Projects · MONIKA INFRASTRUCTURE PVT. LTD.
Tapasya One
Monika Infrastructure · Sector 53, Gurugram
Registered with RERA: Oct 2017
Is it legal?
- RERA registered, valid till Jun 2023 (date has passed)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jul 2024, open)
- Did not submit quarterly progress report (May 2022, open)
- Builder was repeatedly sent notices to comply with Section 42(1D) documents and the QPR; the Authority ordered scrutiny of its REP-I Part A-H documents (Nov 2019, open)
- 2 more cases: reply 4
Will it be delivered on time?
- Deadline Jun 2023, never extended (date has passed)
- Occupation certificate (Jul 2019) covers: Commercial colony buildings in Sector-53, Gurugram (no flats listed)
- Construction, as certified by the architect (Jan–Mar 2024):
- Done: Tower b
- In progress: Tower a 80%
- Money: ₹134 crore spent of ₹177 crore; ₹43 crore still to spend (CA certificate, Mar 2024)
What's on offer?
- 2 units sold (builder's certificate, Mar 2024)
Location
- Nearest metro: Sector 54 Chowk, 4.1 km by road (11 min by car)
- Cyber City 17 min · Airport 35 min by car at 9:30 am
- Within 3 km: 11 hospitals, 13 schools, 6 malls
The builder: Monika Infrastructure
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 0 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | TAPASYA ONE |
|---|---|
| Builder (promoter) | MONIKA INFRASTRUCTURE PVT. LTD. |
| Location | SECTOR 53, GURUGRAM |
| RERA project ID | RERA-GRG-301-2019 |
| Registration certificate number | 317 OF 2017 DATED 17.10.2017 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/06/2023 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 3.1918 acres |
| Licence | 5 OF 2001(31.08.2001) AND 115 OF 2004(27.07.2004) |
| Estimated cost of the project | ₹17,700 lakh (₹177 crore) |
| Total units (plots, apartments, shops) | 82 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | 2 |
| Units unsold when registered | 0 |
| Layout plan approved on | 16-08-2016 |
| Building plans approved on | 16-08-2016 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 30-06-2023 |
|---|---|
| Revised completion date | 30-06-2023 |
| Infrastructure: projected completion | 30-06-2023 |
| Infrastructure: percentage complete when registered | 80% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/03/2024 (JAN-MAR) |
| Latest report submitted on | 13-Jul-2024 |
| Quarterly reports listed on the portal | 22 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2024 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹14.51 lakh (₹0.15 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹1,037.74 lakh (₹10.38 crore) |
| Project bank account (escrow): deposited in the quarter | ₹1,063.97 lakh (₹10.64 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹1,052.25 lakh (₹10.52 crore) |
| Project bank account (escrow): balance at quarter end | ₹88.73 lakh (₹0.89 crore) |
| Units in the project (apartments / plots) | 82 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 31 Mar 2024, for 31 Mar 2024 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against MONIKA INFRASTRUCTURE PVT. LTD. (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026