Projects · DSS BUILDTECH PVT. LTD.
The Melia
Dss Buildtech · Sector 35, Gurugram
Registered with RERA: Oct 2017
Is it legal?
- RERA registered, valid till Apr 2028
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit quarterly progress report (May 2022, open)
- Did not apply to extend registration, submit completion or occupation certificate, or required documents (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jun 2022, open)
- 3 more cases: reply 4
- 17 complaints about this project decided by HRERA since Nov 2023 (2 delay interest ordered, 12 refund ordered, 3 dismissed, withdrawn or settled)
Will it be delivered on time?
- Original deadline not found, extended 2 times to Apr 2028
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Apr–Jun 2026):
- Done: Tower a, Tower b, Tower c, Tower d
- Money: ₹472.2 crore spent of ₹549.8 crore; ₹75.4 crore still to spend (CA certificate, Jun 2026)
What's on offer?
- Registration now covers 995 residential units, 176 EWS units, 20 commercial units and 100 service units
Location
- Nearest metro: Millennium City Centre Gurugram, 14.1 km by road (45 min by car)
- Cyber City 54 min · Airport 44 min by car at 9:30 am
- Within 3 km: 4 hospitals, 0 schools, 1 mall
The builder: Dss Buildtech
- 1 project registered in Gurugram
- 0 with an occupation certificate on record
- 43 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | THE MELIA |
|---|
| Builder (promoter) | DSS BUILDTECH PVT. LTD. |
|---|
| Location | SECTOR 35, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-350-2019 |
|---|
| Registration certificate number | 288 OF 2017 DATED 10.10.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 26/04/2028 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 17.41875 acres |
|---|
| Licence | 77 of 2013 |
|---|
| Estimated cost of the project | ₹44,573 lakh (₹445.73 crore) |
|---|
| Total units (plots, apartments, shops) | 1159 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 0 |
|---|
| Units unsold when registered | 0 |
|---|
| Layout plan approved on | 01-12-2016 |
|---|
| Building plans approved on | Not found in the records checked |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | Not found in the records checked |
|---|
| Revised completion date | Not found in the records checked |
|---|
| Infrastructure: projected completion | 25-10-2021 |
|---|
| Infrastructure: percentage complete when registered | 45% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/06/2026 (APR-JUN) |
|---|
| Latest report submitted on | 24-Aug-2026 |
|---|
| Quarterly reports listed on the portal | 31 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2026 (APR-JUN))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹1,404.23 lakh (₹14.04 crore) |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹627.53 lakh (₹6.28 crore) |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹1,278.64 lakh (₹12.79 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹940.36 lakh (₹9.4 crore) |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹955.62 lakh (₹9.56 crore) |
|---|
| Project bank account (escrow): balance at quarter end | ₹0 |
|---|
| Units in the project (apartments / plots) | Not found in the records checked |
|---|
| Sold in the quarter | Not found in the records checked |
|---|
| EDC (development charges): paid / due as on date | ₹11,618.28 lakh (₹116.18 crore) paid; ₹0 due |
|---|
| Approvals listed | - Layout Plan: Obtained Approval 21-04-2015
- Demarcation Plan: Obtained Approval 21-04-2015
- Zoning Plan: Obtained Approval 21-04-2015
- Service Plans: Obtained Approval 21-12-2017
- Electricity Plans: Obtained Approval 21-12-2017
- Site Plans: Obtained Approval 21-04-2015
- Building Plans: Obtained Approval 21-01-2015
- Fire NOC: Obtained Approval 09-01-2018
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Jun 2026, for June 2026 |
|---|
| By part | - Tower A: 100%, G+14 building; 15 slabs laid by end of quarter; staircase, lift wells and common areas done; finishing works reported done
- Tower B: 100%, G+14 building; 15 slabs laid by end of quarter; staircase, lift wells and common areas done; finishing works reported done
- Tower C: 100%, G+14 building; two basement levels completed; 15 slabs reported; finishing works reported done
- Tower D: 100%, Excavation and raft completed; basement items not applicable; the table ends before the finishing items
|
|---|
| Unclear in the certificate | - Tower D table is cut off after the basement rows, so its finishing and installation status is not shown.
- Tower C slab count is written as '15 15' in the status table.
- Several tables are labelled 'Table - A' for Tower B, C and D, and the Tower B table has a different heading layout.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 6 |
|---|
| By status | Online Complaint Not Yet Received At Office: 1; First Hearing: 4; Pending: 1 |
|---|
| Proceedings | - RERA-GRG-2979-2022: Case RERA-GRG-2979-2022, listed as the Authority against DSS Buildtech Pvt. Ltd. The page does not state the reason for the case. It shows an online complaint that has not yet been received at the office. Status: Online complaint not yet received at office. Complaint not yet dispatched. No next hearing date is listed (NA).
- RERA-GRG-3484-2022: Show cause notice to the promoter for not submitting a quarterly progress report. The Authority asked the promoter to explain in writing and appear for a hearing. Status: First hearing listed for 27 Jun 2022. The page shows no proceedings or order from that hearing. Latest: 27 Jun 2022, First hearing listed at 11.00 am at the HARERA Gurugram office. The promoter was asked to appear with a written reply if it had anything to say. Status shows 'First Hearing', with no proceedings recorded.
- RERA-GRG-3732-2022: Show cause notice to the promoter, DSS Buildtech Pvt. Ltd., for not applying to extend its registration, not submitting a completion, part completion or occupation certificate, and not submitting required documents. The registration certificate is shown as expired. Status: First hearing listed for 28 Jun 2022. No order has been uploaded on the case page. Latest: 28 Jun 2022, First hearing listed. The status shows as FIRST HEARING, with no proceedings, bench or order recorded.
- RERA-GRG-3733-2022: The Authority started this case itself against the promoter, DSS Buildtech Pvt. Ltd., through a show-cause notice. The notice says the promoter did not follow the time it declared for completing the project, as required under section 4(2)(l)(C). Status: First hearing listed for 30 Jun 2022. The page shows no proceedings or order for that hearing. Latest: 30 Jun 2022, First hearing listed. Status shown as 'First Hearing'. Proceedings and order fields are blank.
- RERA-GRG-5166-2022: A complaint filed in the name of HARERA Gurugram (the Authority), through its representative, against the promoter DSS Buildtech Pvt. Ltd. The case page does not state the reason for the complaint. Status: Listed at First Hearing stage. The page shows a first hearing on 30 Jun 2022 with no recorded proceedings, bench order or uploaded order. Latest: 16 Jul 2022, A document was received and recorded (Dak ID 37917) under the remark NEW COMPLAINT, submitted by the complainant's representative.
- RERA-GRG-5449-2019: The Authority's proceeding against DSS Buildtech Pvt. Ltd. (the promoter) for not submitting its registration application (REP-I Part A-H) and quarterly progress report (QPR), as required under a section of the RERA Act written in the document as "Sec42lD" Status: Pending. The last listed hearing was on 24 Feb 2020 with status PENDING, and the page shows a third notice dispatched on 20 Jul 2020. Latest: 20 Jul 2020, A third notice on the section and QPR was dispatched. The complaint was marked as dispatched on this date.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 17 |
|---|
| Cases | - RERA-GRG-5249-2024 (compensation, decided 09-Sep-2026): Buyers sought delay compensation for The Melia; dismissed because interest for the same delay was already allowed earlier.
- RERA-GRG-5720-2025 (complaint, decided 11-Aug-2026): Buyers sought quashing of cancellation notice and recalculated demands; HRERA dismissed as barred by res judicata.
- RERA-GRG-1352-2024 (complaint, decided 12-Dec-2025): Buyer sought refund after surrendering unit over delay; refund refused as buyer defaulted on EMIs, compensation referred to Adjudicating Officer
- RERA-GRG-86-2025 (complaint, decided 28-Nov-2025): Buyers sought possession after delay; builder ordered to hand over possession and pay 10.85% delay interest.
- RERA-GRG-2911-2025 (complaint, decided 28-Nov-2025): Buyer sought delayed possession relief; builder ordered to pay 10.85% interest, hand over possession and execute conveyance deed.
- RERA-GRG-4856-2023 (complaint, decided 11-Sep-2025): Buyer sought refund of a Gurugram flat after possession delay; builder ordered to refund bank-disbursed Rs 62.8 lakh with interest.
- RERA-GRG-4403-2023 (complaint, decided 07-Aug-2025): Buyer sought refund after home loan rejection and cancellation; builder ordered to refund paid amount less 10% earnest money with 10.85% interest.
- RERA-GRG-5247-2024 (complaint, decided 06-Aug-2025): Buyer sought possession of delayed flat; builder ordered to hand over possession and pay 10.90% interest on amounts paid
- RERA-GRG-220-2024 (complaint, decided 23-Apr-2025): Buyer sought refund of Rs 6 lakh booking amount after location misrepresentation; builder ordered to refund with 11.10% interest.
- RERA-GRG-2812-2024 (complaint, decided 21-Mar-2025): Buyers sought refund of Rs 22.69 lakh after withdrawing; authority ordered builder to refund it minus 10% with 11.10% interest.
- RERA-GRG-289-2024 (complaint, decided 02-Jan-2025): Buyers sought refund after possession delay; builder ordered to refund Rs 76.39 lakh with 11.10% interest
- RERA-GRG-279-2024 (complaint, decided 18-Dec-2024): Buyer sought refund after cancelled unit; builder ordered to refund Rs 13.5 lakh with 11.10% interest
- RERA-GRG-2039-2021 (complaint, decided 05-Mar-2024): Buyer sought refund of Rs 20.24 lakh paid; authority ordered refund after deducting 10% earnest money, with 10.85% interest.
- RERA-GRG-5659-2022 (complaint, decided 13-Feb-2024): Buyer sought refund after possession delay; builder ordered to refund Rs 70.14 lakh with 10.85% interest.
- RERA-GRG-381-2023 (complaint, decided 08-Feb-2024): Buyer sought refund after developer delayed the project and no agreement was signed; HRERA ordered refund of Rs 13.49 lakh with 10.85% interest.
- RERA-GRG-6845-2022 (complaint, decided 30-Jan-2024): Buyer sought refund after possession delay; builder ordered to refund Rs 74.38 lakh with 10.85% interest.
- RERA-GRG-1605-2023 (complaint, decided 05-Jan-2024): Buyers sought refund of Rs 6 lakh booking amount; HRERA dismissed the complaint, ordering no refund.
|
|---|
| Decided cases against DSS BUILDTECH PVT. LTD. (all its projects) | 43 (Execution of an earlier order: 4; Complaint: 36; Compensation: 3) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in