RERA’d by NeevHQ

Projects · SOBHA LIMITED

Sobha City, PHASE-6

Sobha · Sector 108, Gurugram

Registered with RERA: Oct 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for Sector 108; the exact site was not found.

The builder: Sobha

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSOBHA CITY, PHASE-6
Builder (promoter)SOBHA LIMITED
LocationREVENUE ESTATE OF BABUPUR VIL LAGE, VILLAGE BABUPUR, SECTOR-108, GURUGRAM, HARYANA
RERA project IDRERA-GRG-1152-2022
Registration certificate numberGGM/620/352/2022/95 DATED 19.10.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/12/2028
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area16.3995 acres
Licence107 of 2008 dated 27.05.2008 valid upto 26.05.2025
Estimated cost of the project₹1,16,844.82 lakh (₹1,168.45 crore)
Total units (plots, apartments, shops)396
Unit sizes (carpet area, as declared)2 units of 1,103 sq ft carpet (2 towers); 4 units of 1,344 sq ft carpet (4 towers); 34 units of 1,348 sq ft carpet (2 towers); 10 units of 1,353 sq ft carpet (4 towers); 1 unit of 1,427 sq ft carpet (1 tower); 68 units of 1,582 sq ft carpet (4 towers); 205 units of 1,597 sq ft carpet (4 towers); 36 units of 1,900 sq ft carpet (2 towers); 36 units of 1,912 sq ft carpet (2 towers)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on27-09-2022
Building plans approved on27-09-2022

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-03-2023
Likely completion date31-12-2028

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on15-Oct-2026
Quarterly reports listed on the portal15

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹6,536.15 lakh (₹65.36 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹4,317.9 lakh (₹43.18 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹4,927.35 lakh (₹49.27 crore)
Project bank account (escrow): withdrawn in the quarter₹3,269 lakh (₹32.69 crore)
Project bank account (escrow): balance at quarter end₹19,118.62 lakh (₹191.19 crore)
Units in the project (apartments / plots)396 apartments
Sold in the quarterNot found in the records checked
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 04-10-2010
  • Zoning Plan: Obtained Approval 30-08-2010
  • Service Plans: Obtained Approval 17-01-2023
  • Electricity Plans: Obtained Approval 17-08-2022
  • Site Plans: Obtained Approval 27-09-2022
  • Building Plans: Obtained Approval 27-09-2022
  • Fire NOC: Obtained Approval 01-02-2023

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for 30 Sep 2026
By part
  • Tower D1: Sub structure, super structure, mechanical, electrical, plumbing and firefighting, internal finishing and external finishing are each certified at 100%.
  • Tower D2: Sub structure, super structure, mechanical, electrical, plumbing and firefighting, internal finishing and external finishing are each certified at 100%.
  • Tower D3: Sub structure 100%, super structure 95%, mechanical 0%, electrical 25%, plumbing and firefighting 15%, internal finishing 9%, external finishing 0%.
  • Tower D4: Sub structure 100%, super structure 46%, mechanical 0%, electrical 12%, plumbing and firefighting 7%, internal finishing 14%, external finishing 0%.
Unclear in the certificate
  • The certificate gives a percentage for each component of each tower, not one overall figure for each tower or for the project.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against SOBHA LIMITED (all its projects)8 (Complaint: 7; Execution of an earlier order: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026