Projects · ASHAINA LANDCRAFT REALTY PVT. LTD.
The Centre Court
Ashaina Landcraft Realty · Sector 88, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registered, valid till Sep 2025 (date has passed)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not apply for registration extension or submit completion/occupation certificate or requisite documents (Jun 2022, open)
- Did not adhere to declared time to complete The Centre Court project (Jun 2022, open)
- Did not submit the quarterly progress report (May 2022, open)
- 3 more cases: reply 4
- 1 complaint about this project decided by HRERA since Nov 2023 (1 refund ordered)
Will it be delivered on time?
- Original deadline Jun 2020, extended to Sep 2025
- 2 occupation certificates issued:
- Apr 2024: Group housing colony: 476 residential and 134 EWS units (610 flats)
- Aug 2025: Towers 2-5, basements, EWS block, community building (635 flats)
- Quarterly progress report shown as "not uploaded" by HRERA
What's on offer?
- Flat types (BHK) as stated in the builder's floor plans uploaded to HRERA:
- 2 BHK
- 3 BHK: 888–1,292 sq ft carpet
Location
- Nearest metro: Millennium City Centre Gurugram, 17.8 km by road (48 min by car)
- Cyber City 54 min · Airport 38 min by car at 9:30 am
- Within 3 km: 0 hospitals, 1 school, 0 malls
Location shown for Sector 88; the exact site was not found.
The builder: Ashaina Landcraft Realty
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 11 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | THE CENTRE COURT |
|---|
| Builder (promoter) | ASHAINA LANDCRAFT REALTY PVT. LTD. |
|---|
| Location | SEC 88-A, VILLAGE HARSARU, GU RUGRAM |
|---|
| RERA project ID | RERA-GRG-440-2019 |
|---|
| Registration certificate number | 46 OF 2017 DATED 11.08.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 30/09/2025 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 6.119 acres |
|---|
| Licence | 46 of 2013 dated 08-06-2013 |
|---|
| Estimated cost of the project | ₹66,600 lakh (₹666 crore) |
|---|
| Total units (plots, apartments, shops) | 476 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | 2 BHK; 3 BHK: 888–1,292 sq ft carpet (source: the builder's floor plans uploaded to HRERA) |
|---|
| Units booked when registered | 289 |
|---|
| Units unsold when registered | 187 |
|---|
| Layout plan approved on | 18-06-2015 |
|---|
| Building plans approved on | 18-06-2015 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 30-06-2020 |
|---|
| Revised completion date | 30-06-2020 |
|---|
| Infrastructure: projected completion | 30-06-2020 |
|---|
| Infrastructure: percentage complete when registered | 41.48% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|
| Latest report period | Not found in the records checked |
|---|
| Latest report submitted on | Not found in the records checked |
|---|
| Quarterly reports listed on the portal | Not found in the records checked |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | - Not an occupation or completion certificate. The document is a HRERA registration certificate under section 7(3) of RERA, with a covering letter and a receipt dated 15 Apr 2024: covers Group housing colony 'The Center Court' at Village Harsaru, Sector-88A, Gurugram. Registered part of project is 6.119 acres (24762.71 sq m) out of 14.025 acres licensed. Covers 610 saleable units: 476 residential units and 134 EWS units. Registration valid from 30 Dec 2020 to 30 Sep 2025.. Addressed to Ashiana Landcraft Realty Private Limited. Unclear in the document: The document is not an occupation or completion certificate, so no occupancy or completion details are given.; The certificate states a licence validity of 07 Jun 2024 and a registration validity up to 30 Sep 2025, but does not state any completion or occupancy status.; The certificate mentions an earlier registration dated 11 Aug 2017 valid up to 30 Jun 2020 plus COVID extension to 29 Dec 2020.; The covering letter dated 30 Dec 2024 asks HRERA to update the promoter's communication details on its portal. It says the project is now run by a new management after an NCLT order dated 11 Aug 2023.
- Occupation Certificate dated 12 Aug 2025: covers Tower-2, Tower-3, Tower-4, Tower-5, two level basements, EWS block and community building of the group housing colony over an area of 14.025 acres (License no. 46 of 2013 dated 08.06.2013) in Sector-88A, Gurugram, developed by Brock Developer Pvt. Ltd in collaboration with Ashiana Landcraft Realty Pvt. Ltd. Towers 2 to 5 have 119 dwelling units each (476 in total). The EWS block has 159 units. Floors: Towers 2 and 5 G+29, Towers 3 and 4 G+29, EWS block G/S+9, community building G+2.. Addressed to Ashiana Landraft Reality Pvt. Ltd.. Composition fees for variations from approved plans: ₹68,385. Unclear in the document: The applicant's name is spelled two ways in the document: Ashiana Landraft Reality Pvt. Ltd. (addressee) and Ashiana Landcraft Realty Pvt. Ltd. (subject line).; The dwelling unit total of 635 is the sum of 476 main dwelling units and 159 EWS units. The document lists these separately and does not state a combined total.; The basement row in the approved area table is partly unclear in the scanned text, so the basement area figures may not be exact.
|
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 6 |
|---|
| By status | Online Complaint Not Yet Received At Office: 1; First Hearing: 3; Pending: 2 |
|---|
| Proceedings | - RERA-GRG-2659-2022: The page does not state what the case is about. It is listed as RERA-GRG-2659-2022, titled HARERA Gurugram (through an individual) v/s Ashaina Landcraft Realty Pvt. Ltd., with the party type shown as Self. Status: The page shows the online complaint as not yet received at the office. Complaint dispatch is marked NA, and the next date of hearing is Not Yet.
- RERA-GRG-2849-2022: Show cause notice to the promoter for not applying for extension of registration, not submitting a completion, part completion or occupation certificate, and not submitting requisite documents. The Authority itself started the proceeding against the promoter, Ashaina Landcraft Realty Pvt. Ltd. Status: Listed for first hearing on 28 Jun 2022. The listing shows status 'First Hearing' with no proceedings, bench order or order recorded. Latest: 28 Jun 2022, First hearing listed. The listing shows status 'First Hearing' with no proceedings recorded.
- RERA-GRG-2850-2022: Suo motu proceeding by the Authority on the promoter's alleged violation of section 4(2)(l)(C) of the RERA Act, 2016, for not adhering to the declared time to complete The Centre Court project in Gurugram. Status: Disposed of on 17 Sep 2024. The Authority noted that the project's registration continuation was granted under section 7(3), valid up to 30 Sep 2025, and closed the matter. The case page still shows the status as PENDING. Latest: 17 Sep 2024, Promoter's representative filed a reply to the show-cause notice. No one appeared for the promoter at hearing. The Authority noted the registration continuation under section 7(3) valid up to 30 Sep 2025 and disposed of the matter. Outcome: Matter disposed of by the Authority on 17 Sep 2024, noting the project's registration continuation granted under section 7(3), valid up to 30 Sep 2025.
- RERA-GRG-2911-2022: Show cause notice to the promoter for not submitting the quarterly progress report. The case was listed in the names of the Authority and a complainant against the promoter company Ashaina Landcraft Realty Pvt. Ltd. Status: First hearing listed for 27 Jun 2022. The hearing status shows FIRST HEARING, with no proceedings recorded and no order uploaded. Latest: 27 Jun 2022, First hearing listed at the HARERA office, Gurugram. The page shows the hearing status as FIRST HEARING, with no proceedings or bench order recorded.
- RERA-GRG-5060-2022: A complaint (RERA-GRG-5060-2022) listed as HARERA Gurugram through the complainant versus Ashaina Landcraft Realty Pvt. Ltd., the promoter. The page does not state the reason for the complaint. Status: Listed for first hearing on 30 Jun 2022. The listing shows status as first hearing, with no order uploaded. No later hearing date is shown on the page. Latest: 16 Jul 2022, A document titled 'new complaint' was submitted by the complainant and received under a Dak ID.
- RERA-GRG-5240-2019: Filing of REP-I Part (A-H) on the HARERA website for the registered project The Centre Court in Sector-88A, Gurugram, developed by M/s Ashiana Landcraft Realty Pvt Ltd. The Authority directed scrutiny of the filing and asked the promoter to make online corrections and submit hard copies before the next hearing. Status: Pending. The next hearing is listed for 17 Feb 2020. Latest: 16 Jul 2020, Third notice under Section 42(1D) dispatched to the promoter.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 1 |
|---|
| Cases | |
|---|
| Decided cases against ASHAINA LANDCRAFT REALTY PVT. LTD. (all its projects) | 11 (Complaint: 11) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in