Projects · IREO GRACE REALTECH PVT.LTD.
The Corridors (Phase 2)
IREO Grace Realtech · Sector 67, Gurugram
Registered with RERA: Dec 2017
Is it legal?
- RERA registered, valid till Jun 2021 (date has passed)
- HRERA has opened 7 cases of its own against the builder over this project (7 open):
- Did not file REP-I (Part A to H) on web portal for offline registered project (Jun 2022, open)
- Did not submit quarterly progress report, prompting show-cause notice (May 2022, open)
- Did not submit completion or occupation certificate after registration extension lapsed (Jun 2022, open)
- 4 more cases: reply 4
Will it be delivered on time?
- Deadline Jan 2022, never extended (date has passed)
- Occupation certificate (Jan 2022) covers: Clusters A, B, C, EWS block, shops, community centre (772 flats)
- Construction, as certified by the architect (Apr–Jun 2026):
- Done: Cluster a, Cluster b, Cluster c
- Money: ₹734.5 crore spent of ₹829.6 crore; ₹95.1 crore still to spend (CA certificate, Jun 2026)
Location
- Nearest metro: Sector 55–56, 8.4 km by road (28 min by car)
- Cyber City 52 min · Airport 61 min by car at 9:30 am
- Within 3 km: 10 hospitals, 17 schools, 3 malls
The builder: IREO Grace Realtech
- 3 projects registered in Gurugram, 1 lapsed
- 2 with an occupation certificate on record
- 272 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | THE CORRIDORS (PHASE 2) |
|---|
| Builder (promoter) | IREO GRACE REALTECH PVT.LTD. |
|---|
| Location | SECTOR 67-A, VILLAGE DHUMASPU R & MAIDAWAS, TEHSIL SOHNA, GURUGRAM, HARYANA |
|---|
| RERA project ID | RERA-GRG-1644-2024 |
|---|
| Registration certificate number | 377 OF 2017 DATED 07.12.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 30/06/2021 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 13.152 acres |
|---|
| Licence | 5 of 2013 Dated 21.02.2013 |
|---|
| Estimated cost of the project | ₹79,883.38 lakh (₹798.83 crore) |
|---|
| Total units (plots, apartments, shops) | 658 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 437 |
|---|
| Units unsold when registered | 221 |
|---|
| Layout plan approved on | 31-05-2013 |
|---|
| Building plans approved on | 31-05-2013 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 30-06-2021 |
|---|
| Revised completion date | 27-01-2022 |
|---|
| Infrastructure: projected completion | 31-07-2024 |
|---|
| Infrastructure: percentage complete when registered | 99% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/06/2026 (APR-JUN) |
|---|
| Latest report submitted on | 29-Jul-2026 |
|---|
| Quarterly reports listed on the portal | 31 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2026 (APR-JUN))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹5,389.88 lakh (₹53.9 crore) |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹1,287.29 lakh (₹12.87 crore) |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹900.42 lakh (₹9 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹5,389.88 lakh (₹53.9 crore) |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹5,856.29 lakh (₹58.56 crore) |
|---|
| Project bank account (escrow): balance at quarter end | ₹9.5 lakh (₹0.1 crore) |
|---|
| Units in the project (apartments / plots) | 672 apartments |
|---|
| Sold in the quarter | 23 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹5,321.88 lakh (₹53.22 crore) paid; ₹0 due |
|---|
| Approvals listed | - Demarcation Plan: Obtained Approval 28-11-2014
- Zoning Plan: Obtained Approval 31-05-2013
- Service Plans: Obtained Approval 21-02-2013
- Electricity Plans: Obtained Approval 23-10-2019
- Site Plans: Obtained Approval 31-05-2013
- Building Plans: Obtained Approval 31-05-2013
- Fire NOC: Obtained Approval 31-05-2013
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 07 Jul 2026, for 30 Jun 2026 |
|---|
| By part | - Cluster A (Buildings A1-A5): 100%, All listed sub-structure, super-structure, MEP and finishing items shown as completed, including terrace waterproofing, entrance lobby and compound wall
- Cluster B (Buildings B5-B8): 100%, All listed sub-structure, super-structure, MEP and finishing items shown as completed, including terrace waterproofing, entrance lobby and compound wall
- Cluster C (Buildings C8-C11): 100%, Listed sub-structure, super-structure, MEP and finishing items shown as 100% complete; later checklist items not visible in the copy
|
|---|
| Unclear in the certificate | - No single overall percentage is stated; the figures are given per component in Table A.
- Cluster C section of Table A is cut off after item 8, so items 9 to 20 are not visible.
- Quarterly work-done value for the period is shown as nil for most Cluster A and B components, so no percent done in the quarter is stated.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | - Part Occupation Certificate dated 27 Jan 2022: covers Buildings in Cluster-A (Buildings A1 to A5), Cluster-B (Buildings B5 to B8), Cluster-C (Buildings C8 to C11), EWS Block-2, Convenient Shopping-1 and Shopping-2, and the Community Building in the Group Housing Colony on 37.512 acres under licence no. 5 of 2013, Sector-67A, Gurugram. Covers 658 main dwelling units and 114 EWS units, plus shops and a community centre.. Addressed to Precision Realtors Pvt. Ltd. and others. Composition fees for variations from approved plans: ₹69,30,560
|
|---|
| Corrigenda / addenda to the registration | - Extension of registration certificate (Form REP-V), Extension No. 01 of 2021, continuing the original registration for The Corridors Phase-2: The registration of The Corridors Phase-2 in Sector 67-A, Gurugram, is extended by six months and is now valid till 30 June 2021. The project is a Group Housing project with a registered area of 13.512 acres (54,683.064 sq m), a total licensed area of 37.512 acres, a total FAR of 92,954.53 sq m and 658 units. The promoter/license holder is M/s Precision Relators Pvt. Ltd. & 3 others, and the developer is M/s Ireo Grace Realtech Pvt Ltd. The extension is subject to these conditions: the promoter must submit renewed licence, Environment Clearance, Beneficial Interest Permission, revised service plans and estimates, and AAI NOC within 1 month of the certificate; must submit the occupation certificate when received; must offer to execute and register a conveyance deed in favour of allottees; and any tax, charge, fee or levy increase after the scheduled completion date must not be charged to the allottee. The extension is granted without prejudice to allottees' rights under the Act, as the promoter has not completed the project within the declared timeline. If the conditions are not met, the Authority may take action, including revoking the registration.
|
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 7 |
|---|
| By status | First Hearing: 3; Online Complaint Not Yet Received At Office: 2; Pending: 2 |
|---|
| Proceedings | - RERA-GRG-2665-2022: Non-filing of REP-I (Part A to H) on the Authority's web portal for an offline registered project, which was registered with either the Interim Real Estate Regulatory Authority, Panchkula or HRERA Gurugram. The Authority started the case against the promoter, IREO Grace Realtech Pvt. Ltd. Status: First hearing listed for 29 Jun 2022 at 11:00 am in HARERA Gurugram. The page records no order or proceedings of the day. Latest: 29 Jun 2022, First hearing scheduled at 11:00 am in HARERA Gurugram, where the promoter may appear and say anything in the matter. The listing status shows 'First Hearing' with no order recorded.
- RERA-GRG-3028-2022: Case RERA-GRG-3028-2022 lists HARERA Gurugram as the party against Ireo Grace Realtech Pvt. Ltd. The page gives no details of the complaint's subject. Status: Online complaint not yet received at office. Complaint not yet dispatched. No hearing date set.
- RERA-GRG-3536-2022: Show cause notice to the promoter, IREO Grace Realtech Pvt Ltd, for not submitting a quarterly progress report. The Authority asked the promoter to appear and give a written reply. Status: First hearing listed for 27 Jun 2022. The page shows no proceedings of the day, bench order or order uploaded. Latest: 27 Jun 2022, First hearing listed in the case. The page records the status as First Hearing, with no proceedings or order shown.
- RERA-GRG-3891-2022: Suo motu proceeding, started by the Authority itself, against the promoter for alleged violation of Section 4(2)(l)(C) of the Act. The alleged violation is not submitting a completion certificate, part completion certificate or occupation certificate after the extension of the project's registration lapsed. Status: Pending. The last order, dated 20 Sep 2024, says the status of the occupation certificate with respect to the registered area is to be examined and the matter put up on file. The next hearing date is not stated in that order. Latest: 24 Sep 2024, Another reply to the show-cause notice received by the Authority.
- RERA-GRG-3895-2022: Case RERA-GRG-3895-2022 lists HARERA Gurugram (through an official) as the complainant against IREO Grace Realtech Pvt. Ltd. The page does not state what the case is about. Status: The page shows the online complaint as not yet received at the office. The next hearing date is 'Not Yet'. No hearing, notice or order is listed.
- RERA-GRG-5068-2022: Complaint no. RERA-GRG-5068-2022, titled HARERA Gurugram through a named representative versus IREO GRACE REALTECH PVT. LTD. (the promoter). The case page does not state the grounds of the complaint. Status: At first hearing stage. The next hearing is listed for 30 Jun 2022. The listing shows status 'FIRST HEARING' with no proceedings or order recorded. Latest: 16 Jul 2022, Document received under Dak ID 38015 from the complainant's side, marked 'NEW COMPLAINT'.
- RERA-GRG-5314-2019: Whether the promoter (IREO Grace Realtech Pvt. Ltd.) failed to file the mandatory REP-I Part A to H project updates and quarterly progress reports on the Authority's web portal, as required under section 11(1) of the Act and rule 14(1)(d) of the Rules. The Authority started this case itself against the promoter. Status: Pending. The last recorded hearing date is 24 Feb 2020 (final personal hearing). The record shows a fourth notice under section 42(1D) dispatched on 20 Jul 2020, with no final decision recorded. Latest: 20 Jul 2020, Fourth notice under section 42(1D) dispatched, with dispatch ID recorded. Penalty: Rs 25,000 per day from 31 Dec 2019 while the default continues, cumulatively up to five percent of the estimated project cost, as ordered on 22 Jan 2020. No record of the penalty being paid or waived.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|
| Decided cases against IREO GRACE REALTECH PVT.LTD. (all its projects) | 272 (Execution of an earlier order: 58; Complaint: 172; Compensation: 42) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in