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on14-Oct-2026
Quarterly reports listed on the portal8

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹185.45 lakh (₹1.85 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹112.88 lakh (₹1.13 crore)
Spent on infrastructure in the quarter₹48.3 lakh (₹0.48 crore)
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)91.00 apartments, 0.00 plots
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹52.96 lakh (₹0.53 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 05-07-2019
  • Zoning Plan: Obtained Approval 05-07-2019
  • Service Plans: Obtained Approval 22-11-2019
  • Electricity Plans: Obtained Approval 22-11-2019
  • Site Plans: Obtained Approval 22-11-2019
  • Building Plans: Obtained Approval 22-11-2019
  • Fire NOC: Obtained Approval 17-05-2020

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for 30 Sep 2026
By part
  • Towers (2 nos): sub structure: 100%, Excavation and raft done; water proofing compound being applied
  • Towers (2 nos): super structure: 45%, Slab work in progress; about 47% of RCC work done on total area
  • Towers (2 nos): mechanical MEP: 0%
  • Towers (2 nos): electrical MEP: 0%, Electrical wiring work in progress within flats
  • Towers (2 nos): plumbing and firefighting: 40%
  • Towers (2 nos): internal finishing: 0%
  • Towers (2 nos): external finishing: 0%
  • Internal roads and pavements (temporary): 100%
  • Water supply: 95%
  • Sewerage (chamber, lines, septic tanks, STP): 100%
  • Storm water drains: 100%
  • Landscaping and tree plantation (temporary): 88%
  • Parks and playgrounds: 95%
  • Children play equipment: 0%
  • Benches: 0%
  • Shopping area: 0%
  • Street lighting and electrification: 95%
  • Treatment and disposal of sewage and sullage water / STP: 50%
  • Solid waste management and disposal: 0%
  • Energy management (solar): 0%
  • Fire protection and fire safety requirements: 0%
  • Electrical meter room, sub-station, receiving station: 0%
  • Community centre (to be transferred to RWA): 95%
  • Compound wall (fencing work): 100%, Completed
Unclear in the certificate
  • Table A covers '2 nos (Towers)' but the towers are not named individually, so progress is given for both together.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against SIGNATUREGLOBAL (INDIA) LIMITED (all its projects)2 (Complaint: 2)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026