Projects · SOBHA COMMERCIAL PRIVATE LIMITED
Sobha Strada
Sobha Commercial · Sector 106, Gurugram
Registered with RERA: Nov 2025
Is it legal?
- RERA registered, valid till Dec 2032
- HRERA opened a case of its own against the builder in May 2026 (still open):
- Why: failed to comply with conditions in registration certificate for Sobha Strada project
- Latest: builder replied to show-cause notice 23 Jun 2026
Will it be delivered on time?
- Deadline Dec 2032, never extended
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- In progress: Block-2 - sub structure 90%, Block-1 - sub structure 58.14%, Block-2 - super structure 10%, Block-1 - super structure 0%, Block-1 - mep mechanical 0%, Block-1 - mep electrical 0%, and 8 more
- Money: ₹105.8 crore spent of ₹552.9 crore; ₹447.1 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 299 units in 32 sizes, as declared to HRERA:
- 3 units of 129 sq ft carpet (2 towers)
- 3 units of 275 sq ft carpet (2 towers)
- 3 units of 278 sq ft carpet (2 towers)
- 52 units of 415 sq ft carpet (2 towers)
- 97 units of 424 sq ft carpet (2 towers)
- 102 units of 433 sq ft carpet (2 towers)
- 26 less common sizes: see the full list below
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 8.7 km by road (14 min by car)
- Cyber City 52 min · Airport 31 min by car at 9:30 am
- Within 3 km: 5 hospitals, 1 school, 1 mall
The builder: Sobha Commercial
- 1 project registered in Gurugram
- 0 with an occupation certificate on record
- 0 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | SOBHA STRADA |
|---|---|
| Builder (promoter) | SOBHA COMMERCIAL PRIVATE LIMITED |
| Location | SECTOR 106, VILLAGE PAWALA KH USRUPUR, GURUGRAM |
| RERA project ID | RERA-GRG-2061-2025 |
| Registration certificate number | GGM/1010/742/2025/113 DATED 17.11.2025 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/12/2032 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 2.03 acres |
| Licence | LC-162 OF 2022, dated 06.10.2022 |
| Estimated cost of the project | ₹55,291.82 lakh (₹552.92 crore) |
| Total units (plots, apartments, shops) | 299 |
| Unit sizes (carpet area, as declared) | 3 units of 129 sq ft carpet (2 towers); 1 unit of 234 sq ft carpet (2 towers); 3 units of 275 sq ft carpet (2 towers); 3 units of 278 sq ft carpet (2 towers); 3 units of 297 sq ft carpet (2 towers); 3 units of 325 sq ft carpet (2 towers); 3 units of 341 sq ft carpet (2 towers); 3 units of 404 sq ft carpet (2 towers); 52 units of 415 sq ft carpet (2 towers); 97 units of 424 sq ft carpet (2 towers); 102 units of 433 sq ft carpet (2 towers); 2 units of 478 sq ft carpet (2 towers); 1 unit of 654 sq ft carpet (2 towers); 1 unit of 698 sq ft carpet (2 towers); 1 unit of 816 sq ft carpet (2 towers); 1 unit of 881 sq ft carpet (2 towers); 2 units of 981 sq ft carpet (2 towers); 2 units of 1,277 sq ft carpet (2 towers); 1 unit of 1,416 sq ft carpet (2 towers); 2 units of 1,451 sq ft carpet (2 towers); 1 unit of 1,467 sq ft carpet (2 towers); 2 units of 1,734 sq ft carpet; 1 unit of 1,747 sq ft carpet (2 towers); 1 unit of 1,748 sq ft carpet (2 towers); 1 unit of 2,001 sq ft carpet (2 towers); 1 unit of 2,100 sq ft carpet (2 towers); 1 unit of 2,172 sq ft carpet (2 towers); 1 unit of 2,248 sq ft carpet (2 towers); 1 unit of 2,771 sq ft carpet (2 towers); 1 unit of 3,083 sq ft carpet (2 towers); 1 unit of 3,270 sq ft carpet (2 towers); 1 unit of 3,388 sq ft carpet (2 towers) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 30-09-2025 |
| Building plans approved on | 30-09-2025 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-01-2026 |
|---|---|
| Likely completion date | 31-12-2032 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 15-Oct-2026 |
| Quarterly reports listed on the portal | 3 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹156.38 lakh (₹1.56 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹820.77 lakh (₹8.21 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹142.18 lakh (₹1.42 crore) |
| Project bank account (escrow): deposited in the quarter | ₹422.72 lakh (₹4.23 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹454.59 lakh (₹4.55 crore) |
| Project bank account (escrow): balance at quarter end | ₹13.58 lakh (₹0.14 crore) |
| Units in the project (apartments / plots) | 299 apartments |
| Sold in the quarter | 10 apartments |
| EDC (development charges): paid / due as on date | ₹1,842.51 lakh (₹18.43 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026, for 30 Sep 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | Pending: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against SOBHA COMMERCIAL PRIVATE LIMITED (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in