Projects · SS GROUP PVT. LTD.
The Leaf
Ss Group · Sector 85, Gurugram
Registered with RERA: May 2019
Is it legal?
- RERA registered, valid till Jun 2023 (date has passed)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Did not submit quarterly progress report; show-cause notice issued 31 May 2022 (May 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jul 2024, open)
- 3 more cases: reply 4
- 12 complaints about this project decided by HRERA since Nov 2023 (3 delay interest ordered, 7 refund ordered, 2 dismissed, withdrawn or settled)
Will it be delivered on time?
- Original deadline Dec 2019, extended to Jun 2023
- The order keeps buyers' right to a refund or interest for the delay
- Occupation certificate (Aug 2021) covers: Block B-9 (30 flats), latest memo (30 flats)
- Construction, as certified by the architect (Jul–Sep 2026):
- Money: ₹487.5 crore spent of ₹483.8 crore (CA certificate, Sep 2026)
What's on offer?
- Registration now covers 659 flats
Location
- Nearest metro: Millennium City Centre Gurugram, 18.8 km by road (51 min by car)
- Cyber City 58 min · Airport 42 min by car at 9:30 am
- Within 3 km: 0 hospitals, 1 school, 0 malls
The builder: Ss Group
- 12 projects registered in Gurugram, 4 lapsed
- 5 with an occupation certificate on record
- 158 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | THE LEAF |
|---|
| Builder (promoter) | SS GROUP PVT. LTD. |
|---|
| Location | SECTOR-85, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-161-2019 |
|---|
| Registration certificate number | GGM/329/61/2019/23 DATED 01.05.2019 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 30/06/2023 |
|---|
| Registered with | HRERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 11.093 acres |
|---|
| Licence | 81 of 2011 (16-09-2011) |
|---|
| Estimated cost of the project | ₹43,546 lakh (₹435.46 crore) |
|---|
| Total units (plots, apartments, shops) | 668 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 422 |
|---|
| Units unsold when registered | 246 |
|---|
| Layout plan approved on | 04-02-2015 |
|---|
| Building plans approved on | 04-02-2015 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 31-12-2016 |
|---|
| Revised completion date | 31-12-2019 |
|---|
| Infrastructure: projected completion | 31-12-2019 |
|---|
| Infrastructure: percentage complete when registered | 16% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
|---|
| Latest report submitted on | 15-Oct-2026 |
|---|
| Quarterly reports listed on the portal | 29 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹0 |
|---|
| Units in the project (apartments / plots) | 659 apartments |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
|---|
| Approvals listed | - Demarcation Plan: Obtained Approval 20-09-2011
- Zoning Plan: Obtained Approval 20-09-2011
- Service Plans: Obtained Approval 02-07-2015
- Electricity Plans: Obtained Approval 04-08-2021
- Site Plans: Obtained Approval 08-08-2013
- Building Plans: Obtained Approval 08-08-2013
- Fire NOC: Obtained Approval 06-01-2022
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 03 Oct 2026, for 30 Sep 2026 |
|---|
| By part | - TOWER-T1: 100%, Structure of S+25 floors complete; all slabs laid; MEP, plastering, flooring and finishing shown as complete; work done during the quarter shown as Nil
|
|---|
| Unclear in the certificate | - Certificate refers to Table B, but Table B is not included in the document.
- Table A shows no overall percentage for the project, only component-wise figures for TOWER-T1.
- Table A shows Water Proofing of the sub-structure as NIL, and compound wall and some installation items as NA.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|
| Corrigenda / addenda to the registration | - Extension of Registration Certificate (Form REP-V), Extension No. 05 of 2020, for the real estate project The Leaf. The user described it as a corrigendum or addendum, but the document itself is an extension. dated 20 Jan 2020: The Authority extended the registration of The Leaf, a group housing project in Sector-85, Gurugram, under Extension No. 05 of 2020. It was originally granted vide registration no. 2019/23, revised as 2020/05. The extension is valid for one year, until 31 Dec 2020. The certificate records a licensed area of 11.093 acres, 8 towers (B1 to B10 plus EWS, listed as T1, T2, T3, B1 to B10) and 659 units. The total FAR registered is 78131.97 sq mtrs. The license holder is Shiva Profins Pvt. Ltd. and the developer is SS Group Pvt. Ltd. The certificate sets conditions. The promoter must renew the license within 3 months of the certificate, submit the occupation certificate when received, offer to execute and register a conveyance deed, deposit 70 percent of amounts realised in a separate account, comply with the Act and rules, and not contravene other applicable laws. If conditions are not met, the Authority may revoke the registration.
|
|---|
| Extensions of registration | |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 5 |
|---|
| By status | Scrutinized: 1; First Hearing: 3; Online Complaint Not Yet Received At Office: 1 |
|---|
| Proceedings | - RERA-GRG-2184-2020: A proceeding the Authority started against the promoter, SS Group Pvt. Ltd., under case RERA-GRG-2184-2020. The page does not state what the complaint or notice is about. Status: Scrutinized. The page shows no next hearing date. Latest: 14 Aug 2020, The case was listed for hearing with the status 'New Complaint'. No proceedings of the day are recorded.
- RERA-GRG-3181-2022: Show cause notice to the promoter SS Group Pvt. Ltd. for not submitting a quarterly progress report. Status: First hearing listed for 27 Jun 2022 at 11.00 am in Gurugram. The page shows no proceedings, bench or order for that date. Latest: 27 Jun 2022, First hearing listed. The listing shows status as First Hearing, with no proceedings of the day, bench or order recorded.
- RERA-GRG-3338-2024: Suo motu monitoring by the Authority of the promoter's alleged violation of Section 4(2)(l)(C) of the RERA Act 2016 for The Leaf project, Gurugram, registered under certificate GGM/329/67/2019 dated 01 May 2019. Status: Order uploaded on 27 Aug 2024. The matter was ordered to be put on file at the first hearing. The case page shows the registration certificate status as RC Expired. No next hearing date is shown. Latest: 27 Aug 2024, Order from the first hearing uploaded.
- RERA-GRG-3637-2022: Proceeding RERA-GRG-3637-2022 listed as HARERA Gurugram versus SS Group Pvt. Ltd. (the promoter). The page does not state the reason for the proceeding. Status: The page shows 'Online complaint not yet received at office'. No next hearing date is listed (NA). Complaint dispatch is shown as 'Not Yet'. No hearing, notice or order entries are shown.
- RERA-GRG-3806-2022: A compliance proceeding started by the Authority against the promoter SS Group Pvt. Ltd. under a notice referred to as 'Compliance us 42ld'. The page does not state the specific reason for the compliance notice. Status: The first hearing was listed for 30 Jun 2022. The listing shows the status as 'First Hearing', with no proceedings, bench order or order recorded for that day. Latest: 30 Jun 2022, The first hearing was listed. A document was received on the same date and recorded as a new complaint. No proceedings or order are recorded for the hearing.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 12 |
|---|
| Cases | - RERA-GRG-4417-2025 (complaint, decided 27-Jan-2026): Buyer sought refund after unit cancellation; builder ordered to refund paid amount minus earnest money, with 10.80% interest.
- RERA-GRG-4634-2025 (complaint, decided 27-Jan-2026): Buyer sought refund with interest; HRERA dismissed complaint as buyer had no allotment in own name.
- RERA-GRG-4413-2025 (complaint, decided 27-Jan-2026): Buyer sought refund after delayed possession; builder ordered to refund paid amount less earnest money with 10.80% interest.
- RERA-GRG-5037-2024 (complaint, decided 31-Oct-2025): Buyer's allotment cancelled by builder over payment default; builder ordered to refund Rs 41.61 lakh less 10% with 10.85% interest.
- RERA-GRG-2966-2023 (compensation, decided 06-Aug-2025): Buyer sought refund after builder cancelled unit in 2014; complaint dismissed as builder was not at fault
- RERA-GRG-936-2024 (complaint, decided 11-Jul-2025): Buyer sought delay interest and compensation for a late flat; builder ordered to pay 11.10% interest on Rs 1.15 crore.
- RERA-GRG-2534-2023 (complaint, decided 16-Apr-2025): Buyer sought refund after builder cancelled flat allotment; builder ordered to refund Rs 41.63 lakh less 10% with 11.10% interest.
- RERA-GRG-248-2022 (complaint, decided 20-Aug-2024): Buyer sought delay compensation and quashing of extra charges; Authority ordered 11.10% delay interest from 12 Mar 2017 and handover of possession.
- RERA-GRG-5638-2022 (complaint, decided 20-Aug-2024): Buyer sought delay compensation and quashing of extra charges; Authority ordered 11.10% delay interest from 12 Mar 2017 and handover of possession.
- RERA-GRG-4863-2022 (complaint, decided 15-Feb-2024): Buyers sought possession and waivers after delay; HRERA ordered builder to pay 10.85% delay interest and handover possession within 30 days.
- RERA-GRG-540-2022 (complaint, decided 08-Feb-2024): Buyer sought refund after possession delay; builder ordered to refund Rs 25.54 lakh with 10.85% interest.
- RERA-GRG-5578-2022 (complaint, decided 04-Jan-2024): Buyers sought refund after unit cancellation with no agreement executed; builder ordered to refund Rs 17.18 lakh with 10.85% interest.
|
|---|
| Decided cases against SS GROUP PVT. LTD. (all its projects) | 158 (Complaint: 118; Execution of an earlier order: 27; Compensation: 13) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in