Projects · SS GROUP PRIVATE LIMITED
Ss Linden Floors -III
Ss Group · Sector 84 & 85, Gurugram
Registered with RERA: Dec 2022
Is it legal?
- RERA registered, valid till Oct 2025 (date has passed)
- HRERA has not opened any case of its own against this project
Will it be delivered on time?
- Deadline Oct 2025, never extended (date has passed)
- Occupation certificate (Nov 2024) covers: Residential building on Plot 12, Block-B, SS Linden (4 flats)
- Money: ₹191.4 crore spent of ₹191.4 crore (CA certificate, Dec 2025)
What's on offer?
- 260 units in 11 sizes, as declared to HRERA:
- 4 units of 1,386 sq ft carpet (1 tower)
- 48 units of 1,525 sq ft carpet (12 towers)
- 124 units of 1,538 sq ft carpet (31 towers)
- 20 units of 1,554 sq ft carpet (5 towers)
- 32 units of 1,565 sq ft carpet (8 towers)
- 12 units of 2,045 sq ft carpet (3 towers)
- 5 less common sizes: see the full list below
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
- 65 plots, 273–489 sq yd
Location
- Nearest metro: Millennium City Centre Gurugram, 18.9 km by road (52 min by car)
- Cyber City 59 min · Airport 43 min by car at 9:30 am
- Within 3 km: 2 hospitals, 1 school, 0 malls
The builder: Ss Group
- 12 projects registered in Gurugram, 4 lapsed
- 5 with an occupation certificate on record
- 158 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | SS LINDEN FLOORS -III |
|---|---|
| Builder (promoter) | SS GROUP PRIVATE LIMITED |
| Location | SS LINDEN, SECTOR -84 & 85 |
| RERA project ID | RERA-GRG-1182-2022 |
| Registration certificate number | GGM/642/374/2022/117 DATED 13.12.2022 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/10/2025 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 16824 acres |
| Licence | 105 OF 2013 dated 11.12.2013 as modified by the order dated 25.05.2021. |
| Estimated cost of the project | ₹25,009 lakh (₹250.09 crore) |
| Total units (plots, apartments, shops) | 325 |
| Unit sizes (carpet area, as declared) | 4 units of 1,386 sq ft carpet (1 tower); 4 units of 1,439 sq ft carpet (1 tower); 48 units of 1,525 sq ft carpet (12 towers); 124 units of 1,538 sq ft carpet (31 towers); 20 units of 1,554 sq ft carpet (5 towers); 32 units of 1,565 sq ft carpet (8 towers); 4 units of 1,722 sq ft carpet (1 tower); 4 units of 2,000 sq ft carpet (1 tower); 12 units of 2,045 sq ft carpet (3 towers); 4 units of 2,264 sq ft carpet (1 tower); 4 units of 2,279 sq ft carpet (1 tower) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 25-05-2021 |
| Building plans approved on | 28-11-2022 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-01-2023 |
|---|---|
| Likely completion date | 31-10-2025 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/12/2025 (OCT-DEC) |
| Latest report submitted on | 07-Mar-2026 |
| Quarterly reports listed on the portal | 12 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2025 (OCT-DEC))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹10,583.4 lakh (₹105.83 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹-6,869.44 lakh (₹-68.69 crore) |
| Spent on construction of apartments in the quarter | ₹2,494.03 lakh (₹24.94 crore) |
| Spent on infrastructure in the quarter | ₹71.2 lakh (₹0.71 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹1,968.87 lakh (₹19.69 crore) |
| Project bank account (escrow): deposited in the quarter | ₹7,621.63 lakh (₹76.22 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹11,418.06 lakh (₹114.18 crore) |
| Project bank account (escrow): balance at quarter end | ₹1,054.32 lakh (₹10.54 crore) |
| Units in the project (apartments / plots) | 212 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 02 Jan 2026, for 31 Dec 2025 |
|---|---|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against SS GROUP PRIVATE LIMITED (all its projects) | 158 (Complaint: 118; Execution of an earlier order: 27; Compensation: 13) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in