Projects · OCEAN SEVEN BUILDTECH PVT LTD
The Venetian
Ocean Seven Buildtech · Sector 70, Gurugram
Registered with RERA: Oct 2020
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Sep 2024)
- HRERA has opened 3 cases of its own against the builder over this project (3 open):
- Did not submit a quarterly progress report; Authority issued show-cause notice 31 May 2022 (May 2022, open)
- 2 more cases: reply 4
- 84 complaints about this project decided by HRERA since Nov 2023 (3 delay interest ordered, 78 refund ordered, 1 compensation ordered, 2 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Sep 2024, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Quarterly progress report shown as "not uploaded" by HRERA
What's on offer?
- Flat types (BHK) as stated in the builder's floor plans uploaded to HRERA:
- 2 BHK: 556–580 sq ft carpet
Location
- Nearest metro: Sector 55–56, 9.2 km by road (35 min by car)
- Cyber City 58 min · Airport 48 min by car at 9:30 am
- Within 3 km: 7 hospitals, 4 schools, 3 malls
Location shown for Sector 70; the exact site was not found.
The builder: Ocean Seven Buildtech
- 3 projects registered in Gurugram, 3 lapsed
- 0 with an occupation certificate on record
- 392 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | THE VENETIAN |
|---|---|
| Builder (promoter) | OCEAN SEVEN BUILDTECH PVT LTD |
| Location | SECTOR-70,BADSHAHPUR |
| RERA project ID | RERA-GRG-629-2020 |
| Registration certificate number | GGM/423/155/2020/39 DATED 27.10.2020 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 02/09/2024 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 5.10 acres |
| Licence | 103 OF 2019 |
| Estimated cost of the project | ₹15,692.15 lakh (₹156.92 crore) |
| Total units (plots, apartments, shops) | 739 |
| Unit sizes (carpet area, as declared) | 367 units of 556 sq ft carpet (5 towers); 372 units of 571 sq ft carpet (5 towers) |
| Flat types (BHK), as stated by the builder | 2 BHK: 556–580 sq ft carpet (source: the builder's floor plans uploaded to HRERA) |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 07-02-2020 |
| Building plans approved on | 07-02-2020 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 02-12-2020 |
|---|---|
| Likely completion date | 02-09-2024 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026