Projects · OLIVE REALCON PVT. LTD. AND MANGLAM MULTIPLEX PVT LTD
Trump Towers Delhi Ncr
Olive Realcon Pvt. Ltd. And Manglam Multiplex · Sector 65, Gurugram
Registered with RERA: Nov 2017
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Dec 2024)
- HRERA has opened 4 cases of its own against the builder over this project (4 open):
- Did not submit quarterly progress report (May 2022, open)
- Quarterly reports not filed (Nov 2019, open)
- 2 more cases: reply 4
Will it be delivered on time?
- Deadline Dec 2024, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Quarterly progress report shown as "not uploaded" by HRERA
What's on offer?
- Flat types (BHK) as stated in the builder's registration form (Form A-H):
- 2 BHK: 254 units
Location
- Nearest metro: Sector 55–56, 5.8 km by road (19 min by car)
- Cyber City 43 min · Airport 61 min by car at 9:30 am
- Within 3 km: 10 hospitals, 20 schools, 7 malls
The builder: Olive Realcon Pvt. Ltd. And Manglam Multiplex
- 1 project registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 8 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | TRUMP TOWERS DELHI NCR |
|---|---|
| Builder (promoter) | OLIVE REALCON PVT. LTD. AND MANGLAM MULTIPLEX PVT LTD |
| Location | SECTOR 65, GURUGRAM, HARYANA |
| RERA project ID | RERA-GRG-601-2020 |
| Registration certificate number | 375 OF 2017 DATED 28.11.2017 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/12/2024 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 2.83125 acres |
| Licence | 234 of 2007 dated 16.10.2007 (54.61225 Acres) , 52 dated.28.08.2009 (0.4375 Acres) , 35 dated 6.05.2010 (1 Acre) |
| Estimated cost of the project | ₹1,88,013 lakh (₹1,880.13 crore) |
| Total units (plots, apartments, shops) | 254 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | 2 BHK: 254 units (source: the builder's registration form (Form A-H)) |
| Units booked when registered | 94 |
| Units unsold when registered | 160 |
| Layout plan approved on | 15-01-2018 |
| Building plans approved on | 15-01-2018 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 31-12-2024 |
|---|---|
| Revised completion date | 31-12-2024 |
| Infrastructure: projected completion | 31-12-2024 |
| Infrastructure: percentage complete when registered | 0.03% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against OLIVE REALCON PVT. LTD. AND MANGLAM MULTIPLEX PVT LTD (all its projects) | 8 (Complaint: 8) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in