Projects · SIGNATUREGLOBAL (INDIA) PRIVATE LIMITED

Signatureglobal Proxima 1

Signatureglobal (India) · Sector 89, Gurugram

Registered with RERA: Dec 2019

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Signatureglobal (India)

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSIGNATUREGLOBAL PROXIMA 1
Builder (promoter)SIGNATUREGLOBAL (INDIA) PRIVATE LIMITED
LocationVILLAGE HAYATPUR, SECTOR 89 G URUGRAM, HARYANA
RERA project IDRERA-GRG-336-2019
Registration certificate numberGGM/383/115/2019/77 DATED 31.12.2019
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to28/06/2026
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area5.00 acres
Licence89 of 2019 dated 02.08.2019
Estimated cost of the project₹17,665.86 lakh (₹176.66 crore)
Total units (plots, apartments, shops)720
Unit sizes (carpet area, as declared)684 units averaging about 590 sq ft carpet (4 towers); 36 units averaging about 640 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on22-11-2019
Building plans approved on25-11-2019

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-01-2020
Likely completion date31-12-2023

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on14-Oct-2026
Quarterly reports listed on the portal26

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹73.61 lakh (₹0.74 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹150 lakh (₹1.5 crore)
Spent on infrastructure in the quarter₹44.19 lakh (₹0.44 crore)
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹253.65 lakh (₹2.54 crore)
Project bank account (escrow): withdrawn in the quarter₹365 lakh (₹3.65 crore)
Project bank account (escrow): balance at quarter end₹22.61 lakh (₹0.23 crore)
Units in the project (apartments / plots)780.00 apartments, 0.00 plots
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹596.86 lakh (₹5.97 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 05-07-2019
  • Zoning Plan: Obtained Approval 02-08-2019
  • Service Plans: Obtained Approval 22-11-2019
  • Site Plans: Obtained Approval 22-11-2019
  • Building Plans: Obtained Approval 22-11-2019
  • Fire NOC: Obtained Approval 17-05-2020

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for 30 Sep 2026
By part
  • 5 towers and 3 commercial buildings (Table A, shown as one entry): Table A shows 100% cumulative work done for sub structure, super structure, MEP and finishing, and 0% work done during the quarter. The detailed status table lists many items as work in progress or yet to start.
  • Internal roads and pavements (temporary): 100%
  • Water supply: 100%
  • Sewerage (chamber, lines, septic tanks, STP): 100%
  • Storm water drains: 100%
  • Landscaping and tree plantation (temporary): 100%
  • Parks and playgrounds: 0%
  • Shopping area: 0%
  • Street lighting and electrification: 0%
  • Solid waste management and disposal: 0%
  • Energy management (solar): 0%
  • Fire protection and fire safety requirements: 0%
  • Electrical meter room, sub-station, receiving station: 0%
  • Site office (temporary): 100%
  • Community centre: 0%
  • Compound wall (fencing work): 100%, Works in progress
Unclear in the certificate
  • The certificate gives no single overall percentage and no tower-wise figures; Table A covers all 5 towers and 3 commercial buildings together.
  • Table A shows 100% cumulative work done for several items, but the detailed status table shows many items as work in progress or yet to start (e.g. lift wells, doors and windows, white washing, terrace waterproofing, entrance lobby).
  • Table A shows 0% work done during the quarter, while the detailed status table lists several items as work in progress.
  • Table B shows the parks, shopping area and solar energy items at 0%, while the Table A and detailed status figures are not split by item in the same way.
  • Basement rows and the Table A percentage column were filled in the certificate but the basement details are marked NA.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed5
By statusScrutinized: 1; First Hearing: 3; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project1
Cases
Decided cases against SIGNATUREGLOBAL (INDIA) PRIVATE LIMITED (all its projects)5 (Complaint: 5)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026