Projects · FOREVER BUILDTECH PVT. LTD
The Roselia
Forever Buildtech · Sector 95A, Gurugram
Registered with RERA: Jun 2017
Is it legal?
- RERA registered, valid till May 2021 (date has passed)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not apply to extend registration; did not submit completion or occupation certificate (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jun 2022, open)
- Did not submit quarterly progress report (May 2022, open)
- 3 more cases: reply 4
- 23 complaints about this project decided by HRERA since Nov 2023 (5 delay interest ordered, 16 refund ordered, 1 other order, 1 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline May 2021, never extended (date has passed)
- Occupation certificate (Jan 2023) covers: Towers A, B, C and D of affordable housing colony
- Construction, as certified by the architect (Jul–Sep 2026):
- Money: ₹243.7 crore spent of ₹243.7 crore (CA certificate, Sep 2026)
What's on offer?
- 1,101 units: 0 sold, 26 unsold (builder's certificate, Sep 2026)
Location
- Nearest metro: Millennium City Centre Gurugram, 22.2 km by road (57 min by car)
- Cyber City 64 min · Airport 46 min by car at 9:30 am
- Within 3 km: 0 hospitals, 0 schools, 0 malls
The builder: Forever Buildtech
- 3 projects registered in Gurugram
- 2 with an occupation certificate on record
- 42 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | THE ROSELIA |
|---|
| Builder (promoter) | FOREVER BUILDTECH PVT. LTD |
|---|
| Location | SEC-95A, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-384-2019 |
|---|
| Registration certificate number | 05 OF 2017 DATED 20.06.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 17/05/2021 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 8.034 acres |
|---|
| Licence | 13 OF 2016 DATED 26/09/2016 |
|---|
| Estimated cost of the project | ₹23,169 lakh (₹231.69 crore) |
|---|
| Total units (plots, apartments, shops) | 1101 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 1055 |
|---|
| Units unsold when registered | 106 |
|---|
| Layout plan approved on | 03-10-2017 |
|---|
| Building plans approved on | Not found in the records checked |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 17-05-2021 |
|---|
| Revised completion date | 17-05-2021 |
|---|
| Infrastructure: projected completion | 17-05-2021 |
|---|
| Infrastructure: percentage complete when registered | 54.47% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
|---|
| Latest report submitted on | 23-Oct-2026 |
|---|
| Quarterly reports listed on the portal | 32 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0.21 lakh (₹0 crore) |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0.17 lakh (₹0 crore) |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹18.39 lakh (₹0.18 crore) |
|---|
| Project bank account (escrow): balance at quarter end | ₹0.18 lakh (₹0 crore) |
|---|
| Units in the project (apartments / plots) | 1101.00 apartments, 0.00 plots |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹1,277.09 lakh (₹12.77 crore) paid; ₹140.57 lakh (₹1.41 crore) due |
|---|
| Approvals listed | - Demarcation Plan: Obtained Approval 26-09-2016
- Zoning Plan: Obtained Approval 26-09-2016
- Service Plans: Obtained Approval 04-01-2017
- Electricity Plans: Obtained Approval 20-11-2017
- Site Plans: Obtained Approval 09-01-2017
- Building Plans: Obtained Approval 09-01-2017
- Fire NOC: Obtained Approval 24-05-2017
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026, for 30 Sep 2026 |
|---|
| By part | - All 11+1 towers (Table A, cumulative figure): 100%, Table A shows work in progress on several finishing and installation items, such as internal flooring, tiling, lift wells and electrical fittings in common areas. Compound wall finishing is in progress.
|
|---|
| Unclear in the certificate | - The certificate gives no separate progress figure for each tower. Table A covers '11+1 Nos. (Towers)' as one set.
- Table A shows 100% cumulative work for every component, but several items in the same table are marked 'work in progress'. Installation items such as lifts, fire-fighting fittings and electrical fittings in common areas are also marked 'work in progress' with 100% shown.
- The certificate shows 0% work done during the quarter for all Table A components, which does not match the 100% cumulative figure for components still in progress.
- Compliance with environment/CRZ NOC conditions is marked 'yet to be start' at 0%, and solid waste management is shown at 0% in Table B. The 100% cumulative figures do not reflect these items.
- No overall percentage of construction completed or percentage done in the quarter is stated as one figure.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 6 |
|---|
| By status | Online Complaint Not Yet Received At Office: 1; First Hearing: 4; Pending: 1 |
|---|
| Proceedings | - RERA-GRG-2595-2022: Case RERA-GRG-2595-2022 lists the Authority (HARERA Gurugram) as the party against Forever Buildtech Pvt. Ltd. The page does not state what the case is about. Status: Online complaint not yet received at office. Complaint not yet dispatched. No next hearing date listed.
- RERA-GRG-2804-2022: Show cause notice issued by the Authority to the promoter for not applying to extend its registration and for not submitting a completion certificate, part completion certificate or occupation certificate, and for not submitting the requisite documents. The case title marks the registration certificate as expired. Status: First hearing listed for 28 Jun 2022. The listing status is First Hearing, and no proceedings or order are recorded yet. Latest: 28 Jun 2022, First hearing listed. No proceedings of the day or bench order is recorded, and no order has been uploaded.
- RERA-GRG-2806-2022: The Authority issued a show-cause notice to the promoter, Forever Buildtech Pvt. Ltd., for not completing its project within the time it had declared, under section 4(2)(l)(C) of the RERA Act. Status: First hearing listed for 30 Jun 2022. The hearing record shows no proceedings, bench order or uploaded order yet. Latest: 30 Jun 2022, First hearing listed. Status shown as First Hearing, with no proceedings or order recorded.
- RERA-GRG-2839-2022: The Authority issued a show cause notice to the promoter, Forever Buildtech Pvt. Ltd., for not submitting its quarterly progress report. The promoter was asked to appear before the Authority on 27 Jun 2022 with a written reply. Status: First hearing was listed for 27 Jun 2022. The page shows no order or outcome from that hearing. Latest: 27 Jun 2022, First hearing was scheduled at 11.00 am at the HARERA Gurugram office, with a written reply to be brought. The listing shows the status as First Hearing, with no order recorded.
- RERA-GRG-4966-2022: Complaint RERA-GRG-4966-2022 listed in the case title as Haryana RERA Gurugram acting through an individual, against the promoter Forever Buildtech Pvt. Ltd. The page does not state what the complaint is about. Status: Listed at the First Hearing stage. A hearing was set for 30 Jun 2022, and the page records no proceedings or order for that date. Latest: 16 Jul 2022, A document was received under Dak ID 38106 and is described as a new complaint, submitted by the complainant's side.
- RERA-GRG-5217-2019: Filing of REP-I Part (A-H) on the HARERA website for the registered project The Roselia in Sector-95A, Gurugram, being developed by M/s Forever Buildtech Pvt Ltd. The Authority directed scrutiny of the promoter's filing and sought compliance with section 42(1D) and the QPR requirement. Status: Pending. The case page lists the next hearing as 17 Feb 2020. The fourth notice was dispatched on 09 Sep 2020 and the complaint was marked dispatched on the same date. Latest: 09 Sep 2020, Fourth notice dispatched for compliance with section 42(1D) and the QPR. Complaint also marked as dispatched on this date.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 23 |
|---|
| Cases | - RERA-GRG-4381-2024 (complaint, decided 27-Jan-2026): Buyer sought Rs 10 lakh compensation; cancellation upheld, builder ordered to refund Rs 16,98,606 less Rs 25,000 with 10.80% interest.
- RERA-GRG-4597-2024 (complaint, decided 03-Dec-2025): Buyers sought correction of project and unit name errors in earlier order; Authority corrected both.
- RERA-GRG-4560-2024 (complaint, decided 23-Jul-2025): Buyer sought delay interest and refunds of excess charges; HRERA ordered builder to pay delay interest at 11.10% p.a., but rejected refund claims after conveyance deed.
- RERA-GRG-1957-2023 (complaint, decided 20-May-2025): Buyer sought delayed possession charges; builder ordered to pay delay interest at 11.10% and charge utilities only as consumed.
- RERA-GRG-1860-2023 (complaint, decided 20-May-2025): Buyer sought delayed possession charges; builder ordered to pay delay interest at 11.10% and charge utilities only as consumed.
- RERA-GRG-7883-2022 (complaint, decided 24-Apr-2025): Buyer got flat 1 year 4 months late; builder ordered to pay 11.10% delay interest up to 01.08.2022.
- RERA-GRG-2335-2024 (complaint, decided 20-Feb-2025): Buyers sought delay compensation and refunds from builder; HRERA ordered 11.10% interest on paid amounts for possession delay, no other refunds.
- RERA-GRG-2464-2024 (complaint, decided 20-Feb-2025): Buyers sought delay compensation and refunds from builder; HRERA ordered 11.10% interest on paid amounts for possession delay, no other refunds.
- RERA-GRG-2381-2024 (complaint, decided 20-Feb-2025): Buyers sought delay compensation and refunds from builder; HRERA ordered 11.10% interest on paid amounts for possession delay, no other refunds.
- RERA-GRG-2354-2024 (complaint, decided 20-Feb-2025): Buyers sought delay compensation and refunds from builder; HRERA ordered 11.10% interest on paid amounts for possession delay, no other refunds.
- RERA-GRG-2362-2024 (complaint, decided 20-Feb-2025): Buyers sought delay compensation and refunds from builder; HRERA ordered 11.10% interest on paid amounts for possession delay, no other refunds.
- RERA-GRG-2413-2024 (complaint, decided 20-Feb-2025): Buyers sought delay compensation and refunds from builder; HRERA ordered 11.10% interest on paid amounts for possession delay, no other refunds.
- RERA-GRG-2396-2024 (complaint, decided 20-Feb-2025): Buyers sought delay compensation and refunds from builder; HRERA ordered 11.10% interest on paid amounts for possession delay, no other refunds.
- RERA-GRG-2377-2024 (complaint, decided 20-Feb-2025): Buyers sought delay compensation and refunds from builder; HRERA ordered 11.10% interest on paid amounts for possession delay, no other refunds.
- RERA-GRG-2334-2024 (complaint, decided 20-Feb-2025): Buyers sought delay compensation and refunds from builder; HRERA ordered 11.10% interest on paid amounts for possession delay, no other refunds.
- RERA-GRG-2376-2024 (complaint, decided 20-Feb-2025): Buyers sought delay compensation and refunds from builder; HRERA ordered 11.10% interest on paid amounts for possession delay, no other refunds.
- RERA-GRG-1135-2023 (complaint, decided 26-Jul-2024): Buyer sought delay interest and refund of excess charges; builder ordered to pay 11% interest on paid amount for delay until July 2022.
- RERA-GRG-1284-2023 (complaint, decided 26-Jul-2024): Buyer sought delay interest and refund of excess charges; builder ordered to pay 11% interest on paid amount for delay until July 2022.
- RERA-GRG-1282-2023 (complaint, decided 26-Jul-2024): Buyer sought delay interest and refund of excess charges; builder ordered to pay 11% interest on paid amount for delay until July 2022.
- RERA-GRG-1285-2023 (complaint, decided 26-Jul-2024): Buyer sought delay interest and refund of excess charges; builder ordered to pay 11% interest on paid amount for delay until July 2022.
- RERA-GRG-3225-2021 (complaint, decided 22-Dec-2023): Buyer sought cancellation withdrawal and delay interest; HRERA upheld cancellation and ordered refund minus Rs 25,000 with 10.85% interest.
- RERA-GRG-6466-2022 (complaint, decided 21-Dec-2023): Buyers sought delay interest and relief from unfair charges; builder ordered to pay 10.85% interest on delay until 14 Jul 2022.
- RERA-GRG-6468-2022 (complaint, decided 21-Dec-2023): Buyers sought delay interest and relief from unfair charges; builder ordered to pay 10.85% interest on delay until 14 Jul 2022.
|
|---|
| Decided cases against FOREVER BUILDTECH PVT. LTD (all its projects) | 42 (Complaint: 39; Execution of an earlier order: 2; Compensation: 1) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in