Projects · 1000 TREES HOUSING PRIVATE LIMITED
The Grove At Sanctuary
1000 Trees Housing · Sector 105, Gurugram
Registered with RERA: Feb 2026
Is it legal?
- RERA registered, valid till Oct 2028
- HRERA has not opened any case of its own against this project
Will it be delivered on time?
- Deadline Oct 2028, never extended
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- In progress: Sub structure 40%, Super structure 0%, Mep 0%, Finishing 0%
- Money: ₹15.6 crore spent of ₹174.8 crore; ₹159.2 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 65 units sold (builder's certificate, Sep 2026)
- Service Apartments/Shop: 65 sold
- 206 units in 33 sizes, as declared to HRERA:
- 8 units of 133 sq ft carpet
- 8 units of 137 sq ft carpet
- 41 units of 295 sq ft carpet
- 8 units of 296 sq ft carpet
- 45 units of 297 sq ft carpet
- 20 units of 300 sq ft carpet
- 27 less common sizes: see the full list below
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 7.5 km by road (9 min by car)
- Cyber City 48 min · Airport 26 min by car at 9:30 am
- Within 3 km: 9 hospitals, 3 schools, 1 mall
The builder: 1000 Trees Housing
- 3 projects registered in Gurugram
- 0 with an occupation certificate on record
- 0 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | THE GROVE AT SANCTUARY |
|---|---|
| Builder (promoter) | 1000 TREES HOUSING PRIVATE LIMITED |
| Location | SECTOR 105, NEAR DAULATABAD F LYOVER, DWARKA EXPRESSWAY |
| RERA project ID | RERA-GRG-2143-2025 |
| Registration certificate number | GGM/1040/772/2026/12 DATED 19.02.2026 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/10/2028 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 2.7620 acres |
| Licence | Valid upto 127 OF 2012 (27.12.2027) |
| Estimated cost of the project | ₹17,480.5 lakh (₹174.81 crore) |
| Total units (plots, apartments, shops) | 206 |
| Unit sizes (carpet area, as declared) | 2 units of 131 sq ft carpet; 8 units of 133 sq ft carpet; 4 units of 136 sq ft carpet; 8 units of 137 sq ft carpet; 2 units of 138 sq ft carpet; 4 units of 149 sq ft carpet; 4 units of 160 sq ft carpet; 1 unit of 164 sq ft carpet (1 tower); 5 units of 165 sq ft carpet; 4 units of 173 sq ft carpet; 4 units of 184 sq ft carpet; 4 units of 190 sq ft carpet; 4 units of 195 sq ft carpet; 2 units of 233 sq ft carpet; 2 units of 248 sq ft carpet; 4 units of 271 sq ft carpet; 4 units of 274 sq ft carpet; 2 units of 276 sq ft carpet; 1 unit of 286 sq ft carpet (1 tower); 41 units of 295 sq ft carpet; 8 units of 296 sq ft carpet; 45 units of 297 sq ft carpet; 20 units of 300 sq ft carpet; 5 units of 303 sq ft carpet; 1 unit of 305 sq ft carpet (1 tower); 5 units of 307 sq ft carpet; 4 units of 314 sq ft carpet; 1 unit of 332 sq ft carpet (1 tower); 2 units of 333 sq ft carpet; 1 unit of 343 sq ft carpet (1 tower); 2 units of 490 sq ft carpet; 1 unit of 599 sq ft carpet (1 tower); 1 unit of 1,135 sq ft carpet (1 tower) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 19-12-2025 |
| Building plans approved on | 19-12-2025 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 31-10-2025 |
|---|---|
| Likely completion date | 30-10-2028 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 21-Oct-2026 |
| Quarterly reports listed on the portal | 2 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹616.01 lakh (₹6.16 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹-495.55 lakh (₹-4.96 crore) |
| Spent on construction of apartments in the quarter | ₹53.03 lakh (₹0.53 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹151.41 lakh (₹1.51 crore) |
| Project bank account (escrow): deposited in the quarter | ₹431.2 lakh (₹4.31 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹480 lakh (₹4.8 crore) |
| Project bank account (escrow): balance at quarter end | ₹0.96 lakh (₹0.01 crore) |
| Units in the project (apartments / plots) | 206 apartments |
| Sold in the quarter | 85 apartments |
| EDC (development charges): paid / due as on date | ₹717.99 lakh (₹7.18 crore) paid; ₹725.28 lakh (₹7.25 crore) due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | for Sep 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against 1000 TREES HOUSING PRIVATE LIMITED (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in