Suncity's Monarch Residences

Dvok Buildcon · Sector 78, Gurugram

Registered with RERA: Jan 2026

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Dvok Buildcon

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameSUNCITY'S MONARCH RESIDENCES
Builder (promoter)DVOK BUILDCON LLP
LocationSECTOR 78, VILLAGE SHIKOPUR
RERA project IDRERA-GRG-2100-2025
Registration certificate numberGGM/1037/769/2026/09 DATED 22.01.2026
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/03/2031
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area9.506 acres
Licence. 121 of 2025 dated 17.07.2025 under NILP-2022
Estimated cost of the project₹2,45,251 lakh (₹2,452.51 crore)
Total units (plots, apartments, shops)900
Unit sizes (carpet area, as declared)16 units of 1,149 sq ft carpet (4 towers); 704 units of 1,333 sq ft carpet (4 towers); 4 units of 1,522 sq ft carpet (1 tower); 176 units of 1,744 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builder2 BHK; 3 BHK (source: the builder's floor plans uploaded to HRERA)
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on17-12-2025
Building plans approved on17-12-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-01-2026
Likely completion date31-03-2031

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on14-Oct-2026
Quarterly reports listed on the portal2

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹861.79 lakh (₹8.62 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹2,507.43 lakh (₹25.07 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹912.51 lakh (₹9.13 crore)
Project bank account (escrow): deposited in the quarter₹3,846.33 lakh (₹38.46 crore)
Project bank account (escrow): withdrawn in the quarter₹4,198 lakh (₹41.98 crore)
Project bank account (escrow): balance at quarter end₹58.05 lakh (₹0.58 crore)
Units in the project (apartments / plots)900 apartments
Sold in the quarter30 apartments
EDC (development charges): paid / due as on date₹2,324.36 lakh (₹23.24 crore) paid; ₹5,020.05 lakh (₹50.2 crore) due
Approvals listed
  • Demarcation Plan: Obtained Approval 20-11-2025
  • Zoning Plan: Obtained Approval 20-11-2025
  • Service Plans: Obtained Approval 10-03-2026
  • Electricity Plans: Obtained Approval 04-06-2025
  • Site Plans: Obtained Approval 20-11-2025
  • Building Plans: Obtained Approval 17-12-2025
  • Fire NOC: Obtained Approval 27-03-2026

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 09 Oct 2026, for 30 Sep 2026
By part
  • Regalia Tower: 11%, Excavation 100% done. Sub-structure is 11% of total proposed work. Super-structure, MEP and finishing are shown as yet to start (0%).
Unclear in the certificate
  • Table A shows work done during the quarter as 55047925, which is larger than the cumulative value till date of 6233853. The figures do not match.
  • Table A lists 50 slabs laid by end of quarter, but the super-structure rows say 'Yet To Start' at 0%. The two entries conflict.
  • No single overall percentage of construction completion is stated for the project. The 11% figure is for the sub-structure component of Regalia Tower only.
  • Table B common areas and facilities are marked as proposed with 0% work done, but no tower-level total is given for them.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against DVOK BUILDCON LLP (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in