Projects · ROSE BUILDING SOLUTIONS PRIVATE LIMITED
Signatureglobal City 37D II
Rose Building Solutions · Sector 37D, Gurugram
Registered with RERA: Mar 2022
Is it legal?
- RERA registered, valid till Feb 2027
- HRERA has opened 2 cases of its own against the builder over this project (2 open):
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jul 2024, open)
- Failed to submit bank escrow agreement and approved service estimates and plans on time (Nov 2022, open). At stake: Authority proposes forfeiting bank guarantee and revoking registration; no penalty imposed yet
Will it be delivered on time?
- Original deadline Feb 2023, extended 4 times to Feb 2027
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- Done: Water supply, Sewerage, Site office
- In progress: Storm water drains 98%, Street lighting/electrification 95%, Treatment and disposal of sewage and sullage water/stp 90%, Internal roads & pavements 88%, Parks and playgrounds 80%, Landscaping & tree plantation 70%, and 9 more
- Money: ₹109.8 crore spent of ₹109.8 crore (CA certificate, Sep 2026)
What's on offer?
- 84 units: 0 sold, 0 unsold (builder's certificate, Sep 2026)
- Registration now covers 84 plots
- 84 plots, 128–179 sq yd
Location
- Nearest metro: Millennium City Centre Gurugram, 21.8 km by road (53 min by car)
- Cyber City 60 min · Airport 41 min by car at 9:30 am
- Within 3 km: 5 hospitals, 2 schools, 1 mall
The builder: Rose Building Solutions
- 3 projects registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 1 buyer complaint decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | SIGNATUREGLOBAL CITY 37D II |
|---|
| Builder (promoter) | ROSE BUILDING SOLUTIONS PRIVATE LIMITED |
|---|
| Location | VILLAGE-GADOLI KALAN, SECTOR- 37D, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-1022-2022 |
|---|
| Registration certificate number | GGM/545/277/2022/20 DATED 31.03.2022 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 24/02/2027 |
|---|
| Registered with | HRERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|
| Land area | 5.62 acres |
|---|
| Licence | 111 of 2021 dated 17/12/2021 |
|---|
| Estimated cost of the project | ₹6,491.93 lakh (₹64.92 crore) |
|---|
| Total units (plots, apartments, shops) | 84 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | Not applicable (new project) |
|---|
| Units unsold when registered | Not applicable (new project) |
|---|
| Layout plan approved on | 20-12-2021 |
|---|
| Building plans approved on | Not found in the records checked |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
|---|
| Latest report submitted on | 14-Oct-2026 |
|---|
| Quarterly reports listed on the portal | 17 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹34.82 lakh (₹0.35 crore) |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹34.8 lakh (₹0.35 crore) |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0.02 lakh (₹0 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹0 |
|---|
| Units in the project (apartments / plots) | 0.00 apartments, 84.00 plots |
|---|
| Sold in the quarter | 0 plots |
|---|
| EDC (development charges): paid / due as on date | ₹655.22 lakh (₹6.55 crore) paid; ₹0 due |
|---|
| Approvals listed | Not found in the records checked |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026, for 30 Sep 2026 |
|---|
| By part | - 84 Nos. (Plots): Excavation done and raft RCC built. Water proofing compound being applied. Super structure, walls, plaster, flooring and MEP work yet to be started.
- Internal roads & pavements: 88%
- Parking: 60%
- Water supply: 100%
- Sewerage (chamber, lines, septic tanks, STP): 100%
- Storm water drains: 98%
- Landscaping & tree plantation: 70%
- Parks and playgrounds: 80%
- Fixing of children play equipment: 0%
- Benches: 0%
- Shopping area: 0%
- Street lighting/electrification: 95%
- Treatment and disposal of sewage and sullage water/STP: 90%
- Solid waste management & disposal: not stated
- Energy management (solar): 0%
- Fire protection and fire safety requirements: 0%
- Electrical meter room, sub-station, receiving station: 0%
- Site office: 100%, Temporary
- Community centre: 0%
- Club: 55%
|
|---|
| Unclear in the certificate | - Table A percentages for the plots are shown as dashes, with no figures given.
- Total number of floors per tower is left blank.
- Solid waste management has no percentage given, only a dash.
- Council of Architects registration number and validity date are left blank.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | - Extension 09 of 2023 dated 17 Apr 2023: registration extended from 28 Feb 2023 to 27 Feb 2024. Conditions include: The promoter must offer to execute and register a conveyance deed in favour of allottees for their unit or apartment, with parking if applicable.; If taxes, charges, fees or levies increase after the scheduled completion date, the increase cannot be charged to allottees. This includes any extension granted.; The extension is granted without prejudice to allottees' rights under section 18 of the Act, as the promoter has not shown reasonable circumstances and fault-free reasons for not completing the project within the declared timeline.; The promoter must comply with the Act and the rules and regulations made under it.; The promoter must not contravene any other law in force that applies to the project.; If these conditions are not met, the Authority may take action, including revoking the registration.
- Extension 09 of 2023 dated 09 Jul 2024: registration extended from 27 Feb 2024 to 26 Feb 2025. Conditions include: The promoter must pay a penalty of Rs. 25 lakhs for violating sections 3 and 4 of the Act. The document says this was paid online on 04 Jul 2024.; The promoter must pay delay possession charges under section 18(1) from its own funds. Project cash inflow must not be used for this.; The registration does not affect allottees' rights to delay possession charges or to withdraw from the project under section 18(1).; Units are sold on a carpet area basis only. The total sale consideration must include all charges, and no separate EDC/IDC is payable beyond it.; No sale through a real estate agent is allowed without a prospectus or brochure, drawings, and a registered agent.; No subvention scheme or assured returns are allowed without prior approval of the Authority.; The promoter cannot accept more than ten percent of the cost as advance payment without a registered written agreement for sale.; The promoter must get its accounts audited by a chartered accountant within six months after each financial year end.; The promoter must submit a monthly comparison of proposed and actual work on the 7th of each month.; The Authority may start penal proceedings for violations, even though the registration is allowed to continue.
- Extension 20 of 2022 dated 22 May 2025: registration extended from 28 Feb 2023 to 26 Feb 2025. Conditions include: The promoter must enter into agreements for sale with allottees in the prescribed form under the Haryana rules.; Sale is on a carpet area basis, and the total sale consideration must include all charges; no separate EDC/IDC is payable except the total sale consideration.; The promoter must deposit 100% of amounts realised from allottees in a separate schedule bank account to cover construction and proportionate land cost, used only for that purpose.; The promoter must not accept more than ten percent of the cost of an apartment, plot or building as advance payment without first entering into a registered written agreement for sale.; The promoter must not sell through a real estate agent without a brochure and approvals, and agents must be registered with HARERA.; There shall be no subvention or assured return scheme for the registered project without prior approval of the Authority.; The promoter must enable formation of an association of allottees within three months of a majority of allottees booking.; The promoter must issue allotment letters as per the draft approved by the Authority.; The individual dates of possession in existing booking agreements shall not be changed if they fall before the date in the detailed project information.; The Authority imposed a penalty of Rs. 25 lakhs for violation of sections 3 and 4 of the Act; the promoter submitted Rs. 25,00,000 by DD dated 07.05.2025 before issuance.; The promoter must not create further encumbrance on future receivables from sold units or separate RERA accounts, except the existing lender's charge.; Rights of allottees under section 18(1) for delay possession charges are not affected; the promoter must pay delay possession charges from its own funds and project cash inflow shall not be used for this purpose.; The promoter declared completion of the entire project by 25.02.2026.; The promoter must submit monthly comparison of proposed and actual work (PERT chart) on the 7th day of each month.; The promoter must submit quarterly progress reports and an annual audited statement of accounts by a chartered accountant.; The Authority may take action, including revoking registration, if conditions are not fulfilled.
- Extension 20 of 2022/7(3)/51/2024/10 dated 11 Aug 2026: registration extended from 25 Feb 2026 to 24 Feb 2027. Conditions include: Promoter must deposit 100% of amounts realized from allottees in a separate account in a schedule bank, to be used only for construction and proportionate land cost.; Promoter must enter into agreements for sale with allottees as prescribed under the HRERA Rules, 2017.; Promoter must not accept more than ten percent of the cost as advance or application fee without a registered written agreement for sale.; No subvention or assured return scheme is permitted without prior approval of the Authority.; Promoter must complete community sites within the declared completion period; failure would attract stringent action and penal proceedings.; Promoter must take required approvals and renewals on time; failure will invite stringent action under the law.; Promoter must not create further charge or hypothecation on future receivables from the sold units or on separate RERA accounts, except the existing charge in favour of the existing lender.; Registration is without prejudice to allottees' rights to delay possession charges under section 18(1); promoter must pay such charges from its own funds, not from project cash inflow.; Promoter declared completion of the entire project by 24 Feb 2027; some licences and approvals will expire within that period.; Authority reserves the right to initiate penal proceedings for violations of the Act, rules and regulations.
|
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 2 |
|---|
| By status | First Hearing: 1; Pending: 1 |
|---|
| Proceedings | |
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|
| Decided cases against ROSE BUILDING SOLUTIONS PRIVATE LIMITED (all its projects) | 1 (Complaint: 1) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in