Projects · PYRAMID PROPMOTO PVT. LTD.
The Balcony
Pyramid Propmoto · Sector 93, Gurugram
Registered with RERA: May 2019
Is it legal?
- RERA registered, valid till Jan 2024 (date has passed)
- HRERA has opened 4 cases of its own against the builder over this project (4 open):
- Did not submit quarterly progress report (Jun 2022, open)
- Did not submit service estimates, plans and fire scheme approval required by registration conditions (Jun 2022, open). At stake: Registration could be revoked and penal proceedings started; no penalty imposed yet
- 2 more cases: reply 4
- 2 complaints about this project decided by HRERA since Nov 2023 (2 delay interest ordered)
Will it be delivered on time?
- Deadline Jan 2024, never extended (date has passed)
- 2 occupation certificates issued:
- Sep 2024: Towers A to G, community hall and ground-floor commercial block (731 flats)
- Apr 2025: 1st floor of commercial block only (no flats listed)
- Construction 100% complete (architect, Jan–Mar 2026)
- Money: ₹155.7 crore spent of ₹167.6 crore (CA certificate, Mar 2026)
What's on offer?
- 815 units sold (builder's certificate, Quarter ending March 2026)
- Affordable Residential Units: 731 of 731 sold
- Commercial Units: 84 of 89 sold
- 754 units, as declared to HRERA:
- 754 units averaging about 680 sq ft carpet (7 towers)
- The builder gave each tower's total carpet area, not each flat's size; averages divide that total by the number of units. HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Millennium City Centre Gurugram, 20.1 km by road (51 min by car)
- Cyber City 58 min · Airport 43 min by car at 9:30 am
- Within 3 km: 0 hospitals, 1 school, 0 malls
The builder: Pyramid Propmoto
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 5 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | THE BALCONY |
|---|---|
| Builder (promoter) | PYRAMID PROPMOTO PVT. LTD. |
| Location | SECTOR-93, GURUGRAM |
| RERA project ID | RERA-GRG-245-2019 |
| Registration certificate number | GGM/334/66/2019/28 DATED 13.05.2019 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 03/01/2024 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 5.0 acres |
| Licence | 01 of 2019 dated 04.01.2019 |
| Estimated cost of the project | ₹14,833 lakh (₹148.33 crore) |
| Total units (plots, apartments, shops) | 754 |
| Unit sizes (carpet area, as declared) | 754 units averaging about 680 sq ft carpet (7 towers) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 12-04-2019 |
| Building plans approved on | 12-04-2019 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-06-2019 |
|---|---|
| Likely completion date | 03-01-2024 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/03/2026 (JAN-MAR) |
| Latest report submitted on | 26-Jun-2026 |
| Quarterly reports listed on the portal | 27 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2026 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 820 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹819.59 lakh (₹8.2 crore) paid; ₹-3.86 lakh (₹-0.04 crore) due |
| Approvals listed | Not found in the records checked |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 31 Mar 2026 |
|---|---|
| Overall work complete | 100% |
| By part |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 2 |
|---|---|
| Cases |
|
| Decided cases against PYRAMID PROPMOTO PVT. LTD. (all its projects) | 5 (Complaint: 5) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in