Sobha City Phase IV
Sobha · Sector 108, Gurugram
Registered with RERA: May 2019
Is it legal?
- RERA registered, valid till Dec 2024 (date has passed)
- HRERA has opened 3 cases of its own against the builder over this project (3 open):
- Did not submit quarterly progress report, prompting Authority show-cause notice (Jun 2022, open)
- 2 more cases: reply 4
Will it be delivered on time?
- Deadline Dec 2024, never extended (date has passed)
- 2 occupation certificates issued:
- Jan 2024: Tower B-3, EWS Tower 03 and basement (99 flats)
- Nov 2024: Tower B-4 and 4th floor of EWS Tower-03 only (72 flats)
- Construction, as certified by the architect (Jul–Sep 2026):
- Done: Tower a3, Tower a4, Tower b3, Tower b4
- Money: ₹354 crore spent of ₹354 crore (CA certificate, Sep 2026)
What's on offer?
- 288 units sold (builder's certificate)
- 288 units in 3 sizes, as declared to HRERA:
- 72 units of 848 sq ft carpet (1 tower)
- 144 units of 1,111 sq ft carpet
- 72 units of 1,280 sq ft carpet (1 tower)
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 11.2 km by road (20 min by car)
- Cyber City 57 min · Airport 37 min by car at 9:30 am
- Within 3 km: 0 hospitals, 0 schools, 0 malls
Location shown for Sector 108; the exact site was not found.
The builder: Sobha
- 10 projects registered in Gurugram, 1 lapsed
- 5 with an occupation certificate on record
- 8 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | SOBHA CITY PHASE IV |
|---|---|
| Builder (promoter) | SOBHA LTD. |
| Location | SECTOR-108, GURUGRAM |
| RERA project ID | RERA-GRG-139-2018 |
| Registration certificate number | GGM/340/72/2019/34 DATED 27.05.2019 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/12/2024 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 2.6778 acres |
| Licence | 107 of 2008(26.05.2020) |
| Estimated cost of the project | ₹40,470 lakh (₹404.7 crore) |
| Total units (plots, apartments, shops) | 288 |
| Unit sizes (carpet area, as declared) | 72 units of 848 sq ft carpet (1 tower); 144 units of 1,111 sq ft carpet; 72 units of 1,280 sq ft carpet (1 tower) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 19-01-2016 |
| Building plans approved on | 19-01-2016 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-02-2019 |
|---|---|
| Likely completion date | 31-12-2024 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 15-Oct-2026 |
| Quarterly reports listed on the portal | 29 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹6.26 lakh (₹0.06 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
| Project bank account (escrow): deposited in the quarter | ₹4.38 lakh (₹0.04 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹13.3 lakh (₹0.13 crore) |
| Units in the project (apartments / plots) | 288 apartments |
| Sold in the quarter | Not found in the records checked |
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026, for 30 Sep 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against SOBHA LTD. (all its projects) | 8 (Complaint: 7; Execution of an earlier order: 1) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in