Turning Point ( Group Housing)

Vatika · Sector 88B, Gurugram

Registered with RERA: Sep 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for Sector 88B; the exact site was not found.

The builder: Vatika

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameTURNING POINT ( GROUP HOUSING)
Builder (promoter)VATIKA LTD
LocationSECTOR-88B, HARSARU, GURUGRAM
RERA project IDRERA-GRG-502-2019
Registration certificate number213 OF 2017 DATED 15.09.2017
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to15/02/2024
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area18.80 acres
Licence91 of 2013 Dated 26.10.2013
Estimated cost of the project₹34,895 lakh (₹348.95 crore)
Total units (plots, apartments, shops)703
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered99
Units unsold when registered604
Layout plan approved on01-05-2015
Building plans approved on01-05-2015

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date30-01-2025
Revised completion date30-01-2025
Infrastructure: projected completion30-01-2025
Infrastructure: percentage complete when registered0%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on02-Nov-2026
Quarterly reports listed on the portal32

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹1,907.99 lakh (₹19.08 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹3,819.15 lakh (₹38.19 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0.87 lakh (₹0.01 crore)
Units in the project (apartments / plots)703 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹1,176.15 lakh (₹11.76 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 18-06-2013
  • Zoning Plan: Obtained Approval 28-10-2013
  • Site Plans: Obtained Approval 01-09-2015
  • Building Plans: Obtained Approval 01-09-2015

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for 30 Sep 2026
By part
  • Phase-I - Substructure: 0.51%, Bulk excavation shown as 50% done. Raft foundation and basements 1 to 3 shown as 0% done. Waterproofing 0% done.
  • Phase-I - Super structure: 0%, No slabs cast yet. Walls, staircase, lift wells and lift lobbies shown as 0% done.
  • Phase-I - MEP (mechanical, electrical, plumbing and fire fighting): 0%, Shown as 0% done. Electrical and plumbing works within flats also 0%.
  • Phase-I - Finishing (internal and external): 0%, Plastering, tiling, flooring, painting and installations all shown as 0% done.
Unclear in the certificate
  • The certificate gives no single overall percentage of construction complete. Percentages in Table A are shares of total proposed work per component, not an overall figure.
  • Table A gives work done values (1877.99 for substructure) with no unit stated, so the amount cannot be confirmed.
  • Table A is headed 'Building/Tower no.' but only 'Phase-I' is entered, so no individual tower figures are given.
  • Table B, referred to in the certificate, is not included in the pages provided.
  • Under 'Total area on each floor' the figure 93588.71 appears, which is the registration area in square metres, not a floor figure.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed4
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 2; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project35
Cases
Decided cases against VATIKA LTD (all its projects)961 (Execution of an earlier order: 43; Complaint: 333; Compensation: 24); breakdown of the latest 400

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026