The Leaf

Navi Estates · Sector 34, Gurugram

Registered with RERA: Jul 2021

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Navi Estates

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameTHE LEAF
Builder (promoter)NAVI ESTATES LLP
LocationVILLAGE DHUNELA, SEC 34
RERA project IDRERA-GRG-833-2021
Registration certificate numberGGM/467/199/2021/35 DATED 14.07.2021
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to28/06/2028
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area2.625 acres
Licence79 of 2018(17/11/2018)
Estimated cost of the project₹9,382 lakh (₹93.82 crore)
Total units (plots, apartments, shops)118
Unit sizes (carpet area, as declared)114 units of 269 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on27-02-2020
Building plans approved on27-02-2020

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction15-12-2020
Likely completion date30-06-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/03/2026 (JAN-MAR)
Latest report submitted on18-Jul-2026
Quarterly reports listed on the portal18

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2026 (JAN-MAR))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹220.98 lakh (₹2.21 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹100 lakh (₹1 crore)
Spent on infrastructure in the quarter₹50 lakh (₹0.5 crore)
Other costs in the quarter (EDC, taxes, etc.)₹30 lakh (₹0.3 crore)
Project bank account (escrow): deposited in the quarter₹153.13 lakh (₹1.53 crore)
Project bank account (escrow): withdrawn in the quarter₹149.39 lakh (₹1.49 crore)
Project bank account (escrow): balance at quarter end₹13.09 lakh (₹0.13 crore)
Units in the project (apartments / plots)1005 apartments
Sold in the quarter44 apartments
EDC (development charges): paid / due as on date₹314.84 lakh (₹3.15 crore) paid; ₹1,712.48 lakh (₹17.12 crore) due
Approvals listed
  • Demarcation Plan: Obtained Approval 24-08-2020
  • Zoning Plan: Obtained Approval 15-01-2018
  • Service Plans: Obtained Approval 29-11-2018
  • Electricity Plans: Obtained Approval 04-12-2019
  • Site Plans: Obtained Approval 19-02-2021
  • Building Plans: Obtained Approval 27-02-2020
  • Fire NOC: Obtained Approval 27-02-2020

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 03 Apr 2026, for 31 Mar 2026
Overall work complete83%
By part
  • Commercial Colony - Sub structure (excavation, foundation, basements, waterproofing): 99.03%
  • Commercial Colony - Super structure (slabs, brick work, block work, staircase, lift wells, machine rooms, water tank): 98.69%, 15 slabs laid by end of quarter
  • Commercial Colony - MEP 3.1 Mechanical (lifts, ventilation): 92.27%
  • Commercial Colony - MEP 3.2 Electrical (conduiting, wiring, fixtures): 93.48%
  • Commercial Colony - MEP 3.3 Plumbing and firefighting (piping, pumps, fixtures): 84.55%
  • Commercial Colony - Finishing 4.1 Internal (plaster, tiling, flooring, painting): 81.82%
  • Commercial Colony - Finishing 4.2 External (plaster, painting, facade): 84.63%
  • Internal Road and Pavements: 80%
  • Parking: 80%
  • Water Supply System (excluding UGT): 70%
  • Sewerage (chamber, lines, excluding STP): 70%
  • Storm Water Drainage: 75%
  • Landscaping and Tree Plantation: 60%
  • Shopping Area: 75%
  • Street Lighting: 35%
  • Treatment of Disposal of Sewage and Sullage water/STP: 45%
  • Solid Waste Management and Disposal: 45%
  • Water conservation, rain water harvesting, percolating well/pit: 40%
  • Energy Management (Solar): 1%
  • Fire Protection and Fire Safety Requirements: 75%
  • Electrical Meter Room, Sub-Station, receiving station/Electrification: 80%
  • UGT (underground water tank): 95%
Unclear in the certificate
  • Table A 'Work done during the quarter' column shows values (0, 33, 34) with no unit, so they are not reported as percentages.
  • Table B 'Parking' has covered (65%) and open (90%) rows with a blank 'No' entry; not clear if they are separate figures.
  • Table A and Table B use WIP for most items without a stage description.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registration
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed2
By statusFirst Hearing: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against NAVI ESTATES LLP (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in