Projects · SS GROUP PRIVATE LIMITED

Ss 100

Ss Group · Sector 49, Gurugram

Registered with RERA: Aug 2020

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for Sector 49; the exact site was not found.

The builder: Ss Group

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSS 100
Builder (promoter)SS GROUP PRIVATE LIMITED
LocationSOUTHERN PERIPHERAL ROAD, VIL L. BADSHAHPUR,SECTOR-49, GURUGRAM, HARYANA
RERA project IDRERA-GRG-705-2020
Registration certificate numberGGM/405/137/2020/21 DATED 17.08.2020
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to30/09/2024
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area1.334 acres
Licence28 OF 1997(05-05-24) 29 OF 1997(05-05-24) 30 OF 1997(05-05-24) 31 OF 1997(05-05-24) 32 OF 1997(05-05-24) 33 OF 1997(05-05-24)
Estimated cost of the project₹12,935 lakh (₹129.35 crore)
Total units (plots, apartments, shops)72
Unit sizes (carpet area, as declared)72 units averaging about 810 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on01-10-2019
Building plans approved on01-10-2019

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-10-2020
Likely completion date30-09-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on15-Oct-2026
Quarterly reports listed on the portal24

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹209.96 lakh (₹2.1 crore)
Spent on construction of apartments in the quarter₹183.46 lakh (₹1.83 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹26.5 lakh (₹0.27 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)72 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹0 paid; ₹649 lakh (₹6.49 crore) due
Approvals listed
  • Demarcation Plan: Obtained Approval 09-01-2019
  • Zoning Plan: Obtained Approval 09-01-2019
  • Site Plans: Obtained Approval 01-10-2019
  • Building Plans: Obtained Approval 01-10-2019
  • Fire NOC: Obtained Approval 24-12-2025

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 04 Oct 2026, for 30 Sep 2026
By part
  • SS100 - Sub Structure: 9.99%, Excavation and raft complete; basement levels 1 to 3 complete; water proofing in progress
  • SS100 - Super Structure: 35%, Walls, staircase, liftwells and lift lobbies complete; building stated as G+15
  • SS100 - Mechanical Work: 7.13%, In progress
  • SS100 - Electrical Work: 9.5%, In progress
  • SS100 - Plumbing & Fire Fighting: 7.13%, Nil in the status table
  • SS100 - Internal Finishing: 16.2%, Internal plaster and white washing complete; tiling and flooring in progress
  • SS100 - External Finishing: 11.26%, External plaster complete; compound wall complete
  • Internal Roads & Pavements: 80%
  • Parkings - Covered: 80%
  • Parkings - Open: 80%
  • Water Supply: 90%
  • Sewerage (chambers, lines, STP, septic tanks): 90%
  • Storm Water Drains: 90%
  • Landscaping & Tree Plantations: 70%
  • Street Lighting/Electrification: 80%
  • Treatment & Disposal of Sewage/STP: 90%
  • Rain Water Harvesting: 90%
  • Energy Management (Solar): 0%
  • Fire Protection & Fire Safety Equipments: 80%
  • Electrical Meter Room, Sub-Station, Receiving Station: 80%
  • Under Ground Water Tank: 90%
Unclear in the certificate
  • The line on the number of slabs laid in Table A (item 8) is cut off, so the number of slabs laid is not clear.
  • Table A shows plumbing and fire fighting as Nil in the status table, but its cumulative value and percentage (7.13%) are listed.
  • Total area on each floor in Table A (30423) has no unit stated.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed3
By statusFirst Hearing: 3
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against SS GROUP PRIVATE LIMITED (all its projects)158 (Complaint: 118; Execution of an earlier order: 27; Compensation: 13)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in