Projects · SIGNATURE INFRABUILD PRIVATE LIMITED

Signatureglobal Aspire

Signature Infrabuild · Sector 95, Gurugram

Registered with RERA: Nov 2019

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Signature Infrabuild

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSIGNATUREGLOBAL ASPIRE
Builder (promoter)SIGNATURE INFRABUILD PRIVATE LIMITED
LocationVILLAGE DHORKA, SECTOR 95 GUR UGRAM, HARYANA
RERA project IDRERA-GRG-322-2019
Registration certificate numberGGM/375/107/2019/69 DATED 14.11.2019
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to28/04/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area5.1125 acres
Licence73 of 2019 dated 04.07.2019
Estimated cost of the project₹18,197.32 lakh (₹181.97 crore)
Total units (plots, apartments, shops)746
Unit sizes (carpet area, as declared)168 units averaging about 560 sq ft carpet; 520 units averaging about 590 sq ft carpet; 58 units averaging about 600 sq ft carpet
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on03-10-2019
Building plans approved on30-09-2019

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-11-2019
Likely completion date31-10-2023

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on23-Oct-2026
Quarterly reports listed on the portal27

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹-2.81 lakh (₹-0.03 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹237.75 lakh (₹2.38 crore)
Spent on construction of apartments in the quarter₹1,027.28 lakh (₹10.27 crore)
Spent on infrastructure in the quarter₹54.63 lakh (₹0.55 crore)
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)824.00 apartments, 0.00 plots
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹610.32 lakh (₹6.1 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 29-05-2019
  • Zoning Plan: Obtained Approval 04-07-2019
  • Service Plans: Obtained Approval 30-09-2019
  • Electricity Plans: Obtained Approval 06-11-2019
  • Site Plans: Obtained Approval 30-09-2019
  • Building Plans: Obtained Approval 30-09-2019
  • Fire NOC: Obtained Approval 05-06-2020

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for 30 Sep 2026
By part
  • Towers (5+1 nos): Sub structure: 100%, Work done in the quarter: 0%
  • Towers (5+1 nos): Super structure: 100%, Work done in the quarter: 0%
  • Towers (5+1 nos): Mechanical (lifts, ventilation): 75%, Work done in the quarter: 5%
  • Towers (5+1 nos): Electrical (conduiting, wiring, fixtures): 82%, Work done in the quarter: 2%
  • Towers (5+1 nos): Plumbing and firefighting (piping, pumps, fixtures): 82%, Work done in the quarter: 2%
  • Towers (5+1 nos): Internal finishing (plaster, tiling, flooring, painting): 77%, Work done in the quarter: 2%
  • Towers (5+1 nos): External finishing (plaster, painting, facade): 87%, Work done in the quarter: 2%
  • Common areas: Internal roads and pavements (temporary): 100%
  • Common areas: Water supply: 50%
  • Common areas: Sewerage (chamber, lines, septic tanks, STP): 70%
  • Common areas: Storm water drains: 70%
  • Common areas: Landscaping and tree plantation (temporary): 100%
  • Common areas: Parks and playgrounds: 55%
  • Common areas: Fixing of children play equipment: 0%
  • Common areas: Benches: 0%
  • Common areas: Shopping area: 65%
  • Common areas: Street lighting and electrification: 45%
  • Common areas: Treatment and disposal of sewage and sullage water (STP): 80%
  • Common areas: Solid waste management and disposal: 0%
  • Common areas: Energy management (solar): 0%
  • Common areas: Fire protection and fire safety: 0%
  • Common areas: Electrical meter room, sub-station, receiving station: 0%
  • Common areas: Site office (temporary): 100%
  • Community centre (to be transferred to RWA): 80%
Unclear in the certificate
  • Table A gives one set of figures for all 5+1 towers together; no tower-wise split is given.
  • Table A 'work done during the quarter' is shown as a percentage for MEP and finishing items but not stated as a single overall figure.
  • Overall and quarter percentages are not stated as single figures in the certificate.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registration
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed4
By statusScrutinized: 1; First Hearing: 2; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against SIGNATURE INFRABUILD PRIVATE LIMITED (all its projects)78 (Complaint: 78)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in