Projects · VATIKA LTD.
Tranquil Heights, PHASE-1
Vatika · Sector 82A, Gurugram
Registered with RERA: Nov 2017
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Apr 2021)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit its quarterly progress report (May 2022, open)
- Failed to apply for registration extension, submit completion or occupation certificate, and requisite documents (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jun 2022, open)
- 3 more cases: reply 4
- 17 complaints about this project decided by HRERA since Nov 2023 (15 refund ordered, 2 compensation ordered)
Will it be delivered on time?
- Deadline Jan 2022, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Money: ₹94.1 crore spent of ₹134.6 crore; ₹40.5 crore still to spend (CA certificate, Dec 2025)
What's on offer?
- 169 units: 101 sold, 68 unsold (builder's certificate, Dec 2025)
- Apartment: 101 of 169 sold
Location
- Nearest metro: Millennium City Centre Gurugram, 19.3 km by road (48 min by car)
- Cyber City 54 min · Airport 45 min by car at 9:30 am
- Within 3 km: 1 hospital, 1 school, 0 malls
The builder: Vatika
- 14 projects registered in Gurugram, 9 lapsed
- 1 with an occupation certificate on record
- 961 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | TRANQUIL HEIGHTS, PHASE-1 |
|---|
| Builder (promoter) | VATIKA LTD. |
|---|
| Location | SECTOR-82A, VILLAGE SHIKOHPUR , TEHSIL MANESAR, GURUGRAM, HARYANA |
|---|
| RERA project ID | RERA-GRG-506-2019 |
|---|
| Registration certificate number | 359 OF 2017 DATED 17.11.2017 |
|---|
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 30/04/2021 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 11.218 acres |
|---|
| Licence | 22 of 2011 dated 24-03-2011 |
|---|
| Estimated cost of the project | ₹13,461 lakh (₹134.61 crore) |
|---|
| Total units (plots, apartments, shops) | 169 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 99 |
|---|
| Units unsold when registered | 70 |
|---|
| Layout plan approved on | 16-02-2017 |
|---|
| Building plans approved on | 16-02-2017 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 30-01-2022 |
|---|
| Revised completion date | 30-01-2022 |
|---|
| Infrastructure: projected completion | 30-01-2022 |
|---|
| Infrastructure: percentage complete when registered | 0% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/12/2025 (OCT-DEC) |
|---|
| Latest report submitted on | 13-Jan-2026 |
|---|
| Quarterly reports listed on the portal | 29 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2025 (OCT-DEC))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹5,294.02 lakh (₹52.94 crore) |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹3,707.06 lakh (₹37.07 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹4.49 lakh (₹0.04 crore) |
|---|
| Units in the project (apartments / plots) | 169 apartments |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹2,218.31 lakh (₹22.18 crore) paid; ₹0 due |
|---|
| Approvals listed | - Zoning Plan: Obtained Approval 16-12-2015
- Electricity Plans: Obtained Approval 25-12-2016
- Site Plans: Obtained Approval 16-02-2017
- Building Plans: Obtained Approval 16-02-2017
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 31 Dec 2025, for 31 Dec 2025 |
|---|
| By part | - Phase-I (Tranquil Heights, one building/tower in Table A): Substructure 75% done (cumulative). Electrical MEP 22%. Superstructure 0% in Table A. 17 slabs laid by quarter end, 49 floors planned. Basement Level 1 at 68%, Basement Level 2 at 77%. Underground water tank 36%. Table A shows 0.00 work done during the quarter for every component.
|
|---|
| Unclear in the certificate | - Table A shows superstructure at 0%, but the activity table lists 17 slabs laid, block work at 19% and structure with plaster at 13%.
- The certificate gives component-wise percentages of total proposed work, not one overall progress figure for the project.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 6 |
|---|
| By status | Online Complaint Not Yet Received At Office: 1; First Hearing: 4; Pending: 1 |
|---|
| Proceedings | - RERA-GRG-3021-2022: A complaint numbered RERA-GRG-3021-2022, listed as HARERA Gurugram against Vatika Ltd. The page gives no grounds or details of the complaint. Status: The page shows the online complaint as not yet received at the office. No next hearing date is set (shown as 'Not Yet'). The complaint listing and order details are empty. Dispatch details show 'NA'.
- RERA-GRG-3528-2022: Show cause notice to the promoter, Vatika Ltd, for not submitting a quarterly progress report. The Authority started this proceeding against the promoter. Status: First hearing listed for 27 Jun 2022. The page shows no order uploaded yet. Latest: 27 Jun 2022, First hearing was scheduled. The page shows the status as First Hearing, with no proceedings or order recorded.
- RERA-GRG-3809-2022: Show cause notice to Vatika Ltd for not applying to extend its registration, not submitting a completion, part completion or occupation certificate, and not submitting requisite documents. The registration certificate is recorded as expired. Status: First hearing listed for 28 Jun 2022. The case page shows status 'First Hearing' with no proceedings, bench order or uploaded order. Latest: 28 Jun 2022, First hearing was listed. The page shows no proceedings or order for this hearing.
- RERA-GRG-3810-2022: Show-cause notice to the promoter, Vatika Ltd, for not following the project completion period it declared under section 4(2)(l)(C) of the RERA Act. Status: First hearing stage. The next hearing is listed for 30 Jun 2022. Latest: 30 Jun 2022, First hearing listed. The case page shows no proceedings or order for this date.
- RERA-GRG-5081-2022: A complaint filed through the complainant against the promoter Vatika Ltd, listed for its first hearing before the Authority. The page shows the complainant as the party, not the Authority starting the case itself. Status: Listed for first hearing on 30 Jun 2022. The page shows no proceedings or order for that hearing. Latest: 16 Jul 2022, The complainant submitted documents under a Dak ID, marked as a new complaint.
- RERA-GRG-5305-2019: The Authority started this case itself against the promoter Vatika Ltd for not filing its quarterly progress reports (REP-I Part A to H) on the web portal for a project, and for not complying with notices. Status: Pending. The last recorded status is PENDING. The next hearing was listed for 24 Feb 2020. The page shows notices sent up to 03 Sep 2020, but no outcome of the 24 Feb 2020 hearing is recorded. Latest: 03 Sep 2020, Fifth notice, for compliance with section 42(1)(d), was sent and the case was dispatched. Penalty: Rs 25,000 per day from 31 Dec 2019 while the default continues, which may extend up to five percent of the estimated project cost. This was decided in the order dated 22 Jan 2020. No record of payment or final imposition is shown.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 17 |
|---|
| Cases | - RERA-GRG-4384-2024 (compensation, decided 07-Sep-2026): Buyers sought compensation for late possession; builder ordered to pay Rs 20.79 lakh with 11% interest.
- RERA-GRG-5596-2023 (compensation, decided 27-Mar-2026): Buyer paid Rs 58.59 lakh, no construction started; builder ordered to pay Rs 18.9 lakh compensation with 10.85% interest.
- RERA-GRG-888-2024 (compensation, decided 28-Jan-2026): Buyer sought compensation for delay and unpaid refund; builder ordered to pay Rs 59.2 lakh and Rs 1 lakh compensation.
- RERA-GRG-3989-2025 (complaint, decided 23-Dec-2025): Buyer sought refund after delayed possession; builder ordered to refund Rs 47.46 lakh with 10.80% interest.
- RERA-GRG-3990-2025 (complaint, decided 23-Dec-2025): Buyer sought refund after delayed possession; builder ordered to refund Rs 47.46 lakh with 10.80% interest.
- RERA-GRG-3994-2025 (complaint, decided 23-Dec-2025): Buyer sought refund after delayed possession; builder ordered to refund Rs 47.46 lakh with 10.80% interest.
- RERA-GRG-3995-2025 (complaint, decided 23-Dec-2025): Buyer sought refund after delayed possession; builder ordered to refund Rs 47.46 lakh with 10.80% interest.
- RERA-GRG-3992-2025 (complaint, decided 23-Dec-2025): Buyer sought refund after delayed possession; builder ordered to refund Rs 47.46 lakh with 10.80% interest.
- RERA-GRG-3993-2025 (complaint, decided 23-Dec-2025): Buyer sought refund after delayed possession; builder ordered to refund Rs 47.46 lakh with 10.80% interest.
- RERA-GRG-5786-2023 (compensation, decided 13-Nov-2025): Buyers sought compensation after the builder abandoned the project; Authority ordered Rs 1.31 crore compensation plus 10.5% interest.
- RERA-GRG-3165-2024 (complaint, decided 12-Aug-2025): Buyer sought refund after project stalled; builder ordered to refund Rs 31.11 lakh with 10.90% interest.
- RERA-GRG-2478-2023 (compensation, decided 30-Apr-2025): Buyers sought refund after delayed possession; builder ordered to pay Rs 7.5 lakh compensation with 10.50% interest.
- RERA-GRG-4918-2023 (complaint, decided 26-Mar-2025): Buyer sought refund after possession delay; builder ordered to refund Rs 70.24 lakh with 11.10% interest.
- RERA-GRG-2238-2023 (complaint, decided 07-Mar-2025): Buyer sought refund after possession delay and abandoned project; builder ordered to refund Rs 77.42 lakh with 11.10% interest.
- RERA-GRG-5985-2022 (complaint, decided 21-Aug-2024): Buyer sought correction of amount paid in earlier refund order; Authority corrected it to Rs 23.63 lakh, and the cheque was never encashed.
- RERA-GRG-1586-2021 (complaint, decided 06-Mar-2024): Buyer sought refund after possession delay; builder ordered to refund Rs 69.74 lakh with 10.85% interest.
- RERA-GRG-3327-2023 (complaint, decided 10-Jan-2024): Buyer sought refund after possession delay; builder ordered to refund Rs 35.48 lakh with 10.85% interest
|
|---|
| Decided cases against VATIKA LTD. (all its projects) | 961 (Execution of an earlier order: 43; Complaint: 333; Compensation: 24); breakdown of the latest 400 |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in