Projects · TULIP INFRATECH PVT. LTD.

Tulip Yellow

Tulip Infratech · Sector 69, Gurugram

Registered with RERA: Nov 2019

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Tulip Infratech

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameTULIP YELLOW
Builder (promoter)TULIP INFRATECH PVT. LTD.
LocationSECTOR 69, VILLAGE BADSHAHPUR
RERA project IDRERA-GRG-292-2019
Registration certificate numberGGM/376/108/2019/70 DATED 14.11.2019
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/12/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area7.4583 acres
Licence16 of 2019 dated 09/02/2019
Estimated cost of the project₹37,916.23 lakh (₹379.16 crore)
Total units (plots, apartments, shops)744
Unit sizes (carpet area, as declared)112 units of 202 sq ft carpet (1 tower); 624 units of 1,034 sq ft carpet (6 towers); 6 units of 1,832 sq ft carpet (6 towers); 2 units of 2,130 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on01-10-2019
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-10-2019
Likely completion date31-12-2027

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/06/2026 (APR-JUN)
Latest report submitted on14-Jul-2026
Quarterly reports listed on the portal26

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2026 (APR-JUN))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹412.59 lakh (₹4.13 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹133.07 lakh (₹1.33 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹297.23 lakh (₹2.97 crore)
Project bank account (escrow): deposited in the quarter₹201.08 lakh (₹2.01 crore)
Project bank account (escrow): withdrawn in the quarter₹225 lakh (₹2.25 crore)
Project bank account (escrow): balance at quarter end₹39.11 lakh (₹0.39 crore)
Units in the project (apartments / plots)632 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹3,613.26 lakh (₹36.13 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 01-02-2019
  • Zoning Plan: Obtained Approval 09-02-2019
  • Service Plans: Obtained Approval 09-08-2019
  • Electricity Plans: Obtained Approval 20-02-2019
  • Site Plans: Obtained Approval 18-04-2019
  • Building Plans: Obtained Approval 18-04-2019
  • Fire NOC: Obtained Approval 18-06-2020

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 08 Jul 2026, for 30 Jun 2026
By part
  • Tower A-1 to A-4: 100%, Construction complete; occupation certificate granted by the Department of Town and Country Planning, Haryana
  • EWS Building: 100%, Construction complete; occupation certificate granted by the Department of Town and Country Planning, Haryana
  • Community Building: 100%, Construction complete; occupation certificate granted by the Department of Town and Country Planning, Haryana
  • Conv Block 2: 100%, Construction complete; occupation certificate granted by the Department of Town and Country Planning, Haryana
  • Tower A5 and A6: 100%, Construction complete; occupation certificate granted on 13 Feb 2026; developer has applied for completion certificate
Unclear in the certificate
  • Tables A and B, which the certificate says give the percentage of work for each tower and activity, are referred to but are not in the copy supplied. Percentages for other towers and activities cannot be confirmed.
  • The certificate gives no single overall percentage of construction complete or work done in the quarter.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed3
By statusScrutinized: 1; First Hearing: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project1
Cases
Decided cases against TULIP INFRATECH PVT. LTD. (all its projects)10 (Complaint: 10)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in