Projects · SARVPRIYA SECURITIES PVT LTD
The Millennia 2
Sarvpriya Securities · Sector 37, Gurugram
Registered with RERA: Jul 2019
Is it legal?
- RERA registered, valid till Feb 2024 (date has passed)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Did not submit quarterly progress report; Authority issued show-cause notice on its own (May 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Aug 2025, open)
- Failed to submit service estimates and plans, environmental clearance, and fire scheme NOC in time (Jun 2022, open). At stake: Possible revocation of registration and penal proceedings; no penalty imposed yet
- 2 more cases: reply 4
Will it be delivered on time?
- Deadline Feb 2024, never extended (date has passed)
- Occupation certificate (Sep 2024) covers: Towers A to K and commercial block (754 homes) (754 flats)
- Construction, as certified by the architect (Jul–Sep 2026):
- Done: 14 parts
- In progress: Towers, table a mechanical 0%, Shopping area 0%, Street lighting and electrification 0%, Treatment and disposal of sewage and stp 0%, Solid waste management and disposal 0%, Energy management 0%, and 2 more
- Money: ₹172.6 crore spent of ₹177.5 crore; ₹4.9 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 754 units: 0 sold, 0 unsold (builder's certificate, Sep 2026)
- 754 units, as declared to HRERA:
- 754 units averaging about 580 sq ft carpet (11 towers)
- The builder gave each tower's total carpet area, not each flat's size; averages divide that total by the number of units. HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Millennium City Centre Gurugram, 14.5 km by road (48 min by car)
- Cyber City 55 min · Airport 38 min by car at 9:30 am
- Within 3 km: 6 hospitals, 3 schools, 1 mall
The builder: Sarvpriya Securities
- 2 projects registered in Gurugram
- 2 with an occupation certificate on record
- 5 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | THE MILLENNIA 2 |
|---|---|
| Builder (promoter) | SARVPRIYA SECURITIES PVT LTD |
| Location | VILLAGE BASAI AND GADOLI KHUR D SECTOR 37 D GURUGRAM HARYANA |
| RERA project ID | RERA-GRG-237-2019 |
| Registration certificate number | GGM/343/75/2019/37 DATED 08.07.2019 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 29/02/2024 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 5.4875 acres |
| Licence | 45 of 2019 dated 01.03.2019 |
| Estimated cost of the project | ₹17,752 lakh (₹177.52 crore) |
| Total units (plots, apartments, shops) | 754 |
| Unit sizes (carpet area, as declared) | 754 units averaging about 580 sq ft carpet (11 towers) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 01-06-2019 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-06-2019 |
|---|---|
| Likely completion date | 29-02-2024 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 17-Oct-2026 |
| Quarterly reports listed on the portal | 28 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
| Project bank account (escrow): deposited in the quarter | ₹6.82 lakh (₹0.07 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹6.82 lakh (₹0.07 crore) |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 754.00 apartments, 0.00 plots |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹838.38 lakh (₹8.38 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026, for 30 Sep 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against SARVPRIYA SECURITIES PVT LTD (all its projects) | 5 (Compensation: 1; Complaint: 4) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in