RERA’d by NeevHQ

Projects · RISEONIC REALTY PVT LTD

Solitaire

Riseonic Realty · Sector 70, Gurugram

Registered with RERA: May 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Riseonic Realty

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSOLITAIRE
Builder (promoter)RISEONIC REALTY PVT LTD
LocationSECTOR 70, BADSHAPUR, HARYANA .
RERA project IDRERA-GRG-1031-2022
Registration certificate numberGGM/567/299/2022/42 DATED 25.05.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to06/01/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area6.1500 acres
Licence03 of 2022
Estimated cost of the project₹23,850.62 lakh (₹238.51 crore)
Total units (plots, apartments, shops)856
Unit sizes (carpet area, as declared)856 units averaging about 600 sq ft carpet (8 towers)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on01-07-2022
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-07-2022
Likely completion date31-08-2026

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on22-Oct-2026
Quarterly reports listed on the portal17

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹2,126.59 lakh (₹21.27 crore)
Borrowed from banks / financial institutions in the quarter₹-7.3 lakh (₹-0.07 crore)
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹630.34 lakh (₹6.3 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹1,169.07 lakh (₹11.69 crore)
Project bank account (escrow): deposited in the quarter₹1,488.61 lakh (₹14.89 crore)
Project bank account (escrow): withdrawn in the quarter₹1,508 lakh (₹15.08 crore)
Project bank account (escrow): balance at quarter end₹287.98 lakh (₹2.88 crore)
Units in the project (apartments / plots)970 apartments
Sold in the quarter970 apartments
EDC (development charges): paid / due as on date₹1,222.92 lakh (₹12.23 crore) paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 07-04-2022
  • Demarcation Plan: Obtained Approval 29-10-2021
  • Zoning Plan: Obtained Approval 10-01-2022
  • Service Plans: Obtained Approval 21-02-2023
  • Electricity Plans: Obtained Approval 26-04-2023
  • Site Plans: Obtained Approval 07-04-2022
  • Building Plans: Obtained Approval 07-04-2022
  • Fire NOC: Obtained Approval 28-10-2022

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 15 Oct 2026, for 30 Sep 2026
By part
  • Sub structure: 100%
  • Super structure: 100%
  • MEP: Mechanical (lifts, ventilation): 40%
  • MEP: Electrical (conduiting, wiring, fixtures): 96.495%
  • MEP: Plumbing and firefighting: 90%, Plumbing and PVC/CPVC piping complete for Towers 1 to 8; firefighting riser and underground complete with butterfly valve and hose reel
  • Finishing: Internal: 90%, Towers 1 to 7 up to 14 floors; Tower 8 up to 10th floor
  • Finishing: External: 80%, Towers 1 to 8
  • White washing: internal walls: 75%
  • White washing: external walls: 60%
  • Finishing: staircase with railing: 0%
  • Finishing: lift wells: 75%
  • Finishing: lift lobbies and common areas floor wise: 75%
  • Installation within flat/unit: doors and window panels: 75%
  • Installation within flat/unit: sanitary fixtures: 0%
  • Installation within flat/unit: modular kitchen: 0%
  • Installation within flat/unit: electrical fittings/lighting: 0%
  • Installation within flat/unit: gas piping: 0%
  • Installation other than flat/unit: lifts: 0%
  • Installation other than flat/unit: overhead tanks: 95%, Towers 2 to 8 complete; Tower 1 one tank complete
  • Installation other than flat/unit: underground water tank: 95%
  • Installation other than flat/unit: firefighting fittings and equipment as per CFO NOC: 85%
  • Installation other than flat/unit: electrical fittings in common areas: 0%
  • Compliance to environment/CRZ NOC conditions: 0%
  • Waterproofing of terraces: 80%
  • Entrance lobby finishing: 75%
  • Construction of compound wall: 95%
Unclear in the certificate
  • Table A is headed Building/Tower no. but no tower is named; the percentages apply to the project components and are not given separately for each tower.
  • Table B (common areas and facilities) percentages are hard to align with their line items in the scan, so they are not listed.
  • 'Nil' entries are recorded as 0 percent.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusPending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project1
Cases
Decided cases against RISEONIC REALTY PVT LTD (all its projects)1 (Complaint: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in