Summit Plaza
DLF · Sector 54, Gurugram
Registered with RERA: Sep 2021
Is it legal?
- RERA registered, valid till Jun 2026 (date has passed)
- HRERA opened a case of its own against the builder in Jun 2022 (still open)
Will it be delivered on time?
- Deadline Jun 2026, never extended (date has passed)
- Occupation certificate (Nov 2025) covers: Phase-C4 commercial building and three basements (no flats listed)
- Construction, as certified by the architect (Jan–Mar 2026):
- In progress: Summit plaza: super structure 99%, Summit plaza: sub structure 97%, Summit plaza: mep plumbing and firefighting 82%, Summit plaza: finishing internal 81%, Summit plaza: mep mechanical 79%, Summit plaza: finishing external 74%, and 1 more
- Money: ₹288.8 crore spent of ₹357.5 crore; ₹68.6 crore still to spend (CA certificate, Mar 2026)
What's on offer?
- 292 units: 0 sold, 292 unsold (builder's certificate, Mar 2026)
- Sizes declared at registration (311 units):
- 311 units averaging about 720 sq ft carpet (1 tower)
- The builder gave each tower's total carpet area, not each flat's size; averages divide that total by the number of units. HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Sector 53-54, 2.8 km by road (8 min by car)
- Cyber City 23 min · Airport 40 min by car at 9:30 am
- Within 3 km: 10 hospitals, 11 schools, 5 malls
The builder: DLF
- 14 projects registered in Gurugram
- 6 with an occupation certificate on record
- 18 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | SUMMIT PLAZA |
|---|---|
| Builder (promoter) | DLF LIMITED |
| Location | DLF CITY PHASE V, SECTOR 54 |
| RERA project ID | RERA-GRG-888-2021 |
| Registration certificate number | GGM/488/220/2021/56 DATED 21.09.2021 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/06/2026 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 2.65 acres |
| Licence | 1. 115 of 1995 (valid upto 28/12/2024) 2. 116 of 1995 (valid upto 28/12/2024) 3. 54 of 1996 (valid upto 29/04/2024) 4. 55 of 1996 (valid upto 29/04/2024) 5. 56 of 1996 (valid upto 29/04/2024) |
| Estimated cost of the project | ₹25,283 lakh (₹252.83 crore) |
| Total units (plots, apartments, shops) | 311 |
| Unit sizes (carpet area, as declared) | 311 units averaging about 720 sq ft carpet (1 tower) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 02-07-2021 |
| Building plans approved on | 02-07-2021 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-09-2021 |
|---|---|
| Likely completion date | 30-06-2026 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/03/2026 (JAN-MAR) |
| Latest report submitted on | 13-Apr-2026 |
| Quarterly reports listed on the portal | 18 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2026 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹692.56 lakh (₹6.93 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹25,806.16 lakh (₹258.06 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹3,075.56 lakh (₹30.76 crore) |
| Project bank account (escrow): deposited in the quarter | ₹500.12 lakh (₹5 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹3,740 lakh (₹37.4 crore) |
| Project bank account (escrow): balance at quarter end | ₹397.97 lakh (₹3.98 crore) |
| Units in the project (apartments / plots) | 292 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 31 Mar 2026, for 31 Mar 2026 |
|---|---|
| By part |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | First Hearing: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against DLF LIMITED (all its projects) | 18 (Complaint: 15; Compensation: 3) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in