Trump Residences Gurgaon

Riverday Infrastructure · Sector 69, Gurugram

Registered with RERA: Mar 2025

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Riverday Infrastructure

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameTRUMP RESIDENCES GURGAON
Builder (promoter)RIVERDAY INFRASTRUCTURE PRIVATE LIMITED
LocationSECTOR 69
RERA project IDRERA-GRG-1850-2025
Registration certificate numberGGM/925/657/2025/28 DATED 13.03.2025
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/09/2032
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area0.633 acres
Licence90 of 2024 dated 18.07.2024
Estimated cost of the project₹1,91,771.48 lakh (₹1,917.71 crore)
Total units (plots, apartments, shops)298
Unit sizes (carpet area, as declared)8 units of 1,243 sq ft carpet (2 towers); 92 units of 1,657 sq ft carpet; 92 units of 2,106 sq ft carpet; 50 units of 2,632 sq ft carpet (2 towers); 50 units of 2,647 sq ft carpet; 2 units of 2,894 sq ft carpet (2 towers); 4 units of 3,877 sq ft carpet (2 towers)
Flat types (BHK), as stated by the builder1 BHK; 2 BHK; 2 BHK + store; 3 BHK; 3 BHK + utility; 4 BHK; 4 BHK + utility (source: the builder's floor plans uploaded to HRERA)
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on27-01-2025
Building plans approved on27-01-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-02-2025
Likely completion date30-04-2033

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on12-Oct-2026
Quarterly reports listed on the portal6

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹3,770.98 lakh (₹37.71 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹1,925.25 lakh (₹19.25 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹190.56 lakh (₹1.91 crore)
Project bank account (escrow): deposited in the quarter₹3,770.98 lakh (₹37.71 crore)
Project bank account (escrow): withdrawn in the quarter₹3,968 lakh (₹39.68 crore)
Project bank account (escrow): balance at quarter end₹101.69 lakh (₹1.02 crore)
Units in the project (apartments / plots)298 apartments
Sold in the quarter6 apartments
EDC (development charges): paid / due as on date₹3,201.74 lakh (₹32.02 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 27-01-2025
  • Zoning Plan: Obtained Approval 23-01-2025
  • Service Plans: Obtained Approval 10-03-2025
  • Electricity Plans: Obtained Approval 23-07-2024
  • Site Plans: Obtained Approval 27-01-2025
  • Building Plans: Obtained Approval 27-01-2025
  • Fire NOC: Obtained Approval 04-03-2025

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for 30 Sep 2025
By part
  • Sub-structure (2 towers, 298 residential units): 55%, Excavation started (98%), raft foundation started (100%), basement level 4 slabs (tower + NTA) at 55%, waterproofing started (30%)
  • Super-structure (2 towers, 298 residential units): 8%, Stilt/ground floor started (60%), slabs at 8% as per approved plans, walls, staircase and lift wells started, lift lobbies started
  • MEP (mechanical, electrical, plumbing and firefighting): 0%, Not started
  • Finishing (internal and external): 0%, Not started
Unclear in the certificate
  • The certificate date reads 30.09.2026 while the quarter ending is 30 Sep 2025; the year may be a typing or scanning error.
  • Table B common areas and services are all shown as 0% or not started, except parking and compound wall status is not clearly stated; no overall percentage is given in the document.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against RIVERDAY INFRASTRUCTURE PRIVATE LIMITED (all its projects)1 (Complaint: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in