Sobha City- Phase 1,PART 2

Sobha · Sector 108, Gurugram

Registered with RERA: Aug 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Sobha

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSOBHA CITY- PHASE 1,PART 2
Builder (promoter)SOBHA LIMITED
LocationVILLAGE BABUPUR,SECTOR-108, G URUGRAM
RERA project IDRERA-GRG-376-2019
Registration certificate number115 OF 2017 DATED 28.08.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to01/05/2022
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area0.76635 acres
Licence107 of 2008 (26.05.2020)
Estimated cost of the project₹33,904 lakh (₹339.04 crore)
Total units (plots, apartments, shops)240
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered197
Units unsold when registered43
Layout plan approved on19-01-2016
Building plans approved on19-01-2016

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date01-05-2022
Revised completion date01-05-2022
Infrastructure: projected completion30-04-2022
Infrastructure: percentage complete when registered27%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on15-Oct-2026
Quarterly reports listed on the portal32

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹0.59 lakh (₹0.01 crore)
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹85.38 lakh (₹0.85 crore)
Units in the project (apartments / plots)240 apartments
Sold in the quarterNot found in the records checked
EDC (development charges): paid / due as on date₹1,092 lakh (₹10.92 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 04-08-2010
  • Zoning Plan: Obtained Approval 30-08-2010
  • Service Plans: Obtained Approval 17-01-2023
  • Electricity Plans: Obtained Approval 15-11-2019
  • Site Plans: Obtained Approval 27-09-2022
  • Building Plans: Obtained Approval 27-09-2022
  • Fire NOC: Obtained Approval 01-02-2023

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for 30 Sep 2026
By part
  • Tower A2: 100%, All 18 floor slabs laid; walls, staircase, lift wells and lift lobbies done on all 18 floors; electrical and plumbing 100% in flats and common areas
  • Tower B2: 100%
  • Tower C2: 100%
Unclear in the certificate
  • Tower A2 Table B: the mechanical works row and the wall finishing status row have no entries on the page.
  • Table B (floor-wise detail) for Towers B2 and C2 is not included in the document.
  • Table A shows work done during the quarter as NIL for all towers, and no single overall project percentage is stated.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed5
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 2; Pending: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project2
Cases
Decided cases against SOBHA LIMITED (all its projects)8 (Complaint: 7; Execution of an earlier order: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026