Tarc Ishva

Tarc · Sector 63A, Gurugram

Registered with RERA: Sep 2024

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Tarc

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameTARC ISHVA
Builder (promoter)TARC LIMITED
LocationSECTOR 63A GURUGRAM
RERA project IDRERA-GRG-1704-2024
Registration certificate numberGGM/865/597/2024/92 DATED 04.09.2024
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/12/2031
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area6.9500 acres
Licence137 of 2023 Date 05.07.2023
Estimated cost of the project₹1,25,948.91 lakh (₹1,259.49 crore)
Total units (plots, apartments, shops)458
Unit sizes (carpet area, as declared)72 units of 219 sq ft carpet (1 tower); 2 units of 1,562 sq ft carpet (2 towers); 24 units of 1,586 sq ft carpet (2 towers); 68 units of 1,589 sq ft carpet (2 towers); 2 units of 1,631 sq ft carpet (2 towers); 40 units of 1,658 sq ft carpet (2 towers); 6 units of 2,079 sq ft carpet (3 towers); 24 units of 2,103 sq ft carpet (3 towers); 214 units of 2,157 sq ft carpet (3 towers); 6 units of 3,526 sq ft carpet (3 towers)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on14-08-2024
Building plans approved on14-08-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-09-2024
Likely completion date31-12-2031

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on15-Oct-2026
Quarterly reports listed on the portal8

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹8,377.27 lakh (₹83.77 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹4,638.3 lakh (₹46.38 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹4,717.31 lakh (₹47.17 crore)
Project bank account (escrow): deposited in the quarter₹8,377.27 lakh (₹83.77 crore)
Project bank account (escrow): withdrawn in the quarter₹8,377.27 lakh (₹83.77 crore)
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)611 apartments
Sold in the quarter33 apartments
EDC (development charges): paid / due as on date₹4,489.74 lakh (₹44.9 crore) paid; ₹878.21 lakh (₹8.78 crore) due
Approvals listed
  • Demarcation Plan: Obtained Approval 16-06-2025
  • Fire NOC: Obtained Approval 18-02-2026

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 05 Oct 2026, for 30 Sep 2026
By part
  • Tower-1: Sub-structure 100% done; super-structure 23% done; walls on floors and staircase under progress; lift wells, MEP and internal and external finishing not started (0%).
  • Tower-2: Sub-structure 90% done; super-structure 23% done; walls on floors and staircase under progress; waterproofing under progress (0%); MEP and finishing not started (0%).
  • Tower-3: Sub-structure 90% done; super-structure 15% done; walls on floors and staircase under progress; waterproofing under progress (0%); MEP and finishing not started (0%).
Unclear in the certificate
  • The certificate refers to Table B, but Table B is not in the copy provided.
  • No single overall percentage is stated for any tower, so the percentages are given by component in the stage notes.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registration
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusDisposed: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against TARC LIMITED (all its projects)2 (Execution of an earlier order: 1; Complaint: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in