Projects · SUPOSHAA REALCON PRIVATE LIMITED
Smartworld Orchard
Suposhaa Realcon · Sector 61, Gurugram
Registered with RERA: Oct 2022
Is it legal?
- RERA registered, valid till Oct 2026 (date has passed)
- HRERA has not opened any case of its own against this project
Will it be delivered on time?
- Original deadline not found, extended 2 times to Oct 2026
- The order keeps buyers' right to a refund or interest for the delay
- 8 occupation certificates issued:
- Jul 2024: Plots A-92 to A-97, Sector 61, Gurugram (4 flats)
- Jul 2024: Six plots in Sector-61: A-107, B-32 to B-35, B-37 (4 flats)
- Jul 2024: Plots B-64 to B-69, Sector-61, DDJAY houses (4 flats)
- Jul 2024: Plots B-91 to B-96, Sector-61: residential, 4 units each (4 flats)
What's on offer?
- Registration now covers 416 residential plots and 4 commercial blocks
Location
- Nearest metro: Sector 55–56, 2.9 km by road (10 min by car)
- Cyber City 34 min · Airport 51 min by car at 9:30 am
- Within 3 km: 6 hospitals, 7 schools, 1 mall
Location shown for Sector 61; the exact site was not found.
The builder: Suposhaa Realcon
- 5 projects registered in Gurugram, 2 lapsed
- 3 with an occupation certificate on record
- 32 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | SMARTWORLD ORCHARD |
|---|---|
| Builder (promoter) | SUPOSHAA REALCON PRIVATE LIMITED |
| Location | SECTOR -61, GURUGRAM MANESAR URBAN COMPLEX, GURUGRAM, HARYANA |
| RERA project ID | RERA-GRG-1039-2022 |
| Registration certificate number | GGM/616/348/2022/91 DATED 04.10.2022 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 29/10/2026 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | Extension Certificate Uploaded |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 23.29999 acres |
| Licence | 68 of 2021 dated 16.09.2021 and 62 of 2022 dated 25.05.2022 |
| Estimated cost of the project | ₹34,256.1 lakh (₹342.56 crore) |
| Total units (plots, apartments, shops) | 420 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | 0 |
| Units unsold when registered | 0 |
| Layout plan approved on | 25-05-2022 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | Not found in the records checked |
|---|---|
| Revised completion date | Not found in the records checked |
| Infrastructure: projected completion | 31-10-2023 |
| Infrastructure: percentage complete when registered | 0% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/06/2026 (APR-JUN) |
| Latest report submitted on | 02-Jul-2026 |
| Quarterly reports listed on the portal | 14 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2026 (APR-JUN))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | Not found in the records checked |
| Sold in the quarter | Not found in the records checked |
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Unclear in the certificate |
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against SUPOSHAA REALCON PRIVATE LIMITED (all its projects) | 32 (Complaint: 28; Compensation: 4) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in