Projects · REVITAL REALTY PVT LTD
The Valley (Affordable Group Housing)
Revital Realty · Sector 78, Gurugram
Registered with RERA: Oct 2018
Is it legal?
- RERA registered, valid till Apr 2030
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Alleged expired project registration, with no appearance at four hearings (Jul 2024, open)
- Did not submit quarterly progress report (Jun 2022, open)
- Failed to meet registration certificate conditions: service plans, fire NOC, collaboration agreement; delay over 45 months (Jun 2022, open). At stake: Builder directed to submit Rs 25 lakh guarantee or cheque/DD; no penalty stated
- 2 more cases: reply 4
- 20 complaints about this project decided by HRERA since Nov 2023 (11 delay interest ordered, 9 refund ordered)
Will it be delivered on time?
- Original deadline Feb 2023, extended to Apr 2030
- No occupation certificate yet (not ready for possession)
- Money: ₹91.1 crore spent of ₹256.4 crore; ₹165.3 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- Registration now covers 7364 residential units
- Sizes declared at registration (1,364 units):
- 1,364 units averaging about 550 sq ft carpet (15 towers)
- The builder gave each tower's total carpet area, not each flat's size; averages divide that total by the number of units. HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Millennium City Centre Gurugram, 21.5 km by road (52 min by car)
- Cyber City 59 min · Airport 49 min by car at 9:30 am
- Within 3 km: 1 hospital, 0 schools, 0 malls
Location shown for Sector 78; the exact site was not found.
The builder: Revital Realty
- 1 project registered in Gurugram
- 0 with an occupation certificate on record
- 32 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | THE VALLEY (AFFORDABLE GROUP HOUSING) |
|---|---|
| Builder (promoter) | REVITAL REALTY PVT LTD |
| Location | SECTOR-78, GURUGRAM |
| RERA project ID | RERA-GRG-80-2018 |
| Registration certificate number | GGM/288/2018/20 DATED 23.10.2018 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/04/2030 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | Extension Certificate Uploaded |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 9.0625 acres |
| Licence | 45 of 2018 dated 29.06.2018 |
| Estimated cost of the project | ₹16,331 lakh (₹163.31 crore) |
| Total units (plots, apartments, shops) | 1364 |
| Unit sizes (carpet area, as declared) | 1,364 units averaging about 550 sq ft carpet (15 towers) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 11-10-2018 |
| Building plans approved on | 11-10-2018 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-03-2019 |
|---|---|
| Likely completion date | 28-02-2023 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 22-Oct-2026 |
| Quarterly reports listed on the portal | 32 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹1,372.5 lakh (₹13.73 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹625.08 lakh (₹6.25 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹255.87 lakh (₹2.56 crore) |
| Project bank account (escrow): deposited in the quarter | ₹1,006.5 lakh (₹10.07 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹1,480 lakh (₹14.8 crore) |
| Project bank account (escrow): balance at quarter end | ₹66.92 lakh (₹0.67 crore) |
| Units in the project (apartments / plots) | 1522 apartments |
| Sold in the quarter | 24 apartments |
| EDC (development charges): paid / due as on date | ₹0 paid; ₹55.61 lakh (₹0.56 crore) due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 05 Oct 2026, for 30 Sep 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in