Projects · RIVERDAY INFRASTRUCTURE PRIVATE LIMITED
Smartworld Sky Arc
Riverday Infrastructure · Sector 69, Gurugram
Registered with RERA: Oct 2024
Is it legal?
- RERA registered, valid till May 2032
- HRERA has not opened any case of its own against this project
- 1 complaint about this project decided by HRERA since Nov 2023 (1 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline May 2032, never extended
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- In progress: Sub-structure 58%, Super-structure 18%, Mep 0%, Finishing 0%, Common areas and services 0%
- Money: ₹1,464.2 crore spent of ₹3,407.7 crore; ₹1,943.4 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 952 units: 863 sold, 89 unsold (builder's certificate)
- Flat types (BHK) as stated in the builder's floor plans uploaded to HRERA:
- 2 BHK
- 2 BHK + store
- 3 BHK
- 952 units in 13 sizes, as declared to HRERA:
- 12 units of 921 sq ft carpet (6 towers)
- 216 units of 1,217 sq ft carpet
- 156 units of 1,370 sq ft carpet (6 towers)
- 78 units of 1,453 sq ft carpet (6 towers)
- 312 units of 1,455 sq ft carpet (6 towers)
- 156 units of 1,797 sq ft carpet (6 towers)
- 7 less common sizes: see the full list below
Location
- Nearest metro: Sector 55–56, 9.3 km by road (33 min by car)
- Cyber City 54 min · Airport 50 min by car at 9:30 am
- Within 3 km: 9 hospitals, 11 schools, 8 malls
The builder: Riverday Infrastructure
- 2 projects registered in Gurugram
- 0 with an occupation certificate on record
- 1 buyer complaint decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | SMARTWORLD SKY ARC |
|---|---|
| Builder (promoter) | RIVERDAY INFRASTRUCTURE PRIVATE LIMITED |
| Location | SECTOR 69 |
| RERA project ID | RERA-GRG-1723-2024 |
| Registration certificate number | GGM/878/610/2024/105 DATED 11.10.2024 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/05/2032 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 6.97635 acres |
| Licence | 90 of 2024 dated 18.07.2024 |
| Estimated cost of the project | ₹3,40,765.96 lakh (₹3,407.66 crore) |
| Total units (plots, apartments, shops) | 952 |
| Unit sizes (carpet area, as declared) | 2 units of 775 sq ft carpet (6 towers); 6 units of 861 sq ft carpet (6 towers); 12 units of 921 sq ft carpet (6 towers); 2 units of 1,203 sq ft carpet (6 towers); 216 units of 1,217 sq ft carpet; 156 units of 1,370 sq ft carpet (6 towers); 78 units of 1,453 sq ft carpet (6 towers); 312 units of 1,455 sq ft carpet (6 towers); 156 units of 1,797 sq ft carpet (6 towers); 4 units of 2,626 sq ft carpet (6 towers); 4 units of 2,938 sq ft carpet (6 towers); 2 units of 3,042 sq ft carpet (6 towers); 2 units of 3,281 sq ft carpet (6 towers) |
| Flat types (BHK), as stated by the builder | 2 BHK; 2 BHK + store; 3 BHK (source: the builder's floor plans uploaded to HRERA) |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 19-09-2024 |
| Building plans approved on | 19-09-2024 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-10-2024 |
|---|---|
| Likely completion date | 31-05-2032 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 14-Oct-2026 |
| Quarterly reports listed on the portal | 7 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹17,458.84 lakh (₹174.59 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹15,012.29 lakh (₹150.12 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹15,229.91 lakh (₹152.3 crore) |
| Project bank account (escrow): deposited in the quarter | ₹17,458.84 lakh (₹174.59 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹17,379 lakh (₹173.79 crore) |
| Project bank account (escrow): balance at quarter end | ₹190.57 lakh (₹1.91 crore) |
| Units in the project (apartments / plots) | 952 apartments |
| Sold in the quarter | 11 apartments |
| EDC (development charges): paid / due as on date | ₹1,531.22 lakh (₹15.31 crore) paid; ₹1,531.22 lakh (₹15.31 crore) due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026, for 30 Sep 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 1 |
|---|---|
| Cases | |
| Decided cases against RIVERDAY INFRASTRUCTURE PRIVATE LIMITED (all its projects) | 1 (Complaint: 1) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in