Sports Ville ( Affordable Group Housing Project)

Hcbs Promoters & Developers · Sector 2 & 35, Gurugram

Registered with RERA: Sep 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Hcbs Promoters & Developers

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSPORTS VILLE ( AFFORDABLE GROUP HOUSING PROJECT)
Builder (promoter)HCBS PROMOTERS & DEVELOPERS PVT. LTD
LocationSECTOR 2 & 35, GURUGRAM
RERA project IDRERA-GRG-542-2019
Registration certificate number228 OF 2017 DATED 19.09.2017
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to18/09/2021
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area6.85 acres
Licence15 of 2014 ( 09-06-2019) RENEWAL 15 OF 2014 ( 09.01.2020)
Estimated cost of the project₹18,190 lakh (₹181.9 crore)
Total units (plots, apartments, shops)1096
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder1 BHK: 321–324 sq ft carpet, 368 units; 2 BHK: 519 sq ft carpet, 728 units (source: the builder's registration form (Form A-H))
Units booked when registered842
Units unsold when registered254
Layout plan approved on10-04-2015
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date06-06-2019
Revised completion date28-02-2020
Infrastructure: projected completion03-12-2019
Infrastructure: percentage complete when registered100%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listQPR not uploaded
Latest report periodNot found in the records checked
Latest report submitted onNot found in the records checked
Quarterly reports listed on the portalNot found in the records checked

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed4
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 2; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project3
Cases
Decided cases against HCBS PROMOTERS & DEVELOPERS PVT. LTD (all its projects)6 (Complaint: 6)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026