RERA’d by NeevHQ

Projects · SIGNATUREGLOBAL (INDIA)LIMITED

Signatureglobal Cloverdale SPR

Signatureglobal (India) · Sector 71, Gurugram

Registered with RERA: Jun 2025

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Signatureglobal (India)

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSIGNATUREGLOBAL CLOVERDALE SPR
Builder (promoter)SIGNATUREGLOBAL (INDIA)LIMITED
LocationVILLAGE - FAIZALPUR JHARSA, S ECTOR-71, GURUGRAM, HARYANA
RERA project IDRERA-GRG-1961-2025
Registration certificate numberGGM/955/687/2025/58 DATED 10.06.2025
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/05/2031
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area8.12 acres
Licence09 of 2010 Dated 23.01.2010 Renewed up to 22.01.2030
Estimated cost of the project₹2,22,812.94 lakh (₹2,228.13 crore)
Total units (plots, apartments, shops)837
Unit sizes (carpet area, as declared)43 units of 201 sq ft carpet (1 tower); 2 units of 315 sq ft carpet (1 tower); 420 units of 1,168 sq ft carpet (3 towers); 280 units of 1,276 sq ft carpet (2 towers); 70 units of 1,807 sq ft carpet (1 tower); 22 units of 2,363 sq ft carpet (2 towers)
Flat types (BHK), as stated by the builder3 BHK; 3 BHK + utility (source: the builder's floor plans uploaded to HRERA)
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on21-05-2025
Building plans approved on21-05-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-06-2025
Likely completion date31-05-2031

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on14-Oct-2026
Quarterly reports listed on the portal5

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹1,029.84 lakh (₹10.3 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹2,501.76 lakh (₹25.02 crore)
Spent on construction of apartments in the quarter₹2,292.59 lakh (₹22.93 crore)
Spent on infrastructure in the quarter₹1,239.01 lakh (₹12.39 crore)
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹1,629.69 lakh (₹16.3 crore)
Project bank account (escrow): withdrawn in the quarter₹2,211 lakh (₹22.11 crore)
Project bank account (escrow): balance at quarter end₹164.34 lakh (₹1.64 crore)
Units in the project (apartments / plots)837.00 apartments, 0.00 plots
Sold in the quarter251 apartments
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 21-05-2025
  • Zoning Plan: Obtained Approval 21-05-2025
  • Service Plans: Obtained Approval 26-05-2025
  • Electricity Plans: Obtained Approval 23-05-2024
  • Site Plans: Obtained Approval 21-05-2025
  • Building Plans: Obtained Approval 21-05-2025
  • Fire NOC: Obtained Approval 21-05-2025

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for 30 Sep 2026
By part
  • Towers (6 nos, Table A): 35%, Excavation in ordinary soil done (35%). Raft RCC not started. Water proofing compound being applied. Super structure not started.
  • Internal roads & pavements (temporary): 55%
  • Landscaping & tree plantation (temporary): 55%
  • Site office (temporary): 100%
Unclear in the certificate
  • Table A gives one set of figures for all 6 towers. No tower-wise split is shown.
  • Table A and Table B percentages are shown as stated. No overall project percentage is given in the certificate.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against SIGNATUREGLOBAL (INDIA)LIMITED (all its projects)2 (Complaint: 2)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in