RERA’d by NeevHQ

Projects · HERO REALTY PRIVATE LIMITED

The Ark

Hero Realty · Sector 85, Gurugram

Registered with RERA: Jun 2023

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for Sector 85; the exact site was not found.

The builder: Hero Realty

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameTHE ARK
Builder (promoter)HERO REALTY PRIVATE LIMITED
LocationSECTOR 85, VILLAGE SIKANDARPU R BADHA, GURGRAM-122004
RERA project IDRERA-GRG-1363-2023
Registration certificate numberGGM/726/458/2023/70 DATED 07.06.2023
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to29/06/2026
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area5.0125 acres
Licence193 of 2022 dated 24.11.2022 valid upto 23.11.2027
Estimated cost of the project₹13,765 lakh (₹137.65 crore)
Total units (plots, apartments, shops)77
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on24-11-2022
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-06-2023
Likely completion date30-06-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/12/2025 (OCT-DEC)
Latest report submitted on15-Jan-2026
Quarterly reports listed on the portal10

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2025 (OCT-DEC))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹500 lakh (₹5 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹349.82 lakh (₹3.5 crore)
Project bank account (escrow): withdrawn in the quarter₹361 lakh (₹3.61 crore)
Project bank account (escrow): balance at quarter end₹105.23 lakh (₹1.05 crore)
Units in the project (apartments / plots)77 plots
Sold in the quarter1 plots
EDC (development charges): paid / due as on date₹468.73 lakh (₹4.69 crore) paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 24-11-2022
  • Demarcation Plan: Obtained Approval 24-11-2022
  • Zoning Plan: Obtained Approval 02-06-2023
  • Service Plans: Obtained Approval 26-06-2023
  • Electricity Plans: Obtained Approval 25-08-2023

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 09 Jan 2026, for 31 Dec 2025
Overall work complete100%
By part
  • Table A: Sub-structure: 0%
  • Table A: Super-structure: 0%
  • Table A: Mechanical MEP: 0%
  • Table A: Electrical MEP: 0%
  • Table A: Plumbing and firefighting MEP: 0%
  • Table A: Internal finishing: 0%
  • Table A: External finishing: 0%
  • Table A: Other including external development, horticulture, parks, street light, PHE, water supply and sewerage: 100%
  • Table B: Internal roads and pavements: 100%
  • Table B: Covered parking: 0%
  • Table B: Open parking: 0%
  • Table B: Water supply: 100%
  • Table B: Sewerage: 100%
  • Table B: Storm water drains: 100%
  • Table B: Landscaping and tree plantation: 100%
  • Table B: Parks and playgrounds: 100%
  • Table B: Children play equipment: 0%
  • Table B: Benches: 0%
  • Table B: Street lighting and electrification: 100%
  • Table B: Sewage treatment plant (STP): 100%
  • Table B: Solid waste management and disposal: 0%
  • Table B: Rain water harvesting: 100%
  • Table B: Energy management (solar): 0%
  • Table B: Fire protection and fire safety: 100%
  • Table B: Electrical meter room, sub-station, receiving station: 100%
  • Table B: Underground water tank: 100%
  • Table B: Compound wall: 100%
Unclear in the certificate
  • The signature date reads 09.01.2025 while the certifying date reads 09.01.2026; 09 Jan 2026 is used here.
  • Table A gives one set of figures for the residential plot, with no tower or block-wise split.
  • The overall 100% figure comes from a note that cites a completion certificate, not from a separate progress figure.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against HERO REALTY PRIVATE LIMITED (all its projects)1 (Complaint: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in