Ultimus 2.0
MRG World · Sector 90, Gurugram
Registered with RERA: Jan 2022
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Jul 2026)
- HRERA has opened 2 cases of its own against the builder over this project (2 open):
- Obtained fire scheme approval 25 days late; service estimates and plans not obtained on time (Oct 2022, open). At stake: Forfeiture of ₹10 lakh bank guarantee proposed; no final penalty recorded yet
- 1 more case: reply 4
Will it be delivered on time?
- Deadline Jul 2026, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Quarterly progress report shown as "not uploaded" by HRERA
What's on offer?
- Flat types (BHK) as stated in the builder's floor plans uploaded to HRERA:
- 2 BHK: 622–623 sq ft carpet
- 2 BHK + study: 646 sq ft carpet
Location
- Nearest metro: Millennium City Centre Gurugram, 20.1 km by road (53 min by car)
- Cyber City 60 min · Airport 44 min by car at 9:30 am
- Within 3 km: 0 hospitals, 1 school, 0 malls
Location shown for Sector 90; the exact site was not found.
The builder: MRG World
- 1 project registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 1 buyer complaint decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | ULTIMUS 2.0 |
|---|---|
| Builder (promoter) | MRG WORLD LLP |
| Location | SECTOR 90 GURUGRAM |
| RERA project ID | RERA-GRG-979-2021 |
| Registration certificate number | GGM/529/261/2022/04 DATED 31.01.2022 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 14/07/2026 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 5.2625 acres |
| Licence | 38 of 2021 |
| Estimated cost of the project | ₹21,247.66 lakh (₹212.48 crore) |
| Total units (plots, apartments, shops) | 769 |
| Unit sizes (carpet area, as declared) | 769 units averaging about 620 sq ft carpet (6 towers) |
| Flat types (BHK), as stated by the builder | 2 BHK: 622–623 sq ft carpet; 2 BHK + study: 646 sq ft carpet (source: the builder's floor plans uploaded to HRERA) |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 26-10-2021 |
| Building plans approved on | 26-10-2021 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 15-01-2022 |
|---|---|
| Likely completion date | 14-07-2026 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against MRG WORLD LLP (all its projects) | 1 (Complaint: 1) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in