Tulip Violet

Tulip Infratech · Sector 69 & 70, Gurugram

Registered with RERA: Jul 2025

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Tulip Infratech

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameTULIP VIOLET
Builder (promoter)TULIP INFRATECH PVT. LTD
LocationSECTOR 69 & 70
RERA project IDRERA-GRG-1939-2025
Registration certificate numberGGM/967/699/2025/70 DATED 03.07.2025
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/12/2032
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area7.64375 acres
Licence34 of 2024 (07-03-2024), 78 of 2010 (15-10-2010)
Estimated cost of the project₹34,528.44 lakh (₹345.28 crore)
Total units (plots, apartments, shops)215
Unit sizes (carpet area, as declared)30 units of 1,314 sq ft carpet (2 towers); 28 units of 1,315 sq ft carpet (2 towers); 3 units of 1,370 sq ft carpet (1 tower); 1 unit of 1,414 sq ft carpet (2 towers); 153 units of 1,863 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on20-02-2025
Building plans approved on20-02-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-07-2025
Likely completion date31-12-2032

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on14-Oct-2026
Quarterly reports listed on the portal4

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹346.63 lakh (₹3.47 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹173.23 lakh (₹1.73 crore)
Units in the project (apartments / plots)274 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹382 lakh (₹3.82 crore) paid; ₹0 due
Approvals listedNot found in the records checked

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 12 Oct 2026
By part
  • Tower A9 - Sub structure (excavation, basement slab and raft): 100%
  • Tower A9 - Super structure (casting and reinforcement): 50%, Casting and reinforcement up to Ground Floor
  • Tower A10 - Sub structure (excavation, basement slab and raft): 100%
  • Tower A10 - Super structure (casting and reinforcement): 100%, Casting and reinforcement up to 6th Floor
Unclear in the certificate
  • The certificate does not state the quarter it covers.
  • No single overall percentage of construction completed or work done in the quarter is given; only tower-wise percentages are shown.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project1
Cases
Decided cases against TULIP INFRATECH PVT. LTD (all its projects)10 (Complaint: 10)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in