RERA’d by NeevHQ

Projects · FOREVER BUILDTECH PVT. LTD

The Roselia

Forever Buildtech · Sector 95A, Gurugram

Registered with RERA: Jun 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Forever Buildtech

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameTHE ROSELIA
Builder (promoter)FOREVER BUILDTECH PVT. LTD
LocationSEC-95A, GURUGRAM
RERA project IDRERA-GRG-384-2019
Registration certificate number05 OF 2017 DATED 20.06.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to17/05/2021
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area8.034 acres
Licence13 OF 2016 DATED 26/09/2016
Estimated cost of the project₹23,169 lakh (₹231.69 crore)
Total units (plots, apartments, shops)1101
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered1055
Units unsold when registered106
Layout plan approved on03-10-2017
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date17-05-2021
Revised completion date17-05-2021
Infrastructure: projected completion17-05-2021
Infrastructure: percentage complete when registered54.47%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on23-Oct-2026
Quarterly reports listed on the portal32

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0.21 lakh (₹0 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹0.17 lakh (₹0 crore)
Project bank account (escrow): withdrawn in the quarter₹18.39 lakh (₹0.18 crore)
Project bank account (escrow): balance at quarter end₹0.18 lakh (₹0 crore)
Units in the project (apartments / plots)1101.00 apartments, 0.00 plots
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹1,277.09 lakh (₹12.77 crore) paid; ₹140.57 lakh (₹1.41 crore) due
Approvals listed
  • Demarcation Plan: Obtained Approval 26-09-2016
  • Zoning Plan: Obtained Approval 26-09-2016
  • Service Plans: Obtained Approval 04-01-2017
  • Electricity Plans: Obtained Approval 20-11-2017
  • Site Plans: Obtained Approval 09-01-2017
  • Building Plans: Obtained Approval 09-01-2017
  • Fire NOC: Obtained Approval 24-05-2017

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for 30 Sep 2026
By part
  • All 11+1 towers (Table A, cumulative figure): 100%, Table A shows work in progress on several finishing and installation items, such as internal flooring, tiling, lift wells and electrical fittings in common areas. Compound wall finishing is in progress.
Unclear in the certificate
  • The certificate gives no separate progress figure for each tower. Table A covers '11+1 Nos. (Towers)' as one set.
  • Table A shows 100% cumulative work for every component, but several items in the same table are marked 'work in progress'. Installation items such as lifts, fire-fighting fittings and electrical fittings in common areas are also marked 'work in progress' with 100% shown.
  • The certificate shows 0% work done during the quarter for all Table A components, which does not match the 100% cumulative figure for components still in progress.
  • Compliance with environment/CRZ NOC conditions is marked 'yet to be start' at 0%, and solid waste management is shown at 0% in Table B. The 100% cumulative figures do not reflect these items.
  • No overall percentage of construction completed or percentage done in the quarter is stated as one figure.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 4; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project23
Cases
Decided cases against FOREVER BUILDTECH PVT. LTD (all its projects)42 (Complaint: 39; Execution of an earlier order: 2; Compensation: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in