The Aspen
Whiteland Corporation · Sector 76, Gurugram
Registered with RERA: Jan 2023
Is it legal?
- RERA registered, valid till Dec 2030
- HRERA has not opened any case of its own against this project
Will it be delivered on time?
- Deadline Dec 2030, never extended
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- Done: Sub structure
- In progress: Super structure 79%, Electrical 30%, Plumbing and firefighting 25%, Internal finishing 18%, Mechanical 8%, External finishing 8%
- Money: ₹961.9 crore spent of ₹1,785.8 crore; ₹823.9 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 619 units: 600 sold, 19 unsold (builder's certificate, July - September 2026)
- Flat types (BHK) as stated in the builder's floor plans uploaded to HRERA:
- 2 BHK
- 3 BHK
- 619 units, as declared to HRERA:
- 619 units averaging about 3,070 sq ft carpet (9 towers)
- The builder gave each tower's total carpet area, not each flat's size; averages divide that total by the number of units.
Location
- Nearest metro: Millennium City Centre Gurugram, 16.9 km by road (48 min by car)
- Cyber City 54 min · Airport 45 min by car at 9:30 am
- Within 3 km: 2 hospitals, 1 school, 1 mall
The builder: Whiteland Corporation
- 12 projects registered in Gurugram
- 1 with an occupation certificate on record
- 1 buyer complaint decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | THE ASPEN |
|---|---|
| Builder (promoter) | WHITELAND CORPORATION PRIVATE LIMITED |
| Location | DARBARIPUR ROAD, SECTOR 76 |
| RERA project ID | RERA-GRG-1246-2022 |
| Registration certificate number | GGM/663/395/2023/07 DATED 12.01.2023 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/12/2030 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 11.96 acres |
| Licence | 91 of 2022 / 92 of 2022 |
| Estimated cost of the project | ₹1,78,580.23 lakh (₹1,785.8 crore) |
| Total units (plots, apartments, shops) | 731 |
| Unit sizes (carpet area, as declared) | 619 units averaging about 3,070 sq ft carpet (9 towers) |
| Flat types (BHK), as stated by the builder | 2 BHK; 3 BHK (source: the builder's floor plans uploaded to HRERA) |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 12-07-2022 |
| Building plans approved on | 12-01-2023 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-07-2023 |
|---|---|
| Likely completion date | 31-12-2030 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 14-Oct-2026 |
| Quarterly reports listed on the portal | 14 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹12,917 lakh (₹129.17 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹5,786 lakh (₹57.86 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹5,230 lakh (₹52.3 crore) |
| Project bank account (escrow): deposited in the quarter | ₹12,917 lakh (₹129.17 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹6,750 lakh (₹67.5 crore) |
| Project bank account (escrow): balance at quarter end | ₹8,302 lakh (₹83.02 crore) |
| Units in the project (apartments / plots) | 619 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹8,276 lakh (₹82.76 crore) paid; ₹8,276 lakh (₹82.76 crore) due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 07 Oct 2026, for July to September 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against WHITELAND CORPORATION PRIVATE LIMITED (all its projects) | 1 (Complaint: 1) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in