Projects · JMS BUILDWELL REALTY PRIVATE LIMITED
The Pride
Jms Buildwell Realty · Sector 95, Gurugram
Registered with RERA: Dec 2022
Is it legal?
- RERA registered, valid till Oct 2025 (date has passed)
- HRERA has not opened any case of its own against this project
- 1 complaint about this project decided by HRERA since Nov 2023 (1 compensation ordered)
Will it be delivered on time?
- Original deadline Oct 2024, extended to Oct 2025
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Construction 100% complete (architect, Jan–Mar 2025)
- Money: ₹52.4 crore spent of ₹53.3 crore; ₹87.7 lakh still to spend (CA certificate, Mar 2025)
What's on offer?
- Registration now covers 109
- 109 plots, 112–178 sq yd
Location
- Nearest metro: Millennium City Centre Gurugram, 23 km by road (58 min by car)
- Cyber City 60 min · Airport 40 min by car at 9:30 am
- Within 3 km: 0 hospitals, 0 schools, 0 malls
The builder: Jms Buildwell Realty
- 3 projects registered in Gurugram
- 0 with an occupation certificate on record
- 4 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | THE PRIDE |
|---|---|
| Builder (promoter) | JMS BUILDWELL REALTY PRIVATE LIMITED |
| Location | SECTOR 95 A |
| RERA project ID | RERA-GRG-1186-2022 |
| Registration certificate number | GGM/643/375/2022/118 DATED 13.12.2022 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 16/10/2025 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | Extension Certificate Uploaded |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 5.0458 acres |
| Licence | 166 of 2022 |
| Estimated cost of the project | ₹1,976 lakh (₹19.76 crore) |
| Total units (plots, apartments, shops) | 109 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 18-10-2022 |
| Building plans approved on | 18-10-2022 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 19-10-2022 |
|---|---|
| Likely completion date | 17-10-2024 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/03/2025 (JAN-MAR) |
| Latest report submitted on | 24-Apr-2025 |
| Quarterly reports listed on the portal | 9 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2025 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹412.7 lakh (₹4.13 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹-25.36 lakh (₹-0.25 crore) |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹8.5 lakh (₹0.09 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹381.91 lakh (₹3.82 crore) |
| Project bank account (escrow): deposited in the quarter | ₹288.89 lakh (₹2.89 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹291.96 lakh (₹2.92 crore) |
| Project bank account (escrow): balance at quarter end | ₹7.72 lakh (₹0.08 crore) |
| Units in the project (apartments / plots) | 109 plots |
| Sold in the quarter | 0 plots |
| EDC (development charges): paid / due as on date | ₹606 lakh (₹6.06 crore) paid; ₹0 due |
| Approvals listed | Not found in the records checked |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 14 Apr 2025, for JAN 2025 to MARCH 2025 |
|---|---|
| Overall work complete | 100% |
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 1 |
|---|---|
| Cases | |
| Decided cases against JMS BUILDWELL REALTY PRIVATE LIMITED (all its projects) | 4 (Complaint: 4) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in