Registration

Project nameSS LINDEN FLOORS -III
Builder (promoter)SS GROUP PRIVATE LIMITED
LocationSS LINDEN, SECTOR -84 & 85
RERA project IDRERA-GRG-1182-2022
Registration certificate numberGGM/642/374/2022/117 DATED 13.12.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/10/2025
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area16824 acres
Licence105 OF 2013 dated 11.12.2013 as modified by the order dated 25.05.2021.
Estimated cost of the project₹25,009 lakh (₹250.09 crore)
Total units (plots, apartments, shops)325
Unit sizes (carpet area, as declared)4 units of 1,386 sq ft carpet (1 tower); 4 units of 1,439 sq ft carpet (1 tower); 48 units of 1,525 sq ft carpet (12 towers); 124 units of 1,538 sq ft carpet (31 towers); 20 units of 1,554 sq ft carpet (5 towers); 32 units of 1,565 sq ft carpet (8 towers); 4 units of 1,722 sq ft carpet (1 tower); 4 units of 2,000 sq ft carpet (1 tower); 12 units of 2,045 sq ft carpet (3 towers); 4 units of 2,264 sq ft carpet (1 tower); 4 units of 2,279 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on25-05-2021
Building plans approved on28-11-2022

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-01-2023
Likely completion date31-10-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/12/2025 (OCT-DEC)
Latest report submitted on07-Mar-2026
Quarterly reports listed on the portal12

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2025 (OCT-DEC))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹10,583.4 lakh (₹105.83 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹-6,869.44 lakh (₹-68.69 crore)
Spent on construction of apartments in the quarter₹2,494.03 lakh (₹24.94 crore)
Spent on infrastructure in the quarter₹71.2 lakh (₹0.71 crore)
Other costs in the quarter (EDC, taxes, etc.)₹1,968.87 lakh (₹19.69 crore)
Project bank account (escrow): deposited in the quarter₹7,621.63 lakh (₹76.22 crore)
Project bank account (escrow): withdrawn in the quarter₹11,418.06 lakh (₹114.18 crore)
Project bank account (escrow): balance at quarter end₹1,054.32 lakh (₹10.54 crore)
Units in the project (apartments / plots)212 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 25-05-2021
  • Demarcation Plan: Obtained Approval 01-09-2021
  • Zoning Plan: Obtained Approval 01-09-2021
  • Service Plans: Obtained Approval 01-02-2022
  • Electricity Plans: Obtained Approval 03-06-2024
  • Site Plans: Obtained Approval 25-05-2021
  • Building Plans: Obtained Approval 01-09-2022

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 02 Jan 2026, for 31 Dec 2025
Unclear in the certificate
  • Paragraph 5 refers to Table A and Table B, which give the percentage of work for each tower or building. These tables are not in the document, so no percentages are recorded.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registration
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against SS GROUP PRIVATE LIMITED (all its projects)158 (Complaint: 118; Execution of an earlier order: 27; Compensation: 13)