Tulip Monsella And Tulip Attila

Tulip Infratech · Sector 53, Gurugram

Registered with RERA: Apr 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Tulip Infratech

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameTULIP MONSELLA AND TULIP ATTILA
Builder (promoter)TULIP INFRATECH PVT. LTD.
LocationSECTOR 53 GURUGRAM
RERA project IDRERA-GRG-966-2021
Registration certificate numberGGM/554/286/2022/29 DATED 25.04.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/12/2030
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area19.244 acres
Licence168 TO 172 OF 2004 AND 545-546 OF 2006
Estimated cost of the project₹3,02,077.02 lakh (₹3,020.77 crore)
Total units (plots, apartments, shops)1276
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder1 BHK: 4 units; 2 BHK + servant room: 4 units; 3 BHK + servant room: 777 units; 4 BHK + servant room + store: 144 units; 4 BHK + servant room + store + study: 4 units; 5 BHK: 2 units; 5 BHK + servant room: 146 units; 5 BHK + servant room + study: 4 units (source: the builder's registration form (Form A-H))
Units booked when registered278
Units unsold when registered998
Layout plan approved on28-10-2021
Building plans approved on13-04-2022

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-12-2029
Revised completion date31-12-2030
Infrastructure: projected completion31-12-2030
Infrastructure: percentage complete when registered5%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on14-Oct-2026
Quarterly reports listed on the portal17

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹7,215.22 lakh (₹72.15 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹4,955.51 lakh (₹49.56 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹1,219.76 lakh (₹12.2 crore)
Project bank account (escrow): deposited in the quarter₹5,050.65 lakh (₹50.51 crore)
Project bank account (escrow): withdrawn in the quarter₹4,300 lakh (₹43 crore)
Project bank account (escrow): balance at quarter end₹754.12 lakh (₹7.54 crore)
Units in the project (apartments / plots)1084 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹11,596.53 lakh (₹115.97 crore) paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 13-12-2022
  • Demarcation Plan: Obtained Approval 01-07-2014
  • Zoning Plan: Obtained Approval 06-08-2014
  • Service Plans: Obtained Approval 05-07-2022
  • Electricity Plans: Obtained Approval 05-07-2022
  • Site Plans: Obtained Approval 13-12-2022
  • Building Plans: Obtained Approval 13-12-2022
  • Fire NOC: Obtained Approval 09-06-2022

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 12 Oct 2026, for 30 Sep 2026
By part
  • Tower 1: Sub structure 100%. Super structure casting and reinforcement up to 39th floor 100%. Mechanical work in progress. Electrical conducting done till 39th floor. Plumbing and firefighting work in progress.
  • Tower 2: Sub structure 100%. Super structure casting and reinforcement up to 39th floor 100%. Mechanical work in progress. Electrical conducting done till 39th floor. Plumbing and firefighting work in progress.
  • Tower 3: Sub structure 100%. Super structure casting and reinforcement up to 39th floor 100%. Mechanical work in progress. Electrical conduiting done till 39th floor. Plumbing and firefighting work in progress.
  • Tower 4: Sub structure (excavation, PCC, foundation) 100%. Basement (Level 3) and water proofing 100%. Super structure casting and reinforcement up to 33rd floor 100%. Mechanical work in progress. Electrical conducting done till 33rd floor. Plumbing and firefighting work in progress.
Unclear in the certificate
  • Tower 5 has a table heading but no progress figures are visible in the document.
  • The certificate gives progress by component for each tower, not one overall percentage for the project or for each tower, so the overall and per-tower percentage fields are left blank.
  • The certificate's work-done-in-quarter figures are not stated as separate values; the table shows the same 100% for the cumulative and proposed work columns.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registration
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusPending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against TULIP INFRATECH PVT. LTD. (all its projects)10 (Complaint: 10)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026