Projects · DESI CONSTRUCTION PRIVATE LIMITED
Tathastu I
Desi Construction · Sector 5, Gurugram
Registered with RERA: Jan 2023
Is it legal?
- RERA registered, valid till Nov 2027
- HRERA opened a case of its own against the builder in Aug 2023 (still open):
- Why: did not submit approved service plans and estimates; required within 3 months of registration
- Latest: 08 Jul 2024 hearing: builder sought two months; next hearing 09 Sep 2024
- At stake: Forfeited security: two ICICI demand drafts of 25 lakh each; no other penalty
- 7 complaints about this project decided by HRERA since Nov 2023 (2 delay interest ordered, 2 refund ordered, 1 compensation ordered, 2 other orders)
Will it be delivered on time?
- Deadline Nov 2027, never extended
- No occupation certificate yet (not ready for possession)
- Construction 82% complete (architect, Jul–Sep 2026)
- Money: ₹355.9 crore spent of ₹497.8 crore; ₹120.4 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 2,167 units: 52 sold, 150 unsold (builder's certificate, Sep 2026)
- Flat types (BHK) as stated in the builder's floor plans uploaded to HRERA:
- 2 BHK + store: 646 sq ft carpet
Location
- Nearest metro: Sector 55–56, 31.4 km by road (62 min by car)
- Cyber City 76 min · Airport 81 min by car at 9:30 am
- Within 3 km: 0 hospitals, 2 schools, 0 malls
The builder: Desi Construction
- 2 projects registered in Gurugram
- 0 with an occupation certificate on record
- 25 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | TATHASTU I |
|---|---|
| Builder (promoter) | DESI CONSTRUCTION PRIVATE LIMITED |
| Location | SECTOR 5, VILLAGE SOHNA |
| RERA project ID | RERA-GRG-1258-2023 |
| Registration certificate number | GGM/676/408/2023/20 DATED 30.01.2023 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 14/11/2027 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 12.8847 acres |
| Licence | 189 OF 2022 |
| Estimated cost of the project | ₹49,777.05 lakh (₹497.77 crore) |
| Total units (plots, apartments, shops) | 2167 |
| Unit sizes (carpet area, as declared) | 435 units averaging about 180 sq ft carpet (5 towers); 1,732 units averaging about 650 sq ft carpet (8 towers) |
| Flat types (BHK), as stated by the builder | 2 BHK + store: 646 sq ft carpet (source: the builder's floor plans uploaded to HRERA) |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 23-01-2023 |
| Building plans approved on | 23-01-2023 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 15-02-2023 |
|---|---|
| Likely completion date | 14-11-2027 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 30-Oct-2026 |
| Quarterly reports listed on the portal | 14 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹1,573.21 lakh (₹15.73 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹-43.8 lakh (₹-0.44 crore) |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹208.22 lakh (₹2.08 crore) |
| Spent on infrastructure in the quarter | ₹323.56 lakh (₹3.24 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹381.77 lakh (₹3.82 crore) |
| Project bank account (escrow): deposited in the quarter | ₹1,105.31 lakh (₹11.05 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹993.41 lakh (₹9.93 crore) |
| Project bank account (escrow): balance at quarter end | ₹183.61 lakh (₹1.84 crore) |
| Units in the project (apartments / plots) | 2167 apartments |
| Sold in the quarter | 55 apartments |
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 05 Oct 2026 |
|---|---|
| Overall work complete | 82% |
| By part |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | Pending: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in